Category:Status Report
MONTHYEARML24240A1692024-09-18018 September 2024 Cy 2023 Summary of Decommissioning Trust Fund Status L-24-007, Report on Status of Decommissioning Funding for Reactors and Independent Spent Fuel Storage Installations – Holtec Decommissioning International, LLC (HDI)2024-03-29029 March 2024 Report on Status of Decommissioning Funding for Reactors and Independent Spent Fuel Storage Installations – Holtec Decommissioning International, LLC (HDI) L-22-022, And Indian Point Nuclear Generating Stations 1, 2, & 3 - Report on Status of Decommissioning Funding for Reactors and Independent Spent Fuel Storage Installations - Holtec.2022-03-25025 March 2022 And Indian Point Nuclear Generating Stations 1, 2, & 3 - Report on Status of Decommissioning Funding for Reactors and Independent Spent Fuel Storage Installations - Holtec. L-21-134, And Indian Point Nuclear Generating Stations 1, 2, & 3 - Report on Status of Decommissioning Funding for Independent Spent Fuel Storage Installations2021-12-17017 December 2021 And Indian Point Nuclear Generating Stations 1, 2, & 3 - Report on Status of Decommissioning Funding for Independent Spent Fuel Storage Installations RS-17-045, Report on Status of Decommissioning Funding for Reactors and Independent Spent Fuel Storage Installations2017-03-30030 March 2017 Report on Status of Decommissioning Funding for Reactors and Independent Spent Fuel Storage Installations RS-16-046, Annual Property Insurance Status Report2017-03-29029 March 2017 Annual Property Insurance Status Report RA-16-065, Seventh Six-Month Status Report in Response to March 12, 2012 Commission Order Modifying Licenses with Regard to Requirements for Mitigation Strategies for Beyond-Design-Basis External Events (Order No. EA-12-049)2016-08-26026 August 2016 Seventh Six-Month Status Report in Response to March 12, 2012 Commission Order Modifying Licenses with Regard to Requirements for Mitigation Strategies for Beyond-Design-Basis External Events (Order No. EA-12-049) ML16239A0442016-08-26026 August 2016 Seventh Six-Month Status Report in Response to March 12, 2012 Commission Order Modifying Licenses with Regard to Reliable Spent Fuel Pool Instrumentation (Order Number EA-12-051) RS-16-094, Property Insurance Status Report for Braidwood Station, Byron Station, Calvert Cliffs, Clinton Power, Dresden Nuclear, LaSalle County, Limerick Generating, Nine Mile Point, Oyster Creek, Peach Bottom, Quad Cities, R.E Ginna, Three Mile Isl2016-04-25025 April 2016 Property Insurance Status Report for Braidwood Station, Byron Station, Calvert Cliffs, Clinton Power, Dresden Nuclear, LaSalle County, Limerick Generating, Nine Mile Point, Oyster Creek, Peach Bottom, Quad Cities, R.E Ginna, Three Mile Isla RA-16-011, Sixth Six-Month Status Report in Response to March 12, 2012 Commission Order Modifying Licenses with Regard to Reliable Spent Fuel Pool Instrumentation (Order Number EA-12-051)2016-02-26026 February 2016 Sixth Six-Month Status Report in Response to March 12, 2012 Commission Order Modifying Licenses with Regard to Reliable Spent Fuel Pool Instrumentation (Order Number EA-12-051) RA-16-010, Sixth Six-Month Status Report in Response to March 12, 2012 Commission Order Modifying Licenses with Regard to Requirements for Mitigation Strategies for Beyond-Design-Basis External Events (Order Number EA-12-049)2016-02-26026 February 2016 Sixth Six-Month Status Report in Response to March 12, 2012 Commission Order Modifying Licenses with Regard to Requirements for Mitigation Strategies for Beyond-Design-Basis External Events (Order Number EA-12-049) RA-15-066, Fifth Six-Month Status Report in Response to March 12, 2012 Commission Order Modifying Licenses with Regard to Reliable Spent Fuel Pool Instrumentation (Order Number EA-12-051)2015-08-28028 August 2015 Fifth Six-Month Status Report in Response to March 12, 2012 Commission Order Modifying Licenses with Regard to Reliable Spent Fuel Pool Instrumentation (Order Number EA-12-051) RA-15-065, Fifth Six-Month Status Report in Response to March 12, 2012 Commission Order Modifying Licenses with Regard to Requirements for Mitigation Strategies for Beyond-Design-Basis External Events (Order Number EA-12-049)2015-08-28028 August 2015 Fifth Six-Month Status Report in Response to March 12, 2012 Commission Order Modifying Licenses with Regard to Requirements for Mitigation Strategies for Beyond-Design-Basis External Events (Order Number EA-12-049) RA-15-009, Fourth Six-Month Status Report in Response to March 12, 2012 Commission Order Modifying Licenses with Regard to Reliable Spent Fuel Pool Instrumentation (Order Number EA-12-051)2015-02-27027 February 2015 Fourth Six-Month Status Report in Response to March 12, 2012 Commission Order Modifying Licenses with Regard to Reliable Spent Fuel Pool Instrumentation (Order Number EA-12-051) RA-14-052, Third Six-Month Status Report in Response to March 12, 2012 Commission Order Modifying Licenses with Regard to Reliable Spent Fuel Pool Instrumentation (Order Number EA-12-051)2014-08-28028 August 2014 Third Six-Month Status Report in Response to March 12, 2012 Commission Order Modifying Licenses with Regard to Reliable Spent Fuel Pool Instrumentation (Order Number EA-12-051) RA-14-002, Second Six-Month Status Report in Response to March 12, 2012 Commission Order Modifying Licenses with Regard to Requirements for Mitigation Strategies for Beyond-Design-Basis External Events (EA-12-049)2014-02-28028 February 2014 Second Six-Month Status Report in Response to March 12, 2012 Commission Order Modifying Licenses with Regard to Requirements for Mitigation Strategies for Beyond-Design-Basis External Events (EA-12-049) RA-13-050, First Six-Month Status Report in Response to March 12, 2012 Commission Order Modifying Licenses with Regard to Reliable Spent Fuel Pool Instrumentation (Order Number EA-12-051)2013-08-28028 August 2013 First Six-Month Status Report in Response to March 12, 2012 Commission Order Modifying Licenses with Regard to Reliable Spent Fuel Pool Instrumentation (Order Number EA-12-051) RA-13-051, First Six-Month Status Report in Response to March 12,2012 Commission Order Modifying Licenses with Regard to Requirements for Mitigation Strategies for Beyond-Design-Basis External Events (Order Number EA-12-049)2013-08-28028 August 2013 First Six-Month Status Report in Response to March 12,2012 Commission Order Modifying Licenses with Regard to Requirements for Mitigation Strategies for Beyond-Design-Basis External Events (Order Number EA-12-049) RS-13-125, First Six-Month Status Report in Response to March 12,2012 Commission Order Modifying Licenses with Regard to Requirements for Mitigation Strategies for Beyond-Design-Basis External Events (Order Number EA-12-049)2013-08-28028 August 2013 First Six-Month Status Report in Response to March 12,2012 Commission Order Modifying Licenses with Regard to Requirements for Mitigation Strategies for Beyond-Design-Basis External Events (Order Number EA-12-049) RA-13-030, Annual Property Insurance Status Report2013-04-0101 April 2013 Annual Property Insurance Status Report RS-13-100, Report on Status of Decommissioning Funding for Reactors2013-04-0101 April 2013 Report on Status of Decommissioning Funding for Reactors RA-12-032, Annual Property Insurance Status Report2012-03-30030 March 2012 Annual Property Insurance Status Report ML1009200492010-04-0101 April 2010 Annual Property Insurance Status Report ML0919606022009-06-17017 June 2009 Commitment Inspection Per IP 71003 - App. C Mc 2515, Infrequent Procedures Status and Next Steps, Rev. 4, as of 12/02/2008 ML0919606082009-06-17017 June 2009 Commitment Inspection Per IP 71003 - App. C Mc 2515, Infrequent Procedures Status and Next Steps (as of 12/18/2008) ML0919606072009-06-17017 June 2009 Commitment Inspection Per IP 71003 - App. C Mc 2515, Infrequent Procedures Status and Next Steps (as of 12/18/2008) ML0919606052009-06-17017 June 2009 Commitment Inspection Per IP 71003 - App. C Mc 2515, Infrequent Procedures Status and Next Steps, Rev 4, with Handwritten Notes (as of 12/10/2008) ML0919606002009-06-17017 June 2009 Commitment Inspection Per IP 71003 - App. C Mc 2515, Infrequent Procedures Status and Next Steps, Rev. 4, as of 12/02/2008 ML0919606012009-06-17017 June 2009 Commitment Inspection Per IP 71003 - App. C Mc 2515, Infrequent Procedures Status and Next Steps, Rev. 4, as of 12/02/2008, with Handwritten Notes ML0919606032009-06-17017 June 2009 Commitment Inspection Per IP 71003 - App. C Mc 2515, Infrequent Procedures Status and Next Steps, Rev 4, (as of 12/10/2008), with Handwritten Notes ML0909202562009-04-0101 April 2009 Annual Property Insurance Status Report RS-09-041, Submittal of Exelon Generation Company, LLC, Report on Status of Decommissioning Funding for Reactors Owned by EGC2009-03-31031 March 2009 Submittal of Exelon Generation Company, LLC, Report on Status of Decommissioning Funding for Reactors Owned by EGC ML0917005242008-12-10010 December 2008 E-mail from R. Conte of USNRC to Various, Regarding Oc Exit Meeting Next Steps ML0634502502006-12-19019 December 2006 November 2006 Report on the Status of Public Petitions Under Title 10 of the Code of Federal Regulations, Section 2.206 ML0607504022006-02-17017 February 2006 E-mail: Fwd: Status of Oyster Creek LRA Draft RAIs (PD) ML0508703272005-03-25025 March 2005 Annual Property Insurance Status Report RS-05-035, Report on Status of Decommissioning Funding for Reactors2005-03-24024 March 2005 Report on Status of Decommissioning Funding for Reactors ML0713401622003-08-21021 August 2003 Post Strike Monitoring Activities - Updated 8/21/03 ML0713401502003-08-0707 August 2003 Strike Monitoring Activities - Updated 8/07/03 ML0713401492003-07-31031 July 2003 Strike Monitoring Activities - Updated 7/31/03 ML0713401462003-07-25025 July 2003 Strike Monitoring Activities - Updated 7/25/03 ML0726703681978-12-31031 December 1978 Jersey Central Power & Light Company. 1978. Oyster Creek and Forked River Nuclear Generating Stations 316(a) and (B) Demonstration, Seventh Progress Report, June 25, 1971, Through Eighth Progress Report, August 18, 1972 2024-09-18
[Table view] |
Text
OYSTER CREEK STRIKE MONITORING ACTIVITIES - UPDATED 7/31/03 (Updated info - complete revision from prior paper)
Overview The Oyster Creek strike is into its third month, now at day 71. A great deal of progress has been made during negotiating discussions this week. The next negotiation meeting is scheduled for August 4, 2003. All control room operator positions are being staffed with current SROs, using a three crew, 12-hour/shift schedule. The operators remain on a "4 on 2 off" shift rotation. Other departments (maint., I&C, Rad Pro) have gone to a "5 - 10 hour1.157407e-4 days <br />0.00278 hours <br />1.653439e-5 weeks <br />3.805e-6 months <br /> day" schedule with weekends off. EP and Fire Brigade staffing are still being maintained at proper levels on back shifts and weekends.
As of 7/31/03, 13 non-licensed operators, 2 chemistry technicians and four clerks have crossed the picket line to rejoin the plant workforce. There are strong rumors that an additional 15 staff may return to work on August 4, including 10 non-licensed operators and 5 licensed operators.
Modified requal training for the SROs, as well as initial fire brigade training for on-site staff, has been initiated with NRC direct observation of the licensed operator requalification training. The return of the 13 non-licensed operators and the completion of initial fire brigade training for on-site staff has allowed the operations department to commence scheduling leave for the senior licensed operators who have been working since the strike began, as well as facilitated increasing the requalification training, so that evaluative training has commenced. This leave schedule has reduced some burden on the operating staff.
The resident inspectors are working a normal, first-forty schedule with weekend and backshift coverage for significant plant evolutions or emergent work. DRS has provided support in observing the modified licensed operator requalification training. Region I senior management continue to discuss site performance observations on a weekly basis and have had frequent site visits (about once every two weeks).
Current Overall Assessment Today is day 71 of the strike. The most recent negotiating session resulted in significant progress toward settlement. Most of the 19 disputed elements in the contract have been successfully agreed upon. The state mediator has asked both parties to take several days off to consider various options on the remaining points and has scheduled the next meeting for Monday, August 4.
The inspectors have noted no issues indicating fatigue or lack of knowledge. The inspectors and regional management spoke to numerous engineering, maintenance, and ops staff and none have expressed that fatigue is a concern at this time.
There have been no significant performance issues identified by either NRC or company oversight since the normal staff went on strike. No PMs or required STs have been missed. In addition, the station management have been exceeding planned work-off goals for all station work backlogs. Company management are well aware that some activities have been delayed or deferred and they have committed to conducting an aggregate impact evaluation to ensure that the decision to delay certain activities was appropriate.
The resident inspectors have the following concerns:
(1) Fatigue - while there's been no evidence of fatigue and considering that some leave schedule has occurred, we are still concerned that fatigue may lead to human errors. The residents will continue to closely monitor performance for evidence of fatigue. The plant has been relying upon a supplement of staff of about 30 people from Peach Bottom, Limerick, and TMI to assist the plant management and professional staff in maintaining operations. Many of these individuals will be needed at their normal sites during the fall to support planned refueling outages. The residents are concerned that if a settlement is not reached prior to end of September, that Exelon will have to provide and train additional supplemental support staff to replace the current staff. This action could increase the probability of knowledge or fatigue-based errors if not managed appropriately.
(2) LORT - (a) Modified Requal training for the on-site SROs has been observed by both resident and DRS staff. The training appears effective, although some individual performance weaknesses have been identified. The inspectors have agreed that remediation actions taken for these individuals were appropriate. (b) The resident inspectors have reviewed the draft training program to be implemented for operations staff once the strike ends. The ROs will have to stand a 40 hour4.62963e-4 days <br />0.0111 hours <br />6.613757e-5 weeks <br />1.522e-5 months <br /> proficiency watch - currently they are planning to complete this by assigning 3 ROs/shift. This is an unusual condition, since normally a proficiency watch is conducted one-on-one and typically involves a single individual at a time. (c) If striking operators do not return before October, Exelon will need to gain additional exemption from the LORT requirements (currently extended to 12/31/03) for those ROs. The plant would still intend to use these ROs on shift prior to completing the examination process as long as all proficiency and requal training is up-to-date.
(3) CAP Backlog - an action request backlog and CAP response backlog is slowly building due to the shuffling of engineering personnel to support operations and maintenance. The backlog has not yet manifested itself into any significant issues. Exelon management are aware of this and other delayed/deferred work, which will be evaluated for the impact to the station. DRS will conduct a mini-PI&R review on August 11 and 18 to evaluate the CAP implementation.
(4) EP - the resident and regional inspectors observed portions of a emergency preparedness practice drill on July 30. No significant weaknesses were observed and JIC performance was improved. FEMA has had some difficulty in resolving scenario comments for the upcoming evaluated exercise in September. R. Bores and N. McNamara have been coordinating resolution of this concern. The State of NJ DEP has not allowed its union employees to cross the strike line. If the strike continues through the exercise date, Exelon legal has determined that the rented facility used for the EOF/JIC could be picketed by the IBEW. In that case it's not clear whether responding state personnel would be permitted access to the EOF/JIC.
(5) Re-integration - the resident inspectors have not reviewed the re-integration plan. We are concerned about possible problem with merging the management and union staff following such a long, contentious labor action. Resident inspectors are developing the inspection plan per IP 92712 to be implemented when the strike is settled.