NRC CY2006 Annual Assessment Meeting CRYSTAL RIVER Crystal River, Florida Crystal River, Florida April 18, 2007 April 18, 2007

Purpose of Todays Meeting

    • A public forum for discussion of Crystal River A public forum for discussion of Crystal River performance performance
    • NRC will address Crystal River performance issues NRC will address Crystal River performance issues identified in the annual assessment letter identified in the annual assessment letter
    • Crystal River management will be given the opportunity Crystal River management will be given the opportunity to respond to the information in the letter and inform the to respond to the information in the letter and inform the NRC of new or existing programs to maintain or NRC of new or existing programs to maintain or improve their performance improve their performance

Agenda

  • Introduction
  • Review of Reactor Oversight Process
  • National Summary of Plant Performance
  • Discussion of Crystal River Plant Performance Results
  • Crystal River Management Response and Remarks
  • NRC Closing Remarks
  • Break
  • NRC Available to Address Public Questions

Region II Organization William Travers Regional Administrator Victor McCree Deputy Regional Administrator Charles Casto Director Division of Reactor Projects Harold Christensen Deputy Director Joseph Shea Director Division of Reactor Safety Kriss Kennedy Deputy Director Michael Ernstes Branch Chief Regional Specialists Crystal River Resident Inspectors Thomas Morrissey Rogerio Reyes Project Engineer Son Ninh

NRC Performance Goals Ensure protection of the public health and safety and the environment Ensure the secure use and management of radioactive materials PRIMARY GOALS OTHER GOALS

  • Ensure openness in NRC regulatory process
  • Ensure that NRC actions are effective, efficient, realistic, and timely
  • Ensure excellence in NRC management to carry out the NRCs strategic objective

Reactor Oversight Process Safety Cornerstones Baseline Inspection Results Significance Threshold Action Matrix Significance Threshold Performance Indicator Results Regulatory Response Strategic Performance Areas Safety Cornerstones Baseline Inspection Results Significance Threshold Action Matrix Significance Threshold Performance Indicator Results Regulatory Response Strategic Performance Areas

Examples of Baseline Inspections z Equipment Alignment

~80 hrs/yr z Triennial Fire Protection

~200 hrs every 3 yrs z Operator Response

~125 hrs/yr z Emergency Preparedness

~80 hrs/yr z Rad Release Controls

~110 hrs every 2 yrs z Worker Radiation Protection ~90 hrs/yr z Corrective Action Program

~250 hrs every 2 yrs z Corrective Action Case Reviews ~60 hrs/yr

Performance Thresholds Safety Significance Green:

Very low safety issue White:

Low-to-moderate safety issue Yellow:

Substantial safety issue Red:

High safety issue NRC Inspection Efforts Green:

Only Baseline Inspections White:

May increase NRC oversight Yellow:

Increased NRC oversight Red:

Increased NRC oversight and other NRC actions

Action Matrix Concept Licensee

Response

Regulatory

Response

Degraded Cornerstone Multiple/Rep.

Degraded Cornerstone Unacceptable Performance Increasing Safety Significance Increasing NRC Inspection Efforts Increasing NRC/Licensee Management Involvement Increasing Regulatory Actions

National Summary of Plant Performance Status at End of CY2006 Licensee Response 70 Regulatory Response 24 Degraded Cornerstone 6

Multiple/Repetitive Degraded Cornerstone 3

Unacceptable 0

Total 103

Crystal River CY2006 Inspection Activities

  • 4268 hours0.0494 days <br />1.186 hours <br />0.00706 weeks <br />0.00162 months <br /> of inspection related activities
  • Resident inspector daily inspections
  • 95001 supplemental inspection
  • Problem identification and resolution inspection
  • Heat sink inspection
  • Radiation protection inspection
  • Modifications/10 CFR 50.59 inspection

Crystal River CY2006 Assessment Results Crystal Rivers performance was within the Licensee Response Column of the NRCs Action Matrix for the third and fourth quarters of CY2006.

Crystal Rivers performance was within the Regulatory Response column in the first and second quarters of CY2006 due to a White inspection finding in the Mitigating System Cornerstone (Fire Protection) originating in the third quarter of CY2005. A supplemental inspection was completed in January 2006 and no findings of significance were identified.

All Unit 3 inspection findings were classified as very low safety significance (Green).

All performance indicators were Green.

Crystal River Assessment Summary

  • Progress Energy operated Crystal River in a manner that preserved public health and safety.
  • All cornerstone objectives were met.
  • NRC plans baseline inspections at Crystal River for the remainder of CY2007.

Crystal River CY2007 Scheduled Inspection Activities

  • Resident inspector daily inspections
  • Component design bases inspection
  • PWR containment sump blockage inspection
  • Radiation protection inspections
  • Inservice inspections

NRC CY2006 NRC CY2006 Annual Assessment Meeting Annual Assessment Meeting CRYSTAL RIVER Crystal River, Florida April 18

Contacting the NRC z Report an emergency (301) 816-5100 (call collect) z Report a safety concern:

(800) 695-7403 Allegation@nrc.gov z General information or questions www.nrc.gov Select What We Do for Public Affairs

Reference Sources z Reactor Oversight Process http://www.nrc.gov/NRR/OVERSIGHT/ASSESS/index.html z Public Electronic Reading Room http://www.nrc.gov/reading-rm.html z Public Document Room 1-800-397-4209 (Toll Free)