April 25, 2007 Mr. Theodore A. Sullivan Site Vice President Entergy Nuclear Operations, Inc.
Vermont Yankee Nuclear Power Station P.O. Box 0500 185 Old Ferry Road Brattleboro, VT 05302-0500
SUBJECT:
OPERATOR LICENSING EXAMINATION APPROVAL VERMONT YANKEE NUCLEAR POWER STATION
Dear Mr. Sullivan:
The purpose of this letter is to confirm the final arrangements for the upcoming operator licensing examinations at the Vermont Yankee Nuclear Power Station.
The NRC has completed its review of the operator license applications submitted in connection with this examination and separately provided a list of approved applicants to Mr. M. Romeo, Operations Training Superintendent.
The NRC has approved the subject examinations and hereby authorizes you to administer the written examinations in accordance with Revision 9 of NUREG-1021, Operator Licensing Examinations Standards for Power Reactors, on April 27, 2007. The NRC staff will administer the operating tests during the weeks of April 30 and May 7, 2007.
Please contact your Chief Examiner, Todd Fish, at 610-337-5369, if you have any questions or identify any errors or changes in the license level (RO or SRO) or type of examination (partial or complete written examination and/or operating test) specified for each applicant.
Sincerely,
/RA/
Marvin D. Sykes, Chief Operations Branch Division of Reactor Safety Docket No. 50-271 License No. DPR-28
Mr. Theodore A. Sullivan Site Vice President Entergy Nuclear Operations, Inc.
Vermont Yankee Nuclear Power Station P.O. Box 0500 185 Old Ferry Road Brattleboro, VT 05302-0500
SUBJECT:
OPERATOR LICENSING EXAMINATION APPROVAL VERMONT YANKEE NUCLEAR POWER STATION
Dear Mr. Sullivan:
The purpose of this letter is to confirm the final arrangements for the upcoming operator licensing examinations at the Vermont Yankee Nuclear Power Station.
The NRC has completed its review of the operator license applications submitted in connection with this examination and separately provided a list of approved applicants to Mr. M. Romeo, Operations Training Superintendent.
The NRC has approved the subject examinations and hereby authorizes you to administer the written examinations in accordance with Revision 9 of NUREG-1021, Operator Licensing Examinations Standards for Power Reactors, on April 27, 2007. The NRC staff will administer the operating tests during the weeks of April 30 and May 7, 2007.
Please contact your Chief Examiner, Todd Fish, at 610-337-5369, if you have any questions or identify any errors or changes in the license level (RO or SRO) or type of examination (partial or complete written examination and/or operating test) specified for each applicant.
Sincerely,
/RA/
Marvin D. Sykes, Chief Operations Branch Division of Reactor Safety Docket No. 50-271 License No. DPR-28 SUNSI Review Complete: MDS (Reviewers Initials)
ADAMS PKG: ML062050096 ML071150479 DOCUMENT NAME: C:\\FileNet\\ML071150479.wpd After declaring this document An Official Agency Record it will be released to the Public.
To receive a copy of this document, indicate in the box: "C" = Copy without attachment/enclosure "E" = Copy with attachment/enclosure "N" = No copy OFFICE RI/DRS/OB RI/DRS/OB RI/DRS/OB NAME CJBixler/TFish for TFish/THF MDSykes/MDS DATE 04/23/07 04/23/07 04/25/07 OFFICIAL RECORD COPY
2 cc:
M. R. Kansler, President, Entergy Nuclear Operations, Inc.
G. J. Taylor, Chief Executive Officer, Entergy Operations J. T. Herron, Senior Vice President M. Balduzzi, Senior Vice President, Northeastern Regional Operations C. Schwarz, Vice-President, Operations Support O. Limpias, Vice President, Engineering D. Mannai, Manager, Licensing, Vermont Yankee Nuclear Power Station Operating Experience Coordinator, Vermont Yankee Nuclear Power Station W. Maguire, General Manager, Plant Operations, Entergy Nuclear Operations, Inc.
N. Rademacher, Director, Engineering, Vermont Yankee Nuclear Power Station J. F. McCann, Director, Licensing C. D. Faison, Manager, Licensing M. J. Colomb, Director of Oversight, Entergy Nuclear Operations, Inc.
Assistant General Counsel, Entergy Nuclear Operations, Inc.
J. H. Sniezek, PWR SRC Consultant M. D. Lyster, PWR SRC Consultant S. Lousteau, Treasury Department, Entergy Services, Inc.
D. O Dowd, Administrator, Radiological Health Section, DPHS, DHHS, State of New Hampshire W. Irwin, Chief, CHP, Radiological Health, Vermont Department of Health Chief, Safety Unit, Office of the Attorney General, Commonwealth of Mass.
D. Lewis, Pillsbury, Winthrop, Shaw, Pittman LLP G. D. Bisbee, Esquire, Deputy Attorney General, Environmental Protection Bureau J. Block, Esquire J. P. Matteau, Executive Director, Windham Regional Commission D. Katz, Citizens Awareness Network (CAN)
R. Shadis, New England Coalition Staff G. Sachs, President/Staff Person, c/o Stopthesale J. Volz, Chairman, Public Service Board, State of Vermont Chairman, Board of Selectman, Town of Vernon State of New Hampshire, SLO Designee State of Vermont, SLO J. Giarrusso, SLO, MEMA, Commonwealth of Massachusetts M. Desilets, Manager - Training and Development
3 Distribution: (via e-mail)
S. Collins, RA M. Dapas, DRA R. Powell, DRP B. Bickett, DRP J. Lamb, RI OEDO M. Kowal, NRR J. Lubinski, NRR J. Kim, PM, NRR J. Boska, Backup PM, NRR D. Pelton, DRP, Senior Resident Inspector B. Sienel, DRP, Resident Inspector A. Rancourt, DRP, Resident OA Region I Docket Room (with concurrences)
ROPreports@nrc.gov (All IRs)
T. Fish, DRS, Chief Examiner M. Sykes, DRS Distribution:
DRS Master Exam File (C. Bixler) (w/concurrences)