Technical Specification Page Correction of Administrative Error in Amendment No. 298, Steam Generator Tube Integrity
ML071010097
Person / Time
Site: Cook American Electric Power icon.png
Issue date: 04/06/2007
From:
NRC/NRR/ADRO/DORL/LPLIII-1
To:
tam P, NRR/ADRO/DORL, 415-1451
Shared Package
ML071010023 List:
References
TAC MD2306
Download: ML071010097 (1)


Text

RCS Operational LEAKAGE 3.4.13 ACTIONS (continued)

CONDITION REQUIRED ACTION COMPLETION TIME C. Identified LEAKAGE not C.1 Reduce LEAKAGE to within 4 hours4.62963e-5 days <br />0.00111 hours <br />6.613757e-6 weeks <br />1.522e-6 months <br /> within limits for reasons limits.

other than primary to secondary LEAKAGE.

D. Required Action and D.1 Be in MODE 3.

6 hours6.944444e-5 days <br />0.00167 hours <br />9.920635e-6 weeks <br />2.283e-6 months <br /> associated Completion Time of Condition A, B, AND or C not met.

D.2 Be in MODE 5.

36 hours4.166667e-4 days <br />0.01 hours <br />5.952381e-5 weeks <br />1.3698e-5 months <br /> OR Pressure boundary LEAKAGE exists.

OR Primary to secondary LEAKAGE not within limit.

SURVEILLANCE REQUIREMENTS SURVEILLANCE FREQUENCY SR 3.4.13.1


NOTES--------------

1. Not required to be performed until 12 hours1.388889e-4 days <br />0.00333 hours <br />1.984127e-5 weeks <br />4.566e-6 months <br /> after establishment of steady state operation.
2.

Not applicable to primary to secondary LEAKAGE.

Verify RCS operational LEAKAGE is within limits by 72 hours8.333333e-4 days <br />0.02 hours <br />1.190476e-4 weeks <br />2.7396e-5 months <br /> performance of RCS water inventory balance.

Cook Nuclear Plant Unit 1 3.4.13-2 Amendment No. 28-7, 298 Corrected by letter of 4/6/07