MONTHYEARML0702601702007-02-0909 February 2007 RAI Related to Revising Mode 4 Residual Heat Removal Shutdown Requirements Project stage: RAI ML0710001542007-03-30030 March 2007 Response to a Request for Additional Information on a License Amendment Request to Revise Mode 4 Residual Heat Removal Shutdown Cooling Requirements Project stage: Response to RAI ML0717805082007-06-19019 June 2007 Withdrawal of Two License Amendment Requests Associated with Mode 3 & 4 Residual Heat Removal (RHR) Shutdown Cooling Requirements Project stage: Withdrawal ML0717105702007-06-25025 June 2007 Withdrawal of Amendment Request Associated with RHR Shutdown Cooling Requirements Project stage: Withdrawal ML0717105892007-06-26026 June 2007 Withdrawal of Amendment Request Associated with Mode 4 Residual Heat Removal (RHR) Shutdown Cooling Requirements Project stage: Withdrawal 2007-06-19
[Table View] |
Similar Documents at Perry |
---|
Category:Letter
MONTHYEARL-24-226, License Renewal Application for the Perry Nuclear Power Plant Revision O - Response to Requests for Confirmatory Information (Rcls) - Set 12024-10-31031 October 2024 License Renewal Application for the Perry Nuclear Power Plant Revision O - Response to Requests for Confirmatory Information (Rcls) - Set 1 IR 05000440/20240032024-10-30030 October 2024 Integrated Inspection Report 05000440/2024003 and 07200069/2024001 L-24-179, License Renewal Application for the Perry Nuclear Power Plant Revision 0 - Supplement 52024-10-21021 October 2024 License Renewal Application for the Perry Nuclear Power Plant Revision 0 - Supplement 5 L-24-208, License Renewal Application for the Perry Nuclear Power Plant - Responses to Request for Additional Information - Round 1 (Set 2)2024-10-0202 October 2024 License Renewal Application for the Perry Nuclear Power Plant - Responses to Request for Additional Information - Round 1 (Set 2) ML24134A1522024-09-17017 September 2024 Exemption from the Requirements of 10 CFR 50.71(e)(4) Final Safety Analysis Report Update Schedule (EPID L-2024-LLE-0005) - Letter L-24-207, License Renewal Application for the Perry Nuclear Power Plant-Response to Request for Additional Information - Set 12024-09-16016 September 2024 License Renewal Application for the Perry Nuclear Power Plant-Response to Request for Additional Information - Set 1 ML24225A0512024-09-13013 September 2024 Issuance of Alternative Request VR-9, Revision 0, Associated with the Fourth 10-Year Inservice Testing Interval ML24256A0872024-09-11011 September 2024 Fws to NRC, Concurrence with Endangered Species Act Nlaa Determinations for Perry License Renewal L-24-201, Spent Fuel Storage Cask Registration2024-09-0909 September 2024 Spent Fuel Storage Cask Registration ML24249A0862024-09-0606 September 2024 Letter to Regina Gasco-Bentley, Chairperson_ Re. NOA of the Draft Site-Specific EIS and Finding of No Historic Properties Affected by Perry Plant Unit 1 Lr ML24166A0172024-09-0606 September 2024 Ltr. to Glenna Wallace, Chief, Eastern Shawnee Tribe of Oklahoma; Re., NOA of the Draft Site-Specific EIS and Finding of No Historic Properties Affected by Perry Plant Unit 1 Lr ML24249A0782024-09-0606 September 2024 Ltr. to Kenneth Meshigaud, Chairperson, _ Re., NOA of the Draft Site-Specific EIS and Finding of No Historic Properties Affected by Perry Plant Unit 1 Lr ML24249A0752024-09-0606 September 2024 Letter to Charles Diebold, Chief_ Re. NOA of the Draft Site-Specific EIS and Finding of No Historic Properties Affected by Perry Plant Unit 1 Lr ML24247A0212024-09-0606 September 2024 NRC Request for Concurrence with Endangered Species Act Determinations for Perry License Renewal, Issuance of Draft Supplemental Environmental Impact Statement, and Opportunity for Public Comment (Consultation Code: 2024-0006782) ML24249A0882024-09-0606 September 2024 Letter to Rickey Armstrong, President_ Re. NOA of the Draft Site-Specific EIS and Finding of No Historic Properties Affected by Perry Plant Unit 1 Lr ML24250A0412024-09-0606 September 2024 Fws to NRC, Perry Nuclear Plant, Unit 1, License Renewal List of Threatened and Endangered Species That May Occur in Your Proposed Project Location or May Be Affected ML24249A0762024-09-0606 September 2024 Letter to Douglas Lankford, Chief_ Re. NOA of the Draft Site-Specific EIS and Finding of No Historic Properties Affected by Perry Plant Unit 1 Lr L-24-200, License Renewal Application for Revision to Supplement 4 for Editorial Corrections2024-09-0505 September 2024 License Renewal Application for Revision to Supplement 4 for Editorial Corrections ML24228A1702024-09-0303 September 2024 Ltr to Rod L. Penfield-Perry Nuclear Power Plant Unit 1-Notice of Avail of the Draft Supp 61 to the GEIS for License Renew of Nuclear Plants ML24228A1712024-09-0303 September 2024 Ltr to Brian Dickens, EPA-Perry Nuclear Power Plant Unit 1-Notice of Avail of the Draft Supp 61 to the GEIS for License Renew of Nuclear Plants L-24-188, Submittal of Quality Assurance Program Manual, Revision 302024-08-27027 August 2024 Submittal of Quality Assurance Program Manual, Revision 30 ML24240A1482024-08-27027 August 2024 Notification of an NRC Biennial Licensed Operator Requalification Program Inspection and Request for Information ML24239A7782024-08-26026 August 2024 Aging Management Audit - Perry Unit 1 - License Renewal Application August 26 2024 L-24-190, Spent Fuel Storage Cask Registration2024-08-26026 August 2024 Spent Fuel Storage Cask Registration IR 05000440/20240052024-08-22022 August 2024 Updated Inspection Plan for Perry Nuclear Power Plant (Report 05000440/2024005) L-24-174, Response to Perry Nuclear Power Plant License Renewal Environmental Report Severe Accident Mitigation Alternatives 2nd Round Request for Additional Information2024-08-15015 August 2024 Response to Perry Nuclear Power Plant License Renewal Environmental Report Severe Accident Mitigation Alternatives 2nd Round Request for Additional Information L-24-186, Response to RAI for Exemption Request from 10 CFR 50.71(e)(4) Final Safety Analysis Update Schedule2024-08-15015 August 2024 Response to RAI for Exemption Request from 10 CFR 50.71(e)(4) Final Safety Analysis Update Schedule IR 05000440/20240022024-08-0808 August 2024 Integrated Inspection Report 05000440/2024002 L-24-178, License Renewal Application Revision O - Supplement 42024-08-0808 August 2024 License Renewal Application Revision O - Supplement 4 L-24-189, License Renewal Application for Revision O - Supplement 12024-08-0707 August 2024 License Renewal Application for Revision O - Supplement 1 L-24-171, Spent Fuel Storage Cask Registration2024-07-30030 July 2024 Spent Fuel Storage Cask Registration ML24150A2022024-07-25025 July 2024 Letter to Rod L. Penfield-Perry Nuclear Power Plant Unit 1-License Renewal Scoping Summary Rpt L-24-108, License Renewal Application, Revision 0 - Supplement 32024-07-24024 July 2024 License Renewal Application, Revision 0 - Supplement 3 05000440/LER-2024-003, Technical Specification Required Shutdown Due to Increase in RCS Unidentified Leakage2024-07-15015 July 2024 Technical Specification Required Shutdown Due to Increase in RCS Unidentified Leakage IR 05000440/20244012024-07-0909 July 2024 Security Baseline Inspection Report 05000440/2024401 L-24-020, License Renewal Application for the Perry Nuclear Power Plant Revision 0, Supplement 22024-06-27027 June 2024 License Renewal Application for the Perry Nuclear Power Plant Revision 0, Supplement 2 05000440/LER-2024-002, Reactor Water Clean Up Leak Detection Loss of Safety Function2024-06-27027 June 2024 Reactor Water Clean Up Leak Detection Loss of Safety Function L-24-036, Annual 10 CFR 50.46 Report of Changes to or Errors in Emergency Core Cooling System Evaluation Models2024-06-27027 June 2024 Annual 10 CFR 50.46 Report of Changes to or Errors in Emergency Core Cooling System Evaluation Models 05000440/LER-2024-001, Operation of the Residual Heat Removal Loops B and C Alternate Keep Fill Configuration Was Prohibited by Technical Specifications and Resulted in an Unanalyzed Condition2024-06-20020 June 2024 Operation of the Residual Heat Removal Loops B and C Alternate Keep Fill Configuration Was Prohibited by Technical Specifications and Resulted in an Unanalyzed Condition IR 05000440/20240112024-06-17017 June 2024 Fire Protection Team Inspection Report 05000440/2024011 ML24157A3782024-06-0606 June 2024 – Revised Request for Information for NRC License Renewal Inspection: Inspection Report 05000440/2024010 ML24141A1632024-05-20020 May 2024 Information Request to Support the NRC Annual Baseline Emergency Action Level and Emergency Plan Changes Inspection L-24-116, Response to License Renewal Environmental Report Severe Accident Mitigation Alternatives Requests for Additional Information and Request for Clarification2024-05-16016 May 2024 Response to License Renewal Environmental Report Severe Accident Mitigation Alternatives Requests for Additional Information and Request for Clarification L-24-085, Nudear Power Plant, Submittal of Emergency Plan, Revision 622024-05-0606 May 2024 Nudear Power Plant, Submittal of Emergency Plan, Revision 62 L-24-103, Response to NRC Regulatory Issue Summary 2024-01, Preparation & Scheduling of Operator Licensing Exams2024-05-0202 May 2024 Response to NRC Regulatory Issue Summary 2024-01, Preparation & Scheduling of Operator Licensing Exams ML24117A1222024-04-26026 April 2024 Confirmation of Initial License Examination IR 05000440/20240012024-04-24024 April 2024 Integrated Inspection Report 05000440/2024001 L-24-097, Submittal of 2023 Annual Radiological Effluent Release Report2024-04-22022 April 2024 Submittal of 2023 Annual Radiological Effluent Release Report L-24-096, Submittal of Annual Radiological Environmental Operating Report2024-04-22022 April 2024 Submittal of Annual Radiological Environmental Operating Report ML24095A3282024-04-19019 April 2024 License Renewal Revised Schedule Letter 2024-09-09
[Table view] |
Text
FENOC PerryNuclear Power Station 10 Center Road FirstEnergyNuclear OperatingCompany Perry, Ohio 44081 L. William Pearce 440-280-5382 Vice President Fax: 440-280-8029 March 30, 2007 PY-CEI/NRR-3026L ATTN: Document Control Desk U.S. Nuclear Regulatory Commission Washington, DC 20555-0001 Perry Nuclear Power Plant Docket No. 50-440
Subject:
Response to a Request for Additional Information on a License Amendment Request to Revise MODE 4 Residual Heat Removal Shutdown Cooling Requirements (TAC NO. MD2140)
In a letter dated February 9, 2007, the Nuclear Regulatory Commission (NRC) requested that additional information be provided to complete the review of a license amendment request submitted by letter dated June 1, 2006 (PY-CEI/NRR-2963L). The amendment request revises MODE 4 Residual Heat Removal Shutdown Cooling Requirements to add a default Condition addressing-siiuations when Condition A cannot be met within its Completion Time. The attach'mentýto"this 'letter provides the requested information.
There are no new regulatory commitments contained in this letter or its attachment. If there are any questions or if additional information is required, please contact Mr. Henry L. Hegrat, Supervisor - Fleet Licensing, at (330) 374-3114.
I declare under penalty of perjury that the foregoing is true and correct. Executed on March ?V , 2007 L. William Pearce
Attachment:
Response to NRC Request for Additional Information dated February 9, 2007 cc: NRC Project Manager NRC Resident Inspector NRC Regibn II State of Ohio AooI
Attachment PY-CEI/NRR-3026L Page 1 of 2 Response to NRC Request for Additional Information dated February 9, 2007 In a Nuclear Regulatory Commission (NRC) Request for Additional Information (RAI) dated February 9, 2007, the NRC provided the following question, along with a background discussion:
Question: Discuss how Perry could comply with the proposed Technical Specifications (TSs) while simultaneously in Condition A and proposed Condition B of TS 3.4.10, if there was no means available to work towards the establishment of an alternate method of decay heat removal.
Background:
If proposed Condition B of TS 3.4.10, "RHR [Residual Heat Removal]
Shutdown Cooling System - Cold Shutdown" is entered, Required Actions of Condition A must still be carried out in accordance with TS 1.3, "Completion Times." TS 1.3 states a required actions condition remains in effect and the required actions apply until the condition no longer exists or the unit is not within the limiting condition for operation (LCO) applicability. Example 1.3-2 in TS 1.3 provides a discussion on simultaneously being in two conditions, A and B, as a result of the completion time for Condition A not being met, and therefore entering Condition B.
TS 3.4.10 Condition A, Required Action A.1 states: "Verify an alternate method of decay heat removal is available for each inoperable RHR shutdown cooling subsystem" (a separate condition entry is allowed for each RHR shutdown cooling subsystem). Page 3 of the license amendment request (LAR) states: "In parallel with this LAR for TS 3.4.10, the Perry performance improvement initiative is tracking a plant design change to incorporate a new alternate decay heat removal method for Mode 4. The new method will be capable of maintaining Cold Shutdown Mode 4 conditions early in a forced outage (24 hours2.777778e-4 days <br />0.00667 hours <br />3.968254e-5 weeks <br />9.132e-6 months <br /> or more after attaining Hot Shutdown Mode 3)." Prior to making this "new alternate decay heat removal method" available, TS compliance issues could still occur. This is the result of not being able to take any required actions for Condition A because there is no means to establish an alternate method of decay heat removal for each inoperable subsystem.
Per TS 1.3, Required Actions of Condition A must be worked on, even if Required Actions of proposed Condition B are completed.
RESPONSE: Addition of the proposed Condition B into Technical Specification (TS) 3.4.10 will allow full compliance with the Technical Specifications by providing Actions that apply when the Required Actions for Condition A cannot be met. The proposed actions are identical to those required by TS 3.9.9, "RHR -- Low Water Level," which served as the model for the proposed change. Use of a default Condition that states "RequiredActions and associated Completion Times of Condition [I not met" is consistent with the majority of the Specifications in the Improved Technical Specifications (ITS).
Default Conditions such as the proposed Condition B are part of the design of the improved TS.
The improved TS design utilizes a box/matrix format that replaced excessive logical connectors, such as "otherwise" and "or." Therefore, when a Completion Time is reached and a default Condition is entered, TS compliance is maintained by meeting the Required Actions of the default Condition, the same as when the two requirements are connected with an "otherwise" or an "or."
This ITS design feature is the basis for the proposed Perry TS amendment.
The above concept is also consistent with previous NRC interpretation regarding compliance with TS Limiting Conditions for Operation and Action statements, as documented in NRC Enforcement Guidance Memorandum (EGM) 97-013, Issued on July 14, 1997. EGM 97-013 directly addresses this issue using an example identical to Example 1.3-2 in TS Section 1.3, except that EGM 97-013 provides more detail than Example 1.3-2 regarding TS compliance. The following excerpts from EGM 97-013 describe the proper application of the human-factored box/matrix ITS format.
Attachment PY-CEI/NRR-3026L Page 2 of 2 AOT Examples CONDITION REQUIRED ACTION COMPLETION TIME A. One pump inoperable A.1 Restore pump to 7 days OPERABLE status.
B. Required Action and B.1 Be in MODE 3 12 hours1.388889e-4 days <br />0.00333 hours <br />1.984127e-5 weeks <br />4.566e-6 months <br /> associated Completion Time not met. AND B.2 Be in MODE 4. 36 hours4.166667e-4 days <br />0.01 hours <br />5.952381e-5 weeks <br />1.3698e-5 months <br /> Example 1:
When a pump is declared inoperable, Condition A is entered. If the pump is not restored to OPERABLE status within 7 days (the AOT), a violation does not exist (emphasis added).
Instead, Condition B is entered and the Completion Time clocks for Required Actions B.1 and B.2 start. A total of 12 hours1.388889e-4 days <br />0.00333 hours <br />1.984127e-5 weeks <br />4.566e-6 months <br /> is allowed for reaching MODE 3 and a total of 36 (not 48 hours5.555556e-4 days <br />0.0133 hours <br />7.936508e-5 weeks <br />1.8264e-5 months <br />) is allowed for reaching MODE 4 from the time that Condition B was entered. ... A violation exists if the pump cannot be restored to OPERABLE status after 7 days and (emphasis added) the unit is not placed in MODE 3 within the next 12 hours1.388889e-4 days <br />0.00333 hours <br />1.984127e-5 weeks <br />4.566e-6 months <br />, or a violation exists if the pump cannot be restored to OPERABLE status after 7 days and (emphasis added) the unit is
.not placed in MODE 4 within the next 36 hours4.166667e-4 days <br />0.01 hours <br />5.952381e-5 weeks <br />1.3698e-5 months <br />.
Again, a violation does not exist unless all actions are not completed within all applicable Completion Times.
Application of the concepts discussed above to the proposed change in Perry TS 3.4.10 results in two potential avenues for TS compliance, explained as follows. When a required RHR shutdown cooling loop becomes inoperable:
- 1) if the Reactor Water Cleanup (RWCU) system is available and can maintain MODE 4, Required Action A.1 can be met within its Completion Time, establishing TS compliance.
- 2) a. if RWCU is unavailable, or incapable of maintaining MODE 4, an alternate method will not be available within 1 hour1.157407e-5 days <br />2.777778e-4 hours <br />1.653439e-6 weeks <br />3.805e-7 months <br />, and the plant will enter into proposed Condition B.
Completion of the Required Actions in Condition B will establish TS compliance.
- b. if at a later time, RWCU becomes available and capable of maintaining MODE 4, an alternate method will be available to meet Condition A. Because Condition A 'remains in effect and the Required Actions continue to apply', Required Action A.1 is satisfied, establishing TS compliance. The Required Actions for default Condition B may be exited.
The above actions would establish compliance with the Technical Specifications while simultaneously in Condition A and proposed Condition B of TS 3.4.10 even if there were no means available to establish an alternate method of decay heat removal.
It should also be noted that for some TS Required Actions, applying an interpretation that initially-entered Actions must be carried out even if the default Actions are met would direct operators to perform actions that could result in safety system initiations, inappropriate isolations/unavailability of safety systems, and plant scrams, even though the TS provide alternate default Required Actions that instead allow time to effect necessary repairs, perform an orderly shutdown, or take other remedial actions.