MONTHYEARULNRC-06853, Submittal of 2023 Fitness for Duty Performance Data Per Per 10 CFR 26.7172024-01-29029 January 2024 Submittal of 2023 Fitness for Duty Performance Data Per Per 10 CFR 26.717 IR 05000483/20230042024-01-19019 January 2024 Integrated Inspection Report 05000483/2023004 ML24008A0552024-01-19019 January 2024 Acceptance of Requested Licensing Action - Proposed Alternative to the Requirements of the ASME Code (EPID L-2023-LLR- 0061) ML23353A1712024-01-18018 January 2024 Issuance of Amendment No. 237 to Clarify Support System Requirements for the Residual Heat Removal System and Control Room Air Conditioning System Under Technical Specifications 3.4.8, 3.7.11, and 3.9.6 ML23317A0012024-01-12012 January 2024 Audit Summary Regarding LAR to Clarify Support System Requirements for the Residual Heat Removal and Control Room Air Conditioning System Under Technical Specifications 3.4.8, 3.7.11, and 3.9.6 ML23347A1212024-01-11011 January 2024 Issuance of Amendment No. 236 to Adopt TSTF-501, Revision 1, Relocate Stored Fuel Oil and Lube Volume Values to Licensee Control EPID L-2023-LLA-0046) ML24011A1492024-01-11011 January 2024 Notification of Post-Approval Site Inspection for License Renewal and Request for Information (05000483/2024011) ULNRC-06847, Supplement to Relief Request from Requirements of ASME BPV Code, Section XI, Subsection Iwl Regarding Examination and Testing of the Unbonded Post-Tensioning System (Relief Request C3R-01)2023-12-21021 December 2023 Supplement to Relief Request from Requirements of ASME BPV Code, Section XI, Subsection Iwl Regarding Examination and Testing of the Unbonded Post-Tensioning System (Relief Request C3R-01) ULNRC-06849, License Renewal Resolution for Commitments 34 and 35 Perform Evaluation of Crack Initiation and Propagation in Steam Generator Divider Plate and Tube-To-Tubesheet Welds2023-12-20020 December 2023 License Renewal Resolution for Commitments 34 and 35 Perform Evaluation of Crack Initiation and Propagation in Steam Generator Divider Plate and Tube-To-Tubesheet Welds ML23346A0392023-12-14014 December 2023 Supplemental Information Needed for Acceptance of Requested Licensing Action Request for Relief from Requirements of ASME Code, Section Xl, Examination and Testing Unbonded Post-Tensioning System ULNRC-06844, Request for Exemption from Specific Requirements in 2023 Security Rule, Enhanced Weapons, Firearms Background Checks, and Security Event Notification2023-12-0707 December 2023 Request for Exemption from Specific Requirements in 2023 Security Rule, Enhanced Weapons, Firearms Background Checks, and Security Event Notification 05000483/LER-2023-001, Submittal of LER 2023-001-00 for Callaway, Unit 1, Inoperable Instrument Tunnel Sump Level Indication Resulted in Condition Prohibited by Technical Specifications2023-11-29029 November 2023 Submittal of LER 2023-001-00 for Callaway, Unit 1, Inoperable Instrument Tunnel Sump Level Indication Resulted in Condition Prohibited by Technical Specifications ULNRC-06827, Supplement to License Amendment Request Regarding Support System Requirements for Residual Heat Removal and Control Room Air Conditioning Systems Under Technical Specifications 3.4.8, 3.7.11, and 3.9.6 (LDCN 22-0029)2023-11-20020 November 2023 Supplement to License Amendment Request Regarding Support System Requirements for Residual Heat Removal and Control Room Air Conditioning Systems Under Technical Specifications 3.4.8, 3.7.11, and 3.9.6 (LDCN 22-0029) IR 05000483/20230102023-11-15015 November 2023 NRC License Renewal Phase 1 Inspection Report 05000483 2023010 IR 05000483/20233012023-11-0909 November 2023 NRC Examination Report 05000483-2023301 ML23311A2082023-11-0909 November 2023 Reassignment of U.S. Nuclear Regulatory Commission Branch Chief in the Division of Operating Reactor Licensing for Plant Licensing Branch IV ML23297A2502023-11-0606 November 2023 Individual Notice of Consideration of Issuance of Amendment to Renewed Facility Operating License, Proposed No Significant Hazards Consideration Determination and Opportunity for a Hearing (EPID L-2022-LLA-0176) - Letter IR 05000483/20240122023-10-24024 October 2023 Information Request for the Cybersecurity Baseline Inspection, Notification to Perform Inspection (05000483/2024012) ML23293A2652023-10-24024 October 2023 3rd Quarter 2023 Integrated Inspection Report ML23240A3692023-10-0505 October 2023 Issuance of Amendment No. 235 to Revise Technical Specifications to Use of Framatome Gaia Fuel (EPID L-2022-LLA-0150) (Non-Proprietary) ML23234A1522023-10-0505 October 2023 Exemption from the Requirements of 10 CFR Part 50, Section 50.46, and Appendix K Regarding Use of M5 Cladding Material (EPID L-2022-LLE-0030) (Letter) ML23305A0942023-10-0202 October 2023 10-CW-2023-09 Post-Exam Submittal ML23270B9662023-09-27027 September 2023 10 CFR 50.55a(z)(I) Request for Relief from ASME OM Code Pump and Valve Testing Requirements for Fifth 120-Month Inservice Testing Interval ML23228A0252023-09-25025 September 2023 Issuance of Amendment No. 234 to Revise Technical Specification 5.5.16, Containment Leakage Rate Testing Program, for Permanent Extension of Type a and Type C Leak Rate Test Frequencies ML23261C3852023-09-25025 September 2023 Safety Evaluation for Operating Quality Assurance Manual Revision 36A ML23166B0882023-09-20020 September 2023 Issuance of Amendment No. 233 for Adoption of Alternative Source Term and Revision of Technical Specifications ML23206A1992023-09-15015 September 2023 Regulatory Audit Summary Regarding License Amendment and Regulatory Exemptions Request for Fuel Transition to Framatome Gaia Fuel (Epids L-2022-LLA-0150 and L-2022-LLE-0030) IR 05000483/20234012023-09-13013 September 2023 NRC Security Baseline Inspection Report 05000483/2023401 ML23240A7572023-08-31031 August 2023 NRC Initial Operator Licensing Examination Approval 05000483/2023301 IR 05000483/20230052023-08-23023 August 2023 Updated Inspection Plan for Callaway Nuclear Power Plant, Unit 1 (Report 05000483/2023005) - Mid Cycle Letter 2023 ULNRC-06824, Response to Request for Additional Information Regarding Operating Quality Assurance Manual (Oqam) Revision 36A2023-08-17017 August 2023 Response to Request for Additional Information Regarding Operating Quality Assurance Manual (Oqam) Revision 36A ML23219A1392023-08-15015 August 2023 Request for Withholding Information from Public Disclosure ULNRC-06830, Transmittal of Updated Technical Specification Markup and Clean Pages for License Amendment Request to Revise Technical Specification 5.5.16, Containment Leakage Rate Testing Program, for Permanent Extension of Type a and Type C Leak2023-08-15015 August 2023 Transmittal of Updated Technical Specification Markup and Clean Pages for License Amendment Request to Revise Technical Specification 5.5.16, Containment Leakage Rate Testing Program, for Permanent Extension of Type a and Type C Leak ML23215A1972023-08-0303 August 2023 Supplement to License Amendment and Exemption Request Regarding Use of Framatome Gaia Fuel (LDCN 22-0002) ULNRC-06223, Minor Correction to License Amendment Request to Revise Technical Specification 5.5.16, Containment Leakage Rate Testing Program, for Permanent Extension of Type a and Type C Leak Rate Test Frequencies (LDCN 2020-0004)2023-07-25025 July 2023 Minor Correction to License Amendment Request to Revise Technical Specification 5.5.16, Containment Leakage Rate Testing Program, for Permanent Extension of Type a and Type C Leak Rate Test Frequencies (LDCN 2020-0004) ULNRC-06799, Submittal of Licensee Event Report 2022-003-01, Class 1E Electrical Air Conditioning System Thermal Expansion Valve Failure Resulted in Condition Prohibited by Technical Specifications2023-07-13013 July 2023 Submittal of Licensee Event Report 2022-003-01, Class 1E Electrical Air Conditioning System Thermal Expansion Valve Failure Resulted in Condition Prohibited by Technical Specifications IR 05000483/20230022023-07-10010 July 2023 Integrated Inspection Report 05000483/2023002 ML23174A1272023-06-23023 June 2023 Cw FFD Document Request List 2023 ML23171A9942023-06-22022 June 2023 Acceptance of Request for Approval of Operating Quality Assurance Manual Revision 36a ULNRC-06821, Post-Audit Follow-Up Information in Support of Callaway'S License Amendment Request and Proposed Exemption to Allow Use of Framatome Gaia Fuel (LDCN 22-0002) (EPID L-2022-LLA-0150 and EPID L-2022-LLE-00301)2023-06-21021 June 2023 Post-Audit Follow-Up Information in Support of Callaway'S License Amendment Request and Proposed Exemption to Allow Use of Framatome Gaia Fuel (LDCN 22-0002) (EPID L-2022-LLA-0150 and EPID L-2022-LLE-00301) IR 05000483/20230112023-06-15015 June 2023 Comprehensive Engineering Team Inspection (CETI) Inspection Report 05000483/2023011 ULNRC-06822, Additional Information Regarding Request for NRC Approval of Operating Quality Assurance Manual (Oqam) Revision 36a2023-06-14014 June 2023 Additional Information Regarding Request for NRC Approval of Operating Quality Assurance Manual (Oqam) Revision 36a ML23158A1462023-06-13013 June 2023 Notification of Post-Approval Site Inspection for License Renewal and Request for Information Inspection (05000483/2023010) ULNRC-06815, Request for NRC Approval of Operating Quality Assurance Manual, Revision 36a2023-06-0505 June 2023 Request for NRC Approval of Operating Quality Assurance Manual, Revision 36a ULNRC-06818, Response to Request for Additional Information Regarding License Amendment Request to Revise Technical Specification 5.5.16, Containment Leakage Rate Testing Program, for Permanent Extension of Type a and Type C Leak Rate .2023-06-0505 June 2023 Response to Request for Additional Information Regarding License Amendment Request to Revise Technical Specification 5.5.16, Containment Leakage Rate Testing Program, for Permanent Extension of Type a and Type C Leak Rate . ML23093A0952023-05-10010 May 2023 Issuance of Amendment No. 232 Regarding Technical Specification Changes for Spent Fuel Storage ULNRC-06816, Withdrawal of Previously Submitted Enclosures Regarding License Amendment Request for Adoption of Alternative Source Term and Revision of Technical Specifications (LDCN 21-0015)2023-05-0909 May 2023 Withdrawal of Previously Submitted Enclosures Regarding License Amendment Request for Adoption of Alternative Source Term and Revision of Technical Specifications (LDCN 21-0015) ML23129A7942023-05-0909 May 2023 Post-Audit Supplement to License Amendment Request and Exemption to Allow Use of Framatome Gaia Fuel (LDCN 22-0002) (Iepid L-2022-LLA-0150 and EPID L-2022-LLE-0030) ML23122A3172023-05-0808 May 2023 Review of the Spring 2022 Steam Generator Tube Inservice Inspections ML23118A3492023-05-0808 May 2023 Request for Withholding Information from Public Disclosure 2024-01-29
[Table view] |
Text
March 29, 2007 CAL No. NRR-07-013 Mr. Charles D. Naslund Senior Vice President and Chief Nuclear Officer Union Electric Company Post Office Box 620 Fulton, MO 65251
SUBJECT:
CONFIRMATORY ACTION LETTER - CALLAWAY PLANT, UNIT 1 (TAC NO. MD4138)
Dear Mr. Naslund:
This letter confirms commitments by Union Electric Company in regard to Alloy 82/182 butt welds in the pressurizer at Callaway Plant, Unit No. 1.
The discovery, in October 2006, of five circumferential indications in three dissimilar metal (DM) welds on the pressurizer at the Wolf Creek Generating Station (Wolf Creek) raised safety concerns based on the size and location of the indications. At Wolf Creek, three indications were in the pressurizer surge nozzle-to-safe end weld, and two separate indications were in the safety and relief nozzle-to-safe end welds. These findings also indicated that significant concerns might exist with the inspection schedules for addressing the pressurizer weld concerns issued by the industry-sponsored Materials Reliability Program (MRP), in Primary System Piping Butt Weld Inspection and Evaluation Guideline (MRP-139).
The Nuclear Regulatory Commission (NRC) is concerned about the pressurizer surge nozzle-to-safe end weld indications, as this is the first time that multiple circumferential primary water stress-corrosion cracking (PWSCC) indications have been identified in a weld. This condition calls into question the degree of safety margin present in past structural integrity evaluations for flawed DM welds susceptible to PWSCC, since multiple stress-corrosion cracking flaws may grow independently and ultimately grow together, significantly reducing the time from flaw initiation to leakage or rupture. The size of the relief nozzle-to-safe end flaw is also of concern, as this flaw has a much larger aspect ratio than those assumed in the estimates used to establish the basis for completing the baseline inspections required by the industry-sponsored MRP. Larger aspect ratios could result in achieving a critical flaw size and rupture before the onset of detectable leakage.
The long-term resolution of this issue is expected to involve changes to the American Society of Mechanical Engineers Boiler and Pressure Vessel Code (ASME Code), and will involve changes to the NRC regulations in Title 10 of the Code of Federal Regulations (10 CFR),
Part 50, Section 50.55a, Codes and standards. The development of the NRC regulations, whether the rule adopts the ASME Code standards or defines separate requirements, will likely benefit from additional operating experience, continuing assessments, and analysis being conducted by the NRC and the MRP.
C. D. Naslund Until NRC regulations are revised, it is necessary to establish a minimum set of enhanced reactor coolant system (RCS) DM butt weld inspection expectations for nickel-based Alloy 82/182 pressurizer surge, spray, safety, and relief nozzle butt welds, including safe end welds, to supplement existing inspection and other requirements of the ASME Code and NRC regulations. In addition, enhanced monitoring of RCS leakage is needed to promptly identify any through-wall flaws in the pressurizer surge, spray, safety, or relief nozzle DM butt welds or safe end DM butt welds to prevent additional degradation from occurring. The above actions provide reasonable assurance that there is no undue risk to the health and safety of the public while the NRC regulations are revised.
The NRC communicated the need for near-term enhancements to the industry through public meetings held on November 30, 2006; December 20, 2006; and February 2, 2007. Licensees submitted letters voluntarily committing to the enhanced inspection and leakage monitoring requirements. After teleconferences with specific licensees held between February 12 through February 23, 2007, the licensees submitted supplemental commitment letters addressing the NRC staffs concerns regarding inspection, compensatory actions, and reporting.
In your letter dated January 31, 2007 (Agencywide Documents Access and Management System (ADAMS) Accession No. ML070380277), as supplemented by letter dated February 28, 2007 (ADAMS Accession no. ML070670457), you described actions you will take at the Callaway Plant, Unit 1 for the pressurizer DM butt welds containing Alloy 82/182 material.
These commitments address: 1) completion schedules for inspection/mitigation of the welds;
- 2) RCS leak monitoring frequency, action levels, and actions; and 3) reporting requirements.
The NRC staff has reviewed these actions and commitments, and agrees that the actions and commitments are appropriate to address the potential of PWSCC of the applicable pressurizer DM butt welds containing Alloy 82/182 material.
Pursuant to Section 182 of the Atomic Energy Act, 42 U.S.C. 2232, you are required to:
- 1) Notify me immediately if your understanding differs from that set forth above;
- 2) Notify me if for any reason you cannot complete the actions and commitments within the specified schedule and advise me in writing of your modified schedule in advance of the change; and
- 3) Notify me in writing when you have completed the actions and commitments addressed in this Confirmatory Action Letter.
Issuance of this Confirmatory Action Letter does not preclude issuance of an order formalizing the above commitments or requiring other actions on the part of the licensee; nor does it preclude the NRC from taking enforcement action for violations of NRC requirements that may have prompted the issuance of this letter. In addition, failure to take the actions addressed in this Confirmatory Action Letter may result in enforcement action.
In accordance with 10 CFR 2.390 of the NRC's "Rules of Practice," a copy of this letter and your response will be made available electronically for public inspection in the NRC Public Document Room or from the NRCs ADAMS, accessible from the NRC Web site at
C. D. Naslund http://www.nrc.gov/reading-rm/adams.html. To the extent possible, your response should not include any personal privacy, proprietary, or safeguards information so that it can be made available to the Public without redaction. If personal privacy or proprietary information is necessary to provide an acceptable response, then please provide a bracketed copy of your response that identifies the information that should be protected and a redacted copy of your response that deletes such information. If you request withholding of such material, you must specifically identify the portions of your response that you seek to have withheld and provide in detail the bases for your claim of withholding (e.g., explain why the disclosure of information will create an unwarranted invasion of personal privacy or provide the information required by 10 CFR 2.390(b) to support a request for withholding confidential commercial or financial information). If safeguards information is necessary to provide an acceptable response, please provide the level of protection described in 10 CFR 73.21.
Sincerely,
/RA/
J. E. Dyer, Director Office of Nuclear Reactor Regulation Docket No. 50-483 License No. NPF-30 cc: See next page
ML070680123 *coordinated with Region IV per OE Manual-per MGE OFFICE CPNB DCI LPL4/PM LPL4/LA LPL4/BC TECH ED DIRS/TA NAME TLupold ESullivan JDonohew LFeizollahi DTerao HChang RPascarelli DATE 3/21/07 3/21/07 3/20/07 3/20/07 3/20/07 2/28/07 3/21/07 OFFICE CPNB/BC DRP/D RIV DORL/D DCI/D ADES/AD NRR/D NAME TChan AHowel III per CHaney MEvans JGrobe JDyer email frm WJones DATE 3/21/07 3/27/07 3/26/07 3/28/07 3/28/07 3/29/07 Callaway Plant, Unit 1 cc:
Professional Nuclear Consulting, Inc. Mr. Dan I. Bolef, President 19041 Raines Drive Kay Drey, Representative Derwood, MD 20855 Board of Directors Coalition for the Environment John ONeill, Esq. 6267 Delmar Boulevard Pillsbury Winthrop Shaw Pittman LLP University City, MO 63130 2300 N. Street, N.W.
Washington, D.C. 20037 Mr. Lee Fritz, Presiding Commissioner Callaway County Court House Mr. Keith A. Mills, Supervising Engineer 10 East Fifth Street Regional Regulatory Affairs/Safety Analysis Fulton, MO 65151 AmerenUE P.O. Box 620 Mr. David E. Shafer Fulton, MO 65251 Superintendent, Licensing Regulatory Affairs U.S. Nuclear Regulatory Commission AmerenUE Resident Inspector Office P.O. Box 66149, MC 470 8201 NRC Road St. Louis, MO 63166-6149 Steedman, MO 65077-1302 Manager, Regulatory Affairs Mr. Les H. Kanuckel AmerenUE Manager, Quality Assurance P.O. Box 620 AmerenUE Fulton, MO 65251 P.O. Box 620 Fulton, MO 65251 Mr. Keith G. Henke, Planner Division of Community and Public Health Missouri Public Service Commission Office of Emergency Coordination Governor Office Building 930 Wildwood P.O. Box 570 200 Madison Street Jefferson City, MO 65102 Jefferson City, MO 65102-0360 Certrec Corporation Regional Administrator, Region IV 4200 South Hulen, Suite 630 U.S. Nuclear Regulatory Commission Fort Worth, TX 76109 611 Ryan Plaza Drive, Suite 400 Arlington, TX 76011-4005 Director, Missouri State Emergency Management Agency Mr. H. Floyd Gilzow P.O. Box 116 Deputy Director for Policy Jefferson City, MO 65102-0116 Missouri Department of Natural Resources P.O. Box 176 Jefferson City, MO 65102-0176 Mr. Rick A. Muench President and Chief Executive Officer Wolf Creek Nuclear Operating Corporation P.O. Box 411 Burlington, KA 66839 June 2006