Text

November 14, 2006 Mr. James H. Riley, Director Engineering Nuclear Energy Institute Suite 400 1776 I Street, NW Washington, DC 20006-3708

SUBJECT:

ACCEPTANCE FOR REVIEW OF ELECTRIC POWER RESEARCH INSTITUTE MOTOR-OPERATED VALVE PERFORMANCE PREDICTION METHODOLOGY SOFTWARE (TAC NO. MD3236)

Dear Mr. Riley:

By letter dated June 8, 2004, as supplemented by letter dated January 6, 2006, the Nuclear Energy Institute submitted for U.S. Nuclear Regulatory Commission (NRC) staff review Addenda 3, 4, 5, 6, and 7 to Electric Power Research Institute Topical Report (TR)-103237 Motor-Operated Valve Performance Prediction Methodology Software. The NRC staff has performed an acceptance review of the TR-103237-R2 and Software Version. We have found that the material presented is sufficient to begin our comprehensive review. The NRC staff expects to issue its request for additional information by February 23, 2007, and issue its draft safety evaluation by June 15, 2007. The NRC staff estimates that the review will require approximately 325 staff hours including project management time. The review schedule milestones and estimated review costs were discussed and agreed upon in a telephone conference between you and the NRC staff on November 6, 2006.

In accordance with the letter dated September 2, 2004 (Agencywide Documents Access and Management System Accession No. ML042460445), the fee branch has waived the Section 170.11 of Title 10 of the Code of Federal Regulations fees associated with this TR review.

Sincerely,

/RA/

Stacey L. Rosenberg, Chief Special Projects Branch Division of Policy and Rulemaking Office of Nuclear Reactor Regulation Project Nos. 669 and 689 cc: See next page

November 14, 2006 Mr. James H. Riley, Director Engineering Nuclear Energy Institute Suite 400 1776 I Street, NW Washington, DC 20006-3708

SUBJECT:

ACCEPTANCE FOR REVIEW OF ELECTRIC POWER RESEARCH INSTITUTE MOTOR-OPERATED VALVE PERFORMANCE PREDICTION METHODOLOGY SOFTWARE (TAC NO. MD3236)

Dear Mr. Riley:

By letter dated June 8, 2004, as supplemented by letter dated January 6, 2006, the Nuclear Energy Institute submitted for U.S. Nuclear Regulatory Commission (NRC) staff review Addenda 3, 4, 5, 6, and 7 to Electric Power Research Institute Topical Report (TR)-103237 Motor-Operated Valve Performance Prediction Methodology Software. The NRC staff has performed an acceptance review of the TR-103237-R2 and Software Version. We have found that the material presented is sufficient to begin our comprehensive review. The NRC staff expects to issue its request for additional information by February 23, 2007, and issue its draft safety evaluation by June 15, 2007. The NRC staff estimates that the review will require approximately 325 staff hours including project management time. The review schedule milestones and estimated review costs were discussed and agreed upon in a telephone conference between you and the NRC staff on November 6, 2006.

In accordance with the letter dated September 2, 2004 (Agencywide Documents Access and Management System Accession No. ML042460445), the fee branch has waived the Section 170.11 of Title 10 of the Code of Federal Regulations fees associated with this TR review.

Sincerely,

/RA/

Stacey L. Rosenberg, Chief Special Projects Branch Division of Policy and Rulemaking Office of Nuclear Reactor Regulation Project Nos. 669 and 689 cc: See next page DISTRIBUTION:

PUBLIC PSPB Reading File TScarborough RidsNrrDpr RidsNrrDprPspb RidsNrrDciCptb RidsNrrLADBaxley RidsAcrsAcnwMailCenter RidsNrrPMTMensah RidsOgcMailCenter RidsNrrDciCfeb RidsNrrDciCpnb ADAMS ACCESSION NO.: ML063120335 NRR-106 OFFICE PSPB/PM PSPB/LA PSPB/BC NAME TMensah DBaxley SRosenberg DATE 11/14/06 11/13/06 11/14/06 OFFICIAL RECORD COPY

Nuclear Energy Institute Project No. 689 Electric Power Research Institute Project No. 669 cc:

Mr. Anthony Pietrangelo, Senior Director Ms. Barbara Lewis Risk Regulation Assistant Editor Nuclear Energy Institute Platts, Principal Editorial Office 1776 I Street, NW, Suite 400 1200 G St., N.W., Suite 1100 Washington, DC 20006-3708 Washington, DC 20005 Mr. H. A. Sepp, Manager Mr. Gary Welsh Regulatory and Licensing Engineering Institute of Westinghouse Electric Company Nuclear Power Operations P. O. Box 355 Suite 100 Pittsburgh, PA 15230-0355 700 Galleria Parkway, SE Atlanta, GA 30339-5957 Mr. Jack Roe Nuclear Energy Institute Mr. David J. Modeen 1776 I Street, NW, Suite 400 Vice President and Chief Nuclear Officer Washington, DC 20006-3708 EPRI 1300 W. T. Harris Boulevard Mr. Charles B. Brinkman Charlotte, NC 28262-8550 Washington Operations ABB-Combustion Engineering, Inc. Mr. John Gaertner 12300 Twinbrook Parkway, Suite 330 EPRI Rockville, MD 20852 1300 W.T. Harris Boulevard Charlotte, NC 28262-8550 Mr. Gary L. Vine, Executive Director EPRI Ms. Rosa Yang 2000 L Street, NW, Suite 805 EPRI Washington, DC 20036-4907 3412 Hillview Avenue Palo Alto, CA 94304-1338 Mr. Pedro Salas Regulatory Assurance Manager - Dresden Mr. Kenneth Huffman Exelon Generation Company, LLC EPRI 6500 N. Dresden Road 1300 W. T. Harris Boulevard Morris, IL 60450-9765 Charlotte, NC 28262-8550