November 9, 2006 Mr. Randy C. Bunt Chair, BWR Owners Group Southern Nuclear Operating Company 40 Inverness Center Parkway/Bin B057 Birmingham, AL 35242

SUBJECT:

ACCEPTANCE FOR REVIEW OF BOILING WATER REACTOR OWNERS GROUP (BWROG) TOPICAL REPORT (TR) NEDC-33178P, REVISION 0, "GENERAL ELECTRIC METHODOLOGY FOR DEVELOPMENT OF REACTOR PRESSURE VESSEL PRESSURE-TEMPERATURE CURVES" (TAC NO. MD2693)

Dear Mr. Bunt:

By letter dated July 28, 2006, the BWROG submitted for U.S. Nuclear Regulatory Commission (NRC) staff review TR NEDC-33178P, Revision 0, "General Electric Methodology for Development of Reactor Pressure Vessel Pressure-Temperature Curves." The NRC staff has performed an acceptance review of the TR NEDC-33178P, Revision 0. We have found that the material presented is sufficient to begin our comprehensive review. The NRC staff expects to issue its request for additional information by April 18, 2007, and issue its draft safety evaluation by November 28, 2007. The NRC staff estimates that the review will require approximately 330 staff hours including project management time. The review schedule milestones and estimated review costs were discussed and agreed upon in a telephone conference between Fred Emerson and the NRC staff on November 2, 2006.

Section 170.21 of Title 10 of the Code of Federal Regulations requires that TRs are subject to fees based on the full cost of the review. You did not request a fee waiver; therefore, NRC staff hours will be billed accordingly.

Sincerely,

/RA/

Stacey L. Rosenberg, Chief Special Projects Branch Division of Policy and Rulemaking Office of Nuclear Reactor Regulation Project No. 691 cc: See next page

November 9, 2006 Mr. Randy C. Bunt Chair, BWR Owners Group Southern Nuclear Operating Company 40 Inverness Center Parkway/Bin B057 Birmingham, AL 35242

SUBJECT:

ACCEPTANCE FOR REVIEW OF BOILING WATER REACTOR OWNERS GROUP (BWROG) TOPICAL REPORT (TR) NEDC-33178P, REVISION 0, "GENERAL ELECTRIC METHODOLOGY FOR DEVELOPMENT OF REACTOR PRESSURE VESSEL PRESSURE-TEMPERATURE CURVES" (TAC NO. MD2693)

Dear Mr. Bunt:

By letter dated July 28, 2006, the BWROG submitted for U.S. Nuclear Regulatory Commission (NRC) staff review TR NEDC-33178P, Revision 0, "General Electric Methodology for Development of Reactor Pressure Vessel Pressure-Temperature Curves." The NRC staff has performed an acceptance review of the TR NEDC-33178P, Revision 0. We have found that the material presented is sufficient to begin our comprehensive review. The NRC staff expects to issue its request for additional information by April 18, 2007, and issue its draft safety evaluation by November 28, 2007. The NRC staff estimates that the review will require approximately 330 staff hours including project management time. The review schedule milestones and estimated review costs were discussed and agreed upon in a telephone conference between Fred Emerson and the NRC staff on November 2, 2006.

Section 170.21 of Title 10 of the Code of Federal Regulations requires that TRs are subject to fees based on the full cost of the review. You did not request a fee waiver; therefore, NRC staff hours will be billed accordingly.

Sincerely,

/RA/

Stacey L. Rosenberg, Chief Special Projects Branch Division of Policy and Rulemaking Office of Nuclear Reactor Regulation Project No. 691 cc: See next page DISTRIBUTION:

PUBLIC PSPB Reading File RidsNrrDpr RidsNrrDprPspb RidsNrrLADBaxley RidsAcrsAcnwMailCenter RidsNrrPMMHoncharik RidsOgcMailCenter RidsNrrDciCvib ADAMS ACCESSION NO.: ML063060083 NRR-106 OFFICE PSPB/PM PSPB/LA PSPB/BC NAME MHoncharik DBaxley SRosenberg DATE 11/9/06 11/9/06 11/9/06 OFFICIAL RECORD COPY

BWR Owners Group Project No. 691 Mr. Doug Coleman Vice Chair, BWR Owners Group Energy Northwest Columbia Generating Station Mail Drp PE20 P.O. Box 968 Richland, WA 99352-0968 Mr. Amir Shahkarami Executive Chair, BWR Owners Group Exelon Generation Co., LLC Cornerstone II at Cantera 4300 Winfield Road Warrenville, IL 60555 Mr. Richard Libra Executive Vice Chair, BWR Owners Group DTE Energy - Fermi 2 M/C 280 OBA 6400 North Dixie Highway Newport, MI 48166 Mr. William A. Eaton Entergy Operations Inc.

P.O. Box 31995 Jackson, MS 39286 Mr. Richard Anderson First Energy Nuclear Operating Co Perry Nuclear Power Plant 10 Center Road Perry, OH 44081 Mr. Scott Oxenford Energy Northwest Columbia Generating Station Mail Drp PE04 P.O. Box 968 Richland, WA 99352-0968 Mr. James F. Klapproth GE Energy M/C A-16 3901 Castle Hayne Road Wilmington, NC 28401 Mr. Joseph E. Conen Regulatory Response Group Chair BWR Owners Group DTE Energy-Fermi 2 200 TAC 6400 N. Dixie Highway Newport, MI 48166 Mr. J. A. Gray, Jr.

Regulatory Response Group Vice-Chair BWR Owners Group Entergy Nuclear Northeast 440 Hamilton Avenue Mail Stop 12C White Plains, NY 10601-5029 Mr. Thomas G. Hurst GE Energy M/C A-16 3901 Castle Hayne Road Wilmington, NC 28401 Mr. Tim E. Abney GE Energy M/C A-16 3901 Castle Hayne Road Wilmington, NC 28401 BWR Owners Group 7/31/06