MONTHYEARML0623501852006-08-25025 August 2006 Forthcoming Pre-Application Review Meeting with Constellation Generation Group/Nine Mile Point, Et. Al., Regarding Nine Mile Point Nuclear Station, Unit Nos. 1 and 2 (NMP1&2) Extended Power Uprate (TAC Nos. MD2843 and MD844) Project stage: Meeting ML0624100142006-08-31031 August 2006 Notice of Forthcoming Pre-Applicaftion Review Meeting with Constellation Generation Group/Nine Mile Point Nuclear Station, LLC Et. Al., Regarding N;Ine Mile Point Nuclear Station, Unit No.2 (NMP2) Extended Power Uprate Project stage: Meeting ML0630003542006-09-26026 September 2006 Slides for Constellation Energy Nine Mile Point 2 Extended Power Uprate Meeting Project stage: Meeting ML0630003512006-10-20020 October 2006 Public Meeting with Constellation Energy Group Regarding Nine Mile Point Unit 2, Pre-Application Extended Power Uprate Meeting, List of Attendees Project stage: Meeting ML0628604822006-10-20020 October 2006 Summary of Category 1 Meeting Working-Level with Constellation Energy Group to Discuss NMP2 Extended Power Uprate Application to Be Submitted During the First Quarter 2008 Project stage: Meeting 2006-08-25
[Table View] |
|
---|
Category:Slides and Viewgraphs
MONTHYEARML24310A0672024-11-0505 November 2024 Constellation NRC Pre-Submittal Meeting Slides - Proposed Alternative for Reactor Vessel Closure Stud Exam Optimization ML24137A1882024-05-16016 May 2024 Annual Assessment Meeting for Pa/Md/Ny/Nj Nuclear Power Plants - NRC Presentation Slides ML24100A7672024-04-11011 April 2024 Meeting Slides - Preapplication with Constellation on Planned Fleet Alternative Request to Adopt OMN-2 ML24089A2612024-04-0909 April 2024 Slides - Constellation - Pre-Application Regarding Hooded Masks 4/9/2024 Meeting Slides (L-2024-LLM-0041) ML24029A1742024-01-30030 January 2024 Constellation Pre-Application January 30, 2024, Meeting Slides - Proposed Alternative to Utilize Code Case N-932, Alternative Requirements for Acceptance of Containment Base Metal Corrosion or Erosion ML23317A0712023-11-14014 November 2023 NRC Pre-Submittal Meeting on November 14th, 2023 - TSTF-591 and Selected 50.69 License Condition Updates (EPID L-2023-LLM-0098) (Slides) ML23262B2602023-09-19019 September 2023 Slides - Constellation - Pre-Application EP 9/25/2023 Meeting Handout ML23255A1042023-08-11011 August 2023 Slides - Constellation - Pre-Application EP 9/18/2023 Draft CEG Presubmittal SG Performance Monitoring Plan Meeting Handout ML23157A0352023-06-0606 June 2023 Annual Assessment Meeting for Pa/Md/Ny/Nj Nuclear Power Plants - NRC Presentation Slides ML23103A4072023-04-13013 April 2023 Presentation Slides for Information Call on 4/13/23 N2E Recirc Discharge Nozzle Weld Repair 2nd Request for Alternative ML23080A2972023-03-21021 March 2023 Presentation Slides for Information Call on 3/21/23 N2E Recirc Discharge Nozzle Weld Repair Request for Alternative NEI 99-01, Slides - Constellation - Pre-Application EP 2/23/2023 Meeting Slides2023-02-21021 February 2023 Slides - Constellation - Pre-Application EP 2/23/2023 Meeting Slides ML22305A5922022-11-0303 November 2022 Pre-Submittal Meeting Presentation Slides - Risk Informed Completion Time (TSTF-505) and Risk Informed Categorization and Treatmentof SSCs (10 CFR 50.69) Proposed License Amendments-Updated ML22301A0132022-11-0303 November 2022 Pre-Submittal Meeting Presentation Slides - Risk Informed Completion Time (TSTF-505) and Risk Informed Categorization and Treatmentof SSCs (10 CFR 50.69) Proposed License Amendments ML22222A1122022-08-0404 August 2022 NMP1 Torus Corrosion Presentation for August 2022 Final ML21314A4472021-11-10010 November 2021 Slides for Presubmittial Meeting for Proposed Alternative to Adopt ASME Code Case N-921 to Extend the Inservice Inspection Interval ML21165A2882021-06-16016 June 2021 Joint Annual Assessment for Pa/Md/Nj/Ny Nuclear Power Plants - Webinar Presentation (Updated) ML21165A1942021-06-16016 June 2021 Joint Annual Assessment Meeting for Pa/Md/Nj/Ny Nuclear Power Plants - Webinar Presentation ML21162A3322021-06-11011 June 2021 BWR Fleet Relief Request Associated with RPV Instrument Nozzle Repairs ML20261G7322020-09-16016 September 2020 Pre-Submittal Slides Extend 120-month Isi/Ist Interval Under 50.55a ML20178A4202020-06-30030 June 2020 NEI Slides for June 30, 2020, Public Meeting on COVID-19 Response ML20175A8722020-06-23023 June 2020 Risk-Informed Inservice Inspection - U.S Nuclear Regulatory Commission (NRC) - Four Element Risk-Informed Approach ML20170B0212020-06-23023 June 2020 NRC Pre-Submittal Meeting Byron Unit 2 One-Time Deferral of Reactor Pressure Vessel Head Penetration Nozzle (Rpvhpn) Inspections ML20163A6552020-06-16016 June 2020 6-16-20 Byron Unit 2 Steam Generator License Amendment Request Pre-Submittal Meeting (NRC) - Byron Unit 2 LAR for One-Time Deferral of Steam Generator Inspections ML20169A5592020-06-16016 June 2020 Steam Generator License Amendment Request Pre-Submittal Meeting (NRC) - Byron Unit 2 LAR for One-Time Deferral of Steam Generator Inspections (Rev 1) ML20098D5082020-04-0909 April 2020 AST LOCA Approach to Elemental Iodine Removal - NRC Public Meeting on RAI 6 - April 9, 2020 ML20022A0262020-01-22022 January 2020 NEI Presentation Status Update for Ropte Short Term Action Plan: Removed Planned Unavailability for Mitigating Systems Performance Index ML19158A1202019-06-10010 June 2019 Rict & 50.69 LARs NRC Pre-submittal Meeting ML19133A0912019-04-22022 April 2019 Supplement to Containment Oxygen Concentration License Amendment Request ML18347B3142018-12-19019 December 2018 Bwrvip/Asme Relief Request Discussion December 19, 2018 ML18334A2162018-11-30030 November 2018 Presentation Slides: Exelon BWR MSIV (Boiling-Water Reactor - Main Steam Isolation Valve) Leakage Optimization for NRC Pre-Submittal Meeting of December 6, 2018 ML18319A1272018-11-19019 November 2018 Slides for 11/19/18 Public Meeting - Exelon Fleet LAR for Common Language for TS 5.7 High Radiation Areas ML18054B3592018-02-27027 February 2018 Slide: NRC Pre-Submittal Meeting for Exelon Fleet LAR to Relocate TS Unit Staff Qualification ANSI Requirements to the QATR, February 27, 2018, Profile Info: Submitted by Frank Mascitelli ML17325A2772017-11-28028 November 2017 November 28, 2017 Pre-Submittal Teleconference Re Planned TSTF-542 LAR Presentation ML17306A0842017-11-0606 November 2017 Meeting Slide for Teleconference with Exelon Generation Company, LLC - Criticality Analysis for NMP1 Boraflex Racks: No Boraflex Credit, 3 Out of 4 Loading, and Cell Blockers ML16153A3442016-06-0101 June 2016 Oswego Chamber of Commerce Assessment Meeting Presentation ML16077A1562016-03-22022 March 2016 Fleet: Pre-application Teleconference with Exelon to Discuss a Potential License Amendment Request Regarding Operating Training Standards ML14084A5342014-03-26026 March 2014 Nrc/Nei Presentation Slides: 13-02 OIP Template Update ML13340A0912013-11-0101 November 2013 Regulatory Conference/Public Meeting - Loss of Shutdown Cooling - Ceng Presentation/Slides ML13059A3742013-03-13013 March 2013 Summary of Category 1 Public Meeting with Nine Mile Point Nuclear Station, Unit 2 Representatives to Discus Planned Amendment Request on Implementation of Mellla+ ML1212100442012-04-0303 April 2012 Meeting Slides - NFPA-805 Pre-Application Meeting with NRC Staff April 3, 2012 ML1113605612011-05-16016 May 2011 NRC Meeting Slides, Nine Mile Point & Fitzpatrick 2011 Annual Assessment Meeting ML0926506592009-09-15015 September 2009 Slides from the Public Meeting with Constellation Energy - Nine Mile Point ISFSI Presentation ML0827705652008-10-27027 October 2008 Extended Power Uprate Pre-Application Meeting Slides ML0827503872008-09-29029 September 2008 Enclosure 2 Meeting Slides ML0811403012008-04-23023 April 2008 NRC Annual Performance Assessment Meeting ML0807901872008-03-18018 March 2008 NRC Annual Performance Assessment Slides, 2007 Reactor Oversight Program ML0712704232007-04-24024 April 2007 Constellation Slides - Nine Mile Point Meeting Annual Assessment Summary 2006-07 ML0710100842007-04-10010 April 2007 Slides for 04/24/2007 Nine Mile Point Annual Assessment Meeting ML0634800282006-12-0404 December 2006 Slides, Nine Mile Point 1 Alternate Source Term, from Nrc/Constellation Energy Meeting 2024-05-16
[Table view] |
Text
Agenda e Meeting Objectives o Background
" Project Overview
" Preliminary Timeline
" Project Submittal
- Related Licensing Actions and Overlaps o Summary e Questions 2
.~.-
A; :)~ *~
Meeting Objectives
" CEG's plan and timeline for a constant pressure extended power uprate at NMP2
" Communication between the NMP2 Uprate project team and the NRC e CEG's benchmarking relative to recent submittals 3
=
Background===
- GE BWR 5 Operating License in 1987 - 3323 MWt
- In 1995, uprated to 105% OLTP - 3467 MWt
- Extended Power Uprate'to 120% OLTP - 3988 MWt 4
EPU Project Organization Projýect Sponsor NMP VicePrsdn NMP Steering .iei
ý,Commit_ tee
" Operations
" Maintenance
" Training 5
Project Overview
" Potential major equipment modifications or replacements
- High pressure turbine replacement
- Feedwater/Condensate system modifications
- Capacitor banks
" Steam dryer evaluations
- Phased increases in power level
6
Preliminary Timeline r irYI I 2006 2007 I 2008 I 0 2009 I 2010 I 2011 I 2012 0 I. 0 I o0 0 0 0 0 0 ft. 0= -J 4E Receive NRC Subn it Submit Approval of Alternate Source Term K>
Alternlkte ,< to NRZ RecE ive NRC A Source oTrm App roval of 4 to NOC RFO -PU 11 Receive NRC4 Approval of I Start EPU S Subi nit ARTS/MELLLA conceptual ARTSIMI .LLLA phase to NItc S ubmit MI:LLLA+
b iNRC Concepti aual I Design l
-Completion of Engineering
- NRC Submi.ttal for " ARTSIMELLLA Installation (RFOli)
ARTSIMELLLA " EPU Modification Installation (RFO1 I /RFO1 21RFO1 3)
- NRC Review and Approval " MELLLA+ Implementation (RFO13)
ARTSIMELLLA Training
- Power Ascension Testing 7
Stakeholder Interfaces
- Stakeholder communications
- Open communication and dialogue with project stakeholders mNRC mNYS Independent System Operator (NYISO) mTransmission owners mLong Island Power Authority (LIPA)
- NYS Department of Environmental Conservation (DEC)
- City and County officials 8
Project Submittal
" Use of RS-O01, Revision 0 "Review Standard for Extended Power Uprates"
" Technical rigor
- Independent Reviews
- Vendor Audit Process
" Industry lessons Learned addressed
- Steam Dryer
- Vibration monitoring
" Ensure current issues understood 9
s,....*pt't - .aillioi.... .p A Related License Submittals and Overlaps
- Reactor Vessel Pressure/Temperature Limits
o Separate pre-submittal teleconferences and meetings will be conducted as needed 10
Summary
- Constellation Energy is committed to safely and reliably implement this power uprate
- Additional meetings are anticipated to maintain close communication 11
Questions?
12