MONTHYEARML0626102462006-12-27027 December 2006 Request for Additional Information Response to Generic Letter 2003-01, Control Room Habitability (TAC Nos. MB9784 and MB9785) Project stage: RAI ML0703803242007-02-0505 February 2007 Request for Additional Information Response to Generic Letter 2003-01, Control Room Habitability Project stage: Request ML0713100282007-05-24024 May 2007 Response to Generic Letter 2003-01 Control Room Habitability Project stage: Other 2007-02-05
[Table View] |
|
---|
Category:Letter
MONTHYEARIR 05000317/20230042024-02-0101 February 2024 Integrated Inspection Report 05000317/2023004 and 05000318/2023004 ML24029A0102024-01-29029 January 2024 Request for Information and Notification of Conduct of IP 71111.21.N.04, Age-Related Degradation, Reference Inspection Report 05000317/2024010 and 05000318/2024010 ML24003A8872024-01-19019 January 2024 Exemption from Select Requirements of 10 CFR Part 73 (EPID L-2023-LLE-0033 (Security Notifications, Reports, and Recordkeeping and Suspicious Activity Reporting)) 05000318/LER-2023-004, Submittal of LER 2023-004-00 for Calvert Cliffs Nuclear Power Plant, Unit 2, Submittal of Automatic Reactor Trip from Reactor Protection System Actuation Due to Loss of Unit Service Transformer2024-01-16016 January 2024 Submittal of LER 2023-004-00 for Calvert Cliffs Nuclear Power Plant, Unit 2, Submittal of Automatic Reactor Trip from Reactor Protection System Actuation Due to Loss of Unit Service Transformer ML24011A0732024-01-11011 January 2024 Proposed Alternative to the Requirements for Repair/Replacement of Saltwater (SW) System Buried Piping 05000318/LER-2023-002, Forward LER 2023-002-00 for Calvert Cliffs Nuclear Power Plant, Unit 2, Automatic Reactor Trip from Reactor Protection System Actuation Due to Loss of Unit Service Transformer2024-01-0808 January 2024 Forward LER 2023-002-00 for Calvert Cliffs Nuclear Power Plant, Unit 2, Automatic Reactor Trip from Reactor Protection System Actuation Due to Loss of Unit Service Transformer 05000318/LER-2023-003, Forward LER 2023-003-00 for Calvert Cliffs Nuclear Power Plant, Unit 2, Manual Actuation of Auxiliary Feedwater System Due to 22 Steam Generator Feedwater Pump Trip2024-01-0808 January 2024 Forward LER 2023-003-00 for Calvert Cliffs Nuclear Power Plant, Unit 2, Manual Actuation of Auxiliary Feedwater System Due to 22 Steam Generator Feedwater Pump Trip ML24005A0222024-01-0505 January 2024 Revised Steam Generator Tube Inspection Reports ML23304A0642024-01-0202 January 2024 Issuance of Amendment No. 349 to Modify the Long-Term Coupon Surveillance Program RS-23-125, Request for Exemption from 10 CFR 2.109(b)2023-12-0707 December 2023 Request for Exemption from 10 CFR 2.109(b) ML23331A2992023-11-27027 November 2023 Submittal of Condition Prohibited by Technical Specifications Due to Failure to Sample Diesel Generator Fuel Oil Storage Tank IR 05000317/20230102023-11-20020 November 2023 Biennial Problem Identification and Resolution Inspection Report 05000317/2023010 and 05000318/2023010 ML23318A4722023-11-14014 November 2023 Supplement to License Amendment Request to Adopt TSTF-59-A ML23317A1032023-11-10010 November 2023 Supplemental Information Letter for Part 73 Exemption Request - Responses to Request for Confirmatory Information ML23317A1192023-11-10010 November 2023 Constellation Energy Generation, LLC - 2023 Annual Report - Guarantees of Payment of Deferred Premiums ML23310A0442023-11-0707 November 2023 Project Manager Assignment IR 05000317/20230402023-11-0202 November 2023 95001 Supplemental Inspection Report 05000317/2023040 and Follow-Up Assessment Letter IR 05000317/20230032023-11-0101 November 2023 Integrated Inspection Report 05000317/2023003 and 05000318/2023003 IR 05000317/20230902023-10-26026 October 2023 Final Significance Determination of a White Finding with Assessment Follow-Up and Notice of Violation; Inspection Report 05000317/2023090 ML23289A1202023-10-16016 October 2023 Request for Exemption from Enhanced Weapons, Firearms Background Checks, and Security Event Notifications Implementation RS-23-097, Constellation Energy Generation, LLC, Advisement of Leadership Changes and Submittal of Updated Standard Practice Procedures Plans2023-10-12012 October 2023 Constellation Energy Generation, LLC, Advisement of Leadership Changes and Submittal of Updated Standard Practice Procedures Plans RS-23-108, Proposed Alternative for Examinations of Examination Categories B-B, B-D, and C-A Steam Generator Pressure Retaining Welds and Full Penetration Welded Nozzles2023-10-11011 October 2023 Proposed Alternative for Examinations of Examination Categories B-B, B-D, and C-A Steam Generator Pressure Retaining Welds and Full Penetration Welded Nozzles RS-23-105, Proposed Alternative for Examinations of Examination Category C-B Steam Generator Nozzle-to-Shell Welds and Nozzle Inside Radius Sections2023-10-10010 October 2023 Proposed Alternative for Examinations of Examination Category C-B Steam Generator Nozzle-to-Shell Welds and Nozzle Inside Radius Sections ML23279A1202023-10-0606 October 2023 Response to NRC Inspection Report and Preliminary White Finding IR 05000317/20230502023-09-29029 September 2023 Special Inspection Report 05000317/2023050 and Preliminary White Finding and Apparent Violation ML23272A1032023-09-29029 September 2023 Condition Prohibited by Technical Specifications Due to Inoperable Nuclear Instrumentation at Very Low Power IR 05000317/20234012023-09-18018 September 2023 Cyber Security Inspection Report 05000317/2023401 and 05000318/2023401 ML23254A0012023-09-0505 September 2023 Registration of Use of Casks to Store Spent Fuel IR 05000317/20230052023-08-31031 August 2023 Updated Inspection Plan for Calvert Cliffs Nuclear Power Plant, Units 1 and 2 (Report 05000317/2023005 and 05000318/2023005) ML23158A1952023-08-30030 August 2023 R. E. Ginna - Issuance of Amendments to Adopt TSTF-273-A, Revision 2, Safety Function Determination Program Clarifications ML23241A8412023-08-29029 August 2023 Response to Request for Additional Information - Proposed Alternative to the Requirements for Repair/Replacement of Saltwater (SW) System Buried Piping ML23240A3872023-08-28028 August 2023 Senior Reactor and Reactor Operator Initial License Examinations ML23151A3472023-08-21021 August 2023 Issuance of Amendments to Adopt TSTF-295-A, Modify Note 2 to Actions of PAM Table to Allow Separate Condition Entry for Each Penetration ML23219A1662023-08-16016 August 2023 Request for Additional Information Regarding Proposed Alternative to the Requirements for Repair/Replacement of Saltwater (SW) System Buried Piping (EPID: L-2023-LLR-0006) - Non-proprietary ML23228A1002023-08-15015 August 2023 Notification of Readiness for NRC 95001 Inspection ML23188A0402023-08-0808 August 2023 Issuance of Amendment Nos. 346 and 324 Adoption of TSTF-577, Revised Frequencies for Steam Generator Tube Inspections, Revision 1 ML23214A1572023-08-0707 August 2023 Correction to the Renewed Facility Operating License Page 3 in Amendment No 345 IR 05000317/20230022023-08-0303 August 2023 Integrated Inspection Report 05000317/2023002 ML23188A0512023-07-13013 July 2023 Correction to the Renewed Facility Operating License Pages in Amendment Nos. 336 and 314 ML23186A0372023-07-13013 July 2023 Correction to the Renewed Facility Operating License Pages in Amendment Nos. 340 and 318 IR 05000317/20233012023-07-12012 July 2023 Initial Operator Licensing Examination Report 05000317/2023301 and 05000318/2023301 IR 05000317/20230122023-07-10010 July 2023 Commercial Grade Dedication Report 05000317/2023012 and 05000318/2023012 ML23180A2362023-06-29029 June 2023 Correction of Errors on Technical Specification Pages RS-23-083, Withdrawal - Proposed Alternatives Related to the Steam Generators2023-06-27027 June 2023 Withdrawal - Proposed Alternatives Related to the Steam Generators ML23156A6752023-06-20020 June 2023 Request for Withholding Information from Public Disclosure for Proposed Alternative to the Requirements for Repair/Replacement of Saltwater System Buried Piping 2024-02-01
[Table view] |
Text
December 27, 2006 Mr. James A. Spina, Vice President Calvert Cliffs Nuclear Power Plant, Inc.
Calvert Cliffs Nuclear Power Plant 1650 Calvert Cliffs Parkway Lusby, MD 20657-4702
SUBJECT:
CALVERT CLIFFS NUCLEAR POWER PLANT, UNIT NOS. 1 AND 2 -
REQUEST FOR ADDITIONAL INFORMATION RE: RESPONSE TO GENERIC LETTER 2003-01, CONTROL ROOM HABITABILITY (TAC NOS. MB9784 AND MB9785)
Dear Mr. Spina:
By letters dated December 5, 2003, and November 23, 2004 (Agencywide Documents Access and Management System (ADAMS) Accession Nos. ML033440342 and ML043380215, respectively), Calvert Cliffs Nuclear Power Plant, Inc., responded to Nuclear Regulatory Commission (NRC) Generic Letter (GL) 2003-01, Control Room Habitability, for Calvert Cliffs Nuclear Power Plant, Unit Nos. 1 and 2 (Calvert Cliffs). In the GL, the NRC staff had requested that licensees confirm that their control rooms meet the design bases (e.g. General Design Criterion (GDC) 1, 3, 4, 5, and 19, draft GDC, or principal design criteria), with special attention to determining that: (1) the most limiting unfiltered and/or filtered inleakage into the control room and comparison to values used in your design bases for meeting control room operator dose limits from accidents (GL 2003-01, Item 1a); (2) the most limiting unfiltered inleakage is incorporated into your hazardous chemical assessments (GL 2003-01, Item 1b); and, (3) the reactor control capability is maintained in the control room or at the alternate shutdown location in the event of smoke (GL 2003-01, Item 1b). The NRC staff had further requested information on any compensatory measures in use to demonstrate control room habitability, and the plans to retire them (GL 2003-01, Item 2).
In GL 2003-01, the NRC staff further requested that licensees assess their Technical Specifications (TSs) to determine if the TSs verify the integrity of the control room envelope (CRE), including ongoing verification of the inleakage assumed in the design basis analysis for control room habitability, and in light of the demonstrated inadequacy of a delta pressure (P) measurement to alone provide such verification (GL 2003-01, Item 1c).
In your December 5, 2003, response, you stated that you do not currently have a TS surveillance requirement for CRE integrity. You further stated that you have established a comprehensive administrative control program for CRE integrity based on Regulatory Guides and Nuclear Energy Institute documents. In your response, you did not mention any plans to adopt TS Task Force (TSTF) Change Traveler TSTF-448, Control Room Habitability.
The NRC staff notes that changes to TSs as proposed in TSTF-448 will be an industry accepted standard to address the potential for excessive inleakage that can increase the radiation exposure to the operators. The staff believes that TSTF-448 will enhance regulatory stability and uniform enforcement. Therefore, the NRC staff requests that you describe your
J. Spina plans to adopt TSTF-448 at Calvert Cliffs. In the event that you decide not to submit an LAR to adopt applicable sections of TSTF-448 into your TSs, the NRC staff requests that you provide an acceptable alternative that will ensure the Calvert Cliffs CRE will be in compliance with the regulations.
This request for additional information was discussed with your staff on December 19, 2006, and it was agreed that your response would be provided within 60 days from the date of this letter.
If you have any questions, please contact me at 301-415-1457.
Sincerely,
/RA/
Patrick Milano, Senior Project Manager Plant Licensing Branch I-1 Division of Operating Reactor Licensing Office of Nuclear Reactor Regulation Docket Nos. 50-317 and 50-318 cc: See next page
ML062610246 OFFICE LPLI-1/PM LPLI-1/LA ACVB/BC PGCB/BC LPLI-1/BC NAME PMilano SLittle RDennig CJackson RLaufer DATE 12/22/06 12/22/06 09/07/06 12/27/06 12/27/06 Calvert Cliffs Nuclear Power Plant, Unit Nos. 1 and 2 cc:
President Ms. Patricia T. Birnie, Esquire Calvert County Board of Co-Director Commissioners Maryland Safe Energy Coalition 175 Main Street P.O. Box 33111 Prince Frederick, MD 20678 Baltimore, MD 21218 Mr. Carey Fleming, Esquire Mr. Roy Hickok Sr. Counsel - Nuclear Generation NRC Technical Training Center Constellation Generation Group, LLC 5700 Brainerd Road 750 East Pratt Street, 17th floor Chattanooga, TN 37411-4017 Baltimore, MD 21202 Mr. Jay S. Gaines Director, Licensing Calvert Cliffs Nuclear Power Plant 1650 Calvert Cliffs Parkway Lusby, MD 20657-4702 Resident Inspector U.S. Nuclear Regulatory Commission P.O. Box 287 St. Leonard, MD 20685 Mr. R. I. McLean, Manager Nuclear Programs Power Plant Research Program Maryland Department of Natural Resources 580 Taylor Avenue (B wing, 3rd floor)
Tawes State Office Building Annapolis, MD 21401 Regional Administrator, Region I U.S. Nuclear Regulatory Commission 475 Allendale Road King of Prussia, PA 19406 Ms. Kristen A. Burger, Esquire Maryland People's Counsel 6 St. Paul Centre Suite 2102 Baltimore, MD 21202-1631