July 7, 2006 LICENSEE:
PPL, Susquehanna, LLC FACILITY:
Susquehanna Steam Electric Station, Units 1 and 2
SUBJECT:
SUMMARY
OF APRIL 5, 2006, CATEGORY 1 MEETING WITH PPL, SUSQUEHANNA, LLC TO DISCUSS THE LICENSEES SCHEDULE FOR LICENSE RENEWAL IN CONJUNCTION WITH AN EXTENDED POWER UPRATE LICENSE AMENDMENT REQUEST (TAC NOS. MC0547 AND MC0548)
On April 5, 2006, a public meeting was held between the U.S. Nuclear Regulatory Commission (NRC, or the staff), and representatives of PPL Susquehanna, LLC at the NRC Headquarters, One White Flint North, 11555 Rockville Pike, Rockville, Maryland. The purpose of the meeting was to discuss PPLs approach and schedule for submitting an application for license renewal (LR) in conjunction with a request for a 14 percent (14%) extended power uprate (EPU) for Susquehanna Steam Electric Station (SSES), Units 1 and 2. A list of participants is provided as.
PPL presented information on three areas related to the EPU license amendment request, provides a description of PPLs work organization for EPU and LR; provides SSES, Units 1 and 2, EPU implementation phases and planned modifications; and Enclosure 4 provides the mid-cycle EPU implementation impacts.
In addition, PPL provided a proposed schedule for license renewal application review based on the NRCs standard license renewal schedule as shown in Enclosures 5 and 6 respectively.
The staff highlighted the major milestones for LR review. A follow up meeting will be scheduled in the near future. One member of the public was in attendance, representing the State of Pennsylvania.
Please direct any inquiries to me at 301-415-1594 or yks@nrc.gov. For inquires related to the EPU amendment request, please contact Mr. Richard Guzman at 301-415-1030.
/RA/
Yoira K. Diaz Sanabria, Project Manager License Renewal Branch A Division of License Renewal Office of Nuclear Reactor Regulation Docket Nos. 50-387 and 50-388
Enclosures:
As Stated cc w/encls: See next page
LIST OF PARTICIPANTS FOR MEETING WITH PENNSYLVANIA POWER LIGHT SUSQUEHANNA, LLC REGARDING PROPOSED LICENSE RENEWAL APPLICATION AND EXTENDED POWER UPRATE APPLICATION APRIL 5, 2006 PARTICIPANTS AFFILIATION Cornelius Holden NRR/DORL Gene Imbro NRR/DE P.T. Kuo NRR/DLR Louise Lund NRR/DLR Yoira K. Diaz Sanabria NRR/DLR/RLRA Richard V. Guzman NRR/DORL/LPLI-1 Jennifer A. Davis NRR/DLR/REBB Chris Jackson NRR/DPR/PGCB Tom Alexion NRR/DPR/PGCB Quynh Nguyen NRR/DPR/PGCB Kamal Manoly NRR/DE/EEMB Richard Laufer NRR/DORL/LPLI-1 Thomas Scarbrough NRC/NRR/DCI/CPTB John Wu NRC/NRR/DE/EEMB Andy du Bouchet NRC/NRR/DE/EEMB Veronica Rodriguez NRC/NRR/DLR/RLRB Bill Rogers NRC/NRR/DE Ken Chang NRC/NRR/DLR/RLRC Jim Davis NRC/NRR/DLR/RLRC Roy Matthew NRC/NRR/DLR/RLRC Ralph Caruso NRC/ACRS Rocco R. Sgarro PPL Susquehanna George T. Jones PPL Susquehanna John A. Bartos PPL Susquehanna Michael B. Detamore PPL Susquehanna John M. Oddo PPL Susquehanna Michael S. Gorski PPL Susquehanna John J. Geosits PPL Susquehanna Brad Fuller DEP Radiation Protection - Pennsylvania
Enclosure 2
Mid Cycle EPU Implementation Impacts All pre-constant power pressure uprate (CPPU) implementation modifications can be pre-installed or installed on line with the exception of one modification.
Current Technical Specifications will not support operation with the Standby Liquid Control (SLC) Modifications.
An outage is required for implementation of SLC Modifications:
- 8 hour9.259259e-5 days <br />0.00222 hours <br />1.322751e-5 weeks <br />3.044e-6 months <br /> limiting condition for operation (LCO) does not support draining and refilling boron storage tank.
- 8 hour9.259259e-5 days <br />0.00222 hours <br />1.322751e-5 weeks <br />3.044e-6 months <br /> LCO does not support implementation of pump logic hardware changes.
- Hardware implementation of pump logic changes in operating panels puts operating unit at risk of a transient.
Other analytic require Pennsylvania Power Light to perform additional analysis which the NRC would need to review.
Early approval of SLC Technical Specification changes would facilitate a smooth mid-cycle implementation of CPPU without the need for an additional outage.
A mid-cycle implementation outage during peak demand has large financial implications.
Operation with CPPU rated (HP) turbine results in a MWe loss at operation creating additional financial implications.
PPL Pre-Outage Decision Points
- SLC Modification Installation based on projected receipt of Technical Specifications.
- HP Turbine installation based on CPPU submittal review progress.
DRAFT LICENSE RENEWAL APPLICATION REVIEW SCHEDULE Milestone Schedule Actual Receive License Renewal (LR) Application
- 09/01/06 Federal Register Notice (FRN) Published - Receipt & Availability 09/08/06 Public Information Meeting - LR Process & Safety Review Overview 09/08/06 FRN Published - Acceptability/Opportunity for Hearing 09/21/06 Audit - Aging Management Programs (AMPs) (1 week on-site) 11/13/06 FRN Published - Intent/Environmental Scoping Meeting 11/17/06 Audit - Scoping and Screening Methodology (1 week on-site) 11/20/06 Public Exit Meeting - Scoping & Screening Methodology Audit 11/27/06 Audit - Aging Management Reviews (AMRs) (1 week on-site) 12/11/06 Environmental Site Audit (1 week on-site) 12/18/06 Deadline for Filing Hearing Requests and Petitions for Intervention 01/05/07 Public Meeting - Environmental Scoping 01/17/07 Environmental Scoping Periods Ends 02/02/07 Public Exit Meeting - AMP/AMR Audit 12/15/06 Environmental Requests for Additional information (RAIs) - Issued 02/09/07 Environmental RAIs - Responses Received 03/16/07 Safety RAIs - Issued (Applicant response time = 30 days) 03/16/07 Safety RAI - Responses Received 04/13/07 Inspection - Scoping and Screening/AMP (2 weeks on-site) 04/16/07 Public Exit Meeting - Scoping & Screening/AMP Inspections 05/11/07 Draft Supplemental Environmental Impact Statement (SEIS) Issued 06/29/07 FRN Published - Availability/Comment on draft SEIS 07/06/07 Public Meeting - draft SEIS 07/13/07 End of draft SEIS Comment Period 08/17/07 Safety Evaluation Report (SER) with Open Item(s) - Issued 11/06/07 ACRS Subcommittee Meeting on SER with Open Item(s) 12/06/07 SER Open Item(s) - Response(s) Received 01/07/08 Final SEIS - Issued 03/31/08 FRN Published - Availability of Final SEIS 04/04/08 Inspection - Optional TBD SER - Issued 04/11/08 FRN Published - Availability of Final SEIS 04/04/08 ACRS Full Committee Meeting on SER 05/15/08 Decision Director NRR (license issued, if approved and no hearing is granted 22 07/07/08 Commission Decision (if hearing is granted - 30 months) 12/xx/08
- NRC assumption 9/1/06 for illustrative purposes
Susquehanna Steam Electric Station, Unit Nos. 1 and 2 cc:
Mr. Britt T. McKinney Sr. Vice President and Chief Nuclear Officer PPL Susquehanna, LLC 769 Salem Blvd., NUCSB3 Berwick, PA 18603-0467 Robert A. Saccone Vice President - Nuclear Operations PPL Susquehanna, LLC 769 Salem Blvd., NUCSB3 Berwick, PA 18603-0467 Aloysius J. Wrape, III General Manager - Performance Improvement and Oversight PPL Susquehanna, LLC Two North Ninth Street, GENPL4 Allentown, PA 18101-1179 Terry L. Harpster General Manager - Plant Support PPL Susquehanna, LLC 769 Salem Blvd., NUCSA4 Berwick, PA 18603-0467 Rocco R. Sgarro Manager - Nuclear Regulatory Affairs PPL Susquehanna, LLC Two North Ninth Street, GENPL4 Allentown, PA 18101-1179 Walter E. Morrissey Supervising Engineer Nuclear Regulatory Affairs PPL Susquehanna, LLC 769 Salem Blvd., NUCSA4 Berwick, PA 18603-0467 Michael H. Crowthers Supervising Engineer Nuclear Regulatory Affairs PPL Susquehanna, LLC Two North Ninth Street, GENPL4 Allentown, PA 18101-1179 Steven M. Cook Manager - Quality Assurance PPL Susquehanna, LLC 769 Salem Blvd., NUCSB2 Berwick, PA 18603-0467 Luis A. Ramos Community Relations Manager, Susquehanna PPL Susquehanna, LLC 634 Salem Blvd., SSO Berwick, PA 18603-0467 Bryan A. Snapp, Esq Assoc. General Counsel PPL Services Corporation Two North Ninth Street, GENTW3 Allentown, PA 18101-1179 Supervisor - Document Control Services PPL Susquehanna, LLC Two North Ninth Street, GENPL4 Allentown, PA 18101-1179 Richard W. Osborne Allegheny Electric Cooperative, Inc.
212 Locust Street P.O. Box 1266 Harrisburg, PA 17108-1266 Director, Bureau of Radiation Protection Pennsylvania Department of Environmental Protection Rachel Carson State Office Building P.O. Box 8469 Harrisburg, PA 17105-8469 Senior Resident Inspector U.S. Nuclear Regulatory Commission P.O. Box 35, NUCSA4 Berwick, PA 18603-0035 Regional Administrator, Region 1 U.S. Nuclear Regulatory Commission 475 Allendale Road King of Prussia, PA 19406
Susquehanna Steam Electric Station, Unit Nos. 1 and 2 cc:
Board of Supervisors Salem Township P.O. Box 405 Berwick, PA 18603-0035 Dr. Judith Johnsrud National Energy Committee Sierra Club 443 Orlando Avenue State College, PA 16803 Please direct any inquiries to me at 301-415-1594 or yks@nrc.gov. For inquires related to the EPU amendment request, please contact Mr. Richard Guzman at 301-415-1030.
/RA/
Yoira K. Diaz Sanabria, Project Manager License Renewal Branch A Division of License Renewal Office of Nuclear Reactor Regulation Docket Nos. 50-387 and 50-388
Enclosures:
As Stated cc w/encls: See next page Accession Number: ML061720220 OFFICE NRR/RLRA/P M
NRR/RLRA/LA NRR/DORL/PM NRR/RLRA/BC NAME YDiazSanabria IKing RGuzman LLund DATE 6/26/06 6/23/06 7/ 7 /06 6/30/06
OFFICIAL RECORD COPY