Proposed Control Room JPMs for the Braidwood Initial Examination - May 2006
ML061710356
Person / Time
Site: Braidwood  Constellation icon.png
Issue date: 05/15/2006
From: Mcneil D
NRC/RGN-III/DRS/OLB
To:
References
Download: ML061710356 (46)


Text

TASK TITLE: Emergency Borate During an ATWS from RWST JPM No.: SIM-108 REV: NRC2006301 TPO No.: 4D.OA-08 K&A No.: 000029EK3.12 TASK No.: R-FR-018, Respond to an ATWS K&A IMP: 4.4/4.7 TRAINEE: SRO EVALUATOR: DATE:

The Trainee: PASSED this JPM. TIME STARTED:

FAILED TIME FINISHED:

JPM TIME: MINUTES CRITICAL ELEMENTS: (*) 4, 5, 6 APPROX COMPLETION TIME 10 MINUTES CRITICAL TIME: NA EVALUATION METHOD: LOCATION:

X PERFORM IN PLANT SIMULATE X SIMULATOR GENERAL

REFERENCES:

1. 1BwFR-S.1, Rev. 1A WOG 1C, Response to Nuclear Power Generation/ATWS.

MATERIALS:

1. 1BwFR-S.1, Rev. 1A WOG 1C TASK STANDARDS:
1. Determine emergency boration flowpath from BAST unavailable.
2. Manually align CV system to perform emergency boration of RCS from the RWST prior to completion of step 4 of 1BwFR-S.1.

TASK CONDITIONS:

1. You are an extra NSO.
2. The turbine has tripped without a reactor trip from high power.
3. 1BwFR-S.1. Response to Nuclear Power Generation/ATWS is in progress.

INITIATING CUES:

1. The simulator is frozen and annunciator panel horns are turned off.
2. The US has directed you to perform an Emergency Boration per step 4 of 1BwFR-S.1. All other steps of 1BwFR-S.1 are being addressed by other NSOs. All annunciator horns are silenced.
3. Notify the US when emergency boration flow has been initiated.
4. When you are ready to begin the JPM, the simulator will be placed in run.

Annunciator horns will be left OFF to minimize noise during JPM performance.

1 SIM-108

RECORD START TIME Note: After giving the initiating cue, cue the simulator operator to start the simulator.

PERFORMANCE STEP STANDARD Circle applicable

1. Refer to 1BwFR-S.1 Step 4 Locate and Open 1BwFR-S.1 SAT UNSAT N/A Note: Examinee will use to Step 4 Comments:

simulator copy of 1BwFR-S.1 for JPM performance.

2. Check at least one Determine one CV pump is SAT UNSAT N/A Centrifugal Charging pump running: Comments:

running

  • OBSERVE RUN light indication and/or ammeter for 1A CV pump
3. Initiate emergency boration Attempt to initiate SAT UNSAT N/A from BAST emergency boration from Comments:

the BAST as follows:

  • Attempt to OPEN 1CV8104
  • Determine emergency boration flow cannot be established from BAST Note: Alternate path begins here Examiners note: 1BwFR-S.1 step 4 RNO column allows establishing emergency boration flow from either the RWST or BAST (using normal RMCS boration flowpath). If examinee attempts to establish emergency boration via RMCS, the boric acid transfer pump will not start. (See JPM step 6 if examinee attempts emergency boration via RMCS)
  • 4 Align CV pump suction to the Perform the following at SAT UNSAT N/A RWST 1PM05J: Comments:
  • OPEN 1CV112D and/or 1CV112E
  • 5 Isolate CV pump suction from Perform the following at SAT UNSAT N/A the VCT 1PM05J: Comments:
  • CLOSE 1CV112B and/or 1CV112C 2

SIM-108

PERFORMANCE STEP STANDARD Circle applicable

  • 6 Maximize Charging flow Perform the following at SAT UNSAT N/A 1PM05J: Comments:
  • Place 1CV121 in manual and raise demand o OBSERVE 1FI-121A increasing o VERIFY letdown established Examiners note: 1BwFR-S.1 step 4 RNO column allows establishing emergency boration flow from either the RWST or BAST (using normal RMCS boration flowpath). If examinee attempts to establish emergency boration via RMCS, the boric acid transfer pump will not start. See JPM step 4 for emergency boration via RWST steps.
7. Initiate emergency boration Attempt to initiate SAT UNSAT N/A from RMCS (N/A if not emergency boration from Comments:

performed) RMCS as follows:

  • OPEN 1CV110A
  • OPEN 1CV110B
  • Determine emergency boration flow cannot be established from RMCS
8. Check Pressurizer Pressure < CHECKS Pzr Pressure < SAT UNSAT N/A 2335 psig 2335 psig as follows: Comments:
  • OBSERVES PZR Pressure indicators o Operate PZR PORV(s) as necessary until pressure <2135 psig, then close PZR PORV(s)
9. Notify Unit Supervisor Perform the following: SAT UNSAT N/A CUE: Acknowledge reports. o Notify the Unit Comments:

Supervisor emergency boration flow is established o Notify Unit Supervisor of 1CV8104 failure to open CUE: THIS COMPLETES THIS JPM.

RECORD STOP TIME COMMENTS:

3 SIM-108

TASK CONDITIONS:

1. You are an extra NSO.
2. The turbine has tripped without a reactor trip from high power.
3. 1BwFR-S.1. Response to Nuclear Power Generation/ATWS is in progress.

INITIATING CUES:

1. The simulator is frozen and annunciator panel horns are turned off.
2. The US has directed you to perform an Emergency Boration per step 4 of 1BwFR-S.1.

All other steps of 1BwFR-S.1 are being addressed by other NSOs. All annunciator horns are silenced.

3. Notify the US when emergency boration flow has been initiated.
4. When you are ready to begin the JPM, the simulator will be placed in run.

Annunciator horns will be left OFF to minimize noise during JPM performance.

4 SIM-108

SIMULATOR SETUP GUIDE:

  • Verify/perform TQ-BR-201-0113, BRAIDWOOD TRAINING DEPARTMENT SIMULATOR EXAMINATION SECURITY ACTIONS CHECKLIST.
  • Establish the conditions of IC 21, 100% power, steady state, equilibrium xenon.
  • Complete items on Simulator Ready for Training Checklist
  • Place simulator in RUN.
  • Run caep SIM-108 from disk and verify the following actuate:
  • IMF RP02A
  • IMF RP02B
  • IOR ZDI1CV8104 CLS
  • IMF CV03
  • IOR ZDIRMIO IN
  • IOR ZDIBKSEL MAN
  • IRF TC03 TRIP
  • Start both AF pumps.
  • Place simulator in freeze.
  • Turn off simulator horns.
  • Verify simulator copy of 1BwFR-S.1 is place kept through step 3.

Verify all other place keeping marks removed.

  • At examiners cue, place simulator in run.
  • If running the JPM repetitively, perform the following:
  • Open 1CV112B & C
  • Close 1CV112D & E
  • Restore 1CV121 to automatic
  • Verify simulator copy of 1BwFR-S.1 is place kept through step 3.

Verify all other place keeping marks removed.

  • Place simulator in freeze.
  • Turn off simulator horns.

COMMENTS:

(Final) 5 SIM-108

TASK TITLE: Establish Automatic Pzr Level Control with Failed 1CV121 JPM No.: SIM-219 REV: NRC2006301 TPO No.: 4C.GP-06 K&A No.: 011000A4.04 TASK No.: R-GP-053, Transfer Pzr level control K&A IMP: 3.2/2.9 from manual to automatic.

TRAINEE: SRO EVALUATOR: DATE:

The Trainee: PASSED this JPM. TIME STARTED:

FAILED TIME FINISHED:

JPM TIME: MINUTES CRITICAL ELEMENTS: (*) 2, 4 APPROX COMPLETION TIME 8 MINUTES CRITICAL TIME: NA EVALUATION METHOD: LOCATION:

X PERFORM IN PLANT SIMULATE X SIMULATOR GENERAL

REFERENCES:

1. 1BwGP 100-1, Rev. 22, Plant Heatup.

MATERIALS:

1. 1BwGP 100-1, Rev. 22, Step 62.

TASK STANDARDS:

1. Determine 1CV121 failed high.
2. Operate 1CV121 in manual to control pressurizer level and RCP seal injection flow prior to completing 1BwGP 100-1, step F.62.

TASK CONDITIONS:

1. You are the Unit 1 NSO.
2. The Unit is at full power.
3. One hour ago, Pzr Level Channel 1LT-459 was restored from test.
4. Actual pressurizer level and demanded pressurizer level have been matched for 16 minutes.

INITIATING CUES:

1. The US has directed you restore automatic pressurizer level control per the applicable portions of step F.62 of 1BwGP 100-1.
2. Inform the US when automatic pressurizer level control is established.

1 SIM-219

RECORD START TIME PERFORMANCE STEP STANDARD Circle applicable

1. Refer to 1BwGP 100-1 step 62 Locate and open 1BwGP SAT UNSAT N/A Note: Examinee will use 100-1 to step F.62 Comments:

simulator copy of 1BwGP 100-1 for JPM performance.

CUE: All Prerequisites, Precautions, Limitations and Actions have been met.

Examiners note: When examinee places 1FK-121 in automatic, 1CV121 will fail to 100%

open.

  • 2. Place Pressurizer Level Perform the following at SAT UNSAT N/A control in Automatic 1PM05J to establish Comments:

automatic pressurizer level control:

o ADJUST 1CV121 in MANUAL to match PZR actual level with demanded level o MAINTAIN PZR actual and demanded level equal for 10-15 minutes o VERIFY/PLACE 1LK-459, Master Pzr Level Controller in MANUAL

  • PLACE 1CV121 in AUTO Note: Alternate path begins here
3. Identify 1FK-121 (1CV121) Identify 1FK-121 (1CV121) SAT UNSAT N/A failure failure Comments:

o Annunciator 1-9-D3, CHG LINE FLOW HIGH/LOW o Identify 1CV121 demand signal rising to 100% and 1CV121 throttling to full open 2

SIM-219

PERFORMANCE STEP STANDARD Circle applicable

  • 4. Mitigate the pressurizer Perform the following to SAT UNSAT N/A level transient caused by an mitigate the failure of Comments:

increase in charging flow 1CV121:

  • REDUCE demanded signal to throttle charging flow to maintain a stable pressurizer level at program value with no seal injection low flow annunciators lit.
5. Inform US of 1CV121 Inform US of 1CV121 SAT UNSAT N/A controller failure. failure Comments:

CUE: As US, acknowledge failure of 1CV121 and that you will inform maintenance CUE: THIS COMPLETES THIS JPM.

RECORD STOP TIME COMMENTS:

3 SIM-219

TASK CONDITIONS:

1. You are the Unit 1 NSO.
2. The Unit is at full power.
3. One hour ago, Pzr Level Channel 1LT-459 was restored from test.
4. Actual pressurizer level and demanded pressurizer level have been matched for 16 minutes.

INITIATING CUES:

1. The US has directed you restore automatic pressurizer level control per the applicable portions of step F.62 of 1BwGP 100-1.
2. Inform the US when automatic pressurizer level control is established.

4 SIM-219

SIMULATOR SETUP GUIDE:

  • Verify/perform TQ-BR-201-0113, BRAIDWOOD TRAINING DEPARTMENT SIMULATOR EXAMINATION SECURITY ACTIONS CHECKLIST.
  • Establish the conditions of IC 21, 100% power, steady state, equilibrium xenon.
  • Complete items on Simulator Ready for Training Checklist
  • Place simulator in RUN.
  • Place 1CV121 in MANUAL
  • Place Master PZR Level Controller to MANUAL
  • Insert IMF CV10 100
  • Verify 1BwGP 100-1 place keeping marks are removed.

COMMENTS:

(Final) 5 SIM-219

TASK TITLE: Raise SI Accumulator Level with 1A SI pump (375 psig in RCS)

JPM Number: SIM-204 Rev. NRC2006301 TPO No.: 4C.SI-02 K&A No.: 006000A1.13 Task No.: R-SI-001, Fill the SI accumulators K&A Imp.: 3.5/3.7 TRAINEE: SRO EVALUATOR: DATE:

The Trainee: PASSED this JPM. TIME STARTED:

FAILED TIME FINISHED:

JPM TIME: MINUTES Critical Elements: (*) 4, 6, 9, 11-13, 16, 21, 22 Approx. Completion Time: 45 minutes Critical Time: N/A EVALUATION METHOD: LOCATION:

X PERFORM IN PLANT SIMULATE X SIMULATOR GENERAL

REFERENCES:

1. BwAR 1-5-C1, Rev. 8E2, ACCUM 1C LEVEL HIGH/LOW
2. BwAR 1-5-C2, Rev 6E3, ACCUM 1C PRESS HIGH/LOW
3. BwOP SI-5, Rev. 22, Raising SI Accumulator Level with SI Pumps
4. BwOP SI-9, Rev 11, Lowering SI Accumulator Pressure
5. Tech Spec 3.5.1 MATERIALS:
1. Copy of BwAR 1-5-C1
2. Copy of BwAR 1-5-C2, if needed
3. Copy of BwOP SI-5
4. Copy of BwOP SI-9, if needed TASK STANDARDS:
1. Determine 1A SI train required to be isolated from RCS cold legs during fill of 1C SI Accumulator.
2. Restore 1C SI Accumulator Level within Tech. Spec. limit prior to completion of BwOP SI-5, step F.8b.5.
3. Restore 1C SI Accumulator Level within Tech. Spec. limit prior to JPM completion.

TASK CONDITIONS:

1. You are the Unit 1 Extra NSO.
2. RCS heat up is in progress per 1BwGP 100-1.
3. Unit 1 is in Mode 3, RCS temperature is 360°F and RCS pressure is 375 psig.
4. All systems and controls are normal for the present conditions.

INITIATING CUES:

1. Annunciator 1-5-C1, ACCUM 1C LEVEL HIGH/LOW, has been is lit.
2. The US has directed you to raise the 1C accumulator level to > 38% but within the Technical Specification limit by using the 1A SI pump. Other control room operators are maintaining all other plant conditions. NLOs have been briefed and are standing by as needed.
3. Inform the US when you have restored 1C SI accumulator level.
4. There a NO personnel in Unit 1 Containment.

1 SIM-204

RECORD START TIME PERFORMANCE STEP STANDARD Circle applicable

1. Refer to BwAR 1-5-C1, ACCUM Locate and open SAT UNSAT N/A 1C LEVEL HIGH LOW BwAR 1-5-C1 and perform Comments:

CUE: When student locates the following:

correct procedure, o Monitor 1LI-954 and provide copy. 955 to determine level CUE: If asked as US, is low.

confirm that DEQUIP o Monitor SER points has been entered for 0581 and 2042 to 1C SI Accumulator determine level is level, LCO 3.4.13 has low.

been reviewed, and AAR 1BwOS SI-1a is being

  • Monitor 1PI-964 and reviewed. 965 to determine pressure is stable.

o Notify US to enter LCO 3.5.1.

2. Refer to BwOP SI-5, Raising Locate and open BwOP SI- SAT UNSAT N/A SI Accumulator Level with SI 5: Comments:

Pumps.

CUE: When examinee locates correct procedure, provide copy.

CUE: All Prerequisites, Precautions, Limitations and Actions are met.

CUE: If asked as US, RWST recirc pump and purification loop are not running, and RWST boron is 2300 ppm and has not been diluted since last sampled.

Examiners note: 1SI8806 and 8813 are SVAG valves and are maintained deenergized.

Their position may be verified on the 1PM06J Group 1 or 4 Readiness Lights, 1PM06J SVAG Valve Status Lights, or locally. The examinee should NOT energize 1SI8806 and/or 1SI8813 per BwOP SI-100 in order to check 1SI8806 and/or 1SI8813 position using the indicating lights at 1PM06J. Energizing 1SI8806 and/or 1SI8813 is NOT necessary since the valves are in their correct position and energizing 1SI8806 and/or 1SI8813 would make BOTH trains of ECCS inoperable and unnecessarily place Unit 1 in Tech Spec 3.5.2.

2 SIM-204

PERFORMANCE STEP STANDARD Circle applicable

3. Verify valve alignment. At 1PM06J, perform the SAT UNSAT N/A (steps F.1 - F.4) following: Comments:

CUE: If asked to verify

  • VERIFY/OPEN:

valves locally, as NLO

  • 1SI8806 report all valves are
  • 1SI8923A OPEN.

o 1SI8923B

  • 1SI8814
  • 1SI8813 o 1SI8920

(step F.5)

  • OPEN 1SI8888
5. Verify SI to Radwaste At 1PM11J, perform the SAT UNSAT N/A flowpath isolated. following: Comments:

(step F.6)

  • Verify/CLOSE 1SI8964
  • 6. Align Accumulator for fill. At 1PM06J, perform the SAT UNSAT N/A (step F.7) following: Comments:
  • OPEN 1SI8871
7. Determine applicable plant Determine plant status SAT UNSAT N/A status for accumulator fill for accumulator fill Comments:

(step F.8)

  • Unit 1 in Mode 3 (RCS temperature > 350°F, Keff <0.99)
  • RCS pressure 1850 psig
  • Determine BwOP SI-5, step F.8.b applicable for 1C SI accumulator fill
8. Initiate LCOAR 1BwOL 3.5.2. Inform US of need to SAT UNSAT N/A (step F.8.b) enter LCOAR 1BwOL 3.5.2. Comments:

CUE: As US, acknowledge

  • Determine LCO 3.5.2 LCOAR 3.5.2 entry entry required prior requirement. to closing 1SI8821A 3

SIM-204

PERFORMANCE STEP STANDARD Circle applicable

  • 9. Isolate 1A SI Pump from Cold At 1PM06J, VERIFY/CLOSE: SAT UNSAT N/A Legs.
  • 1SI8821A Comments:

(step F.8.b.1)

Examiners note: 1SI8802A is SVAG valve and is maintained deenergized; its position may be verified on the 1PM06J Group 1 or 5 Readiness Lights, 1PM06J SVAG Valve Status Lights, or locally. The examinee should NOT energize 1SI8802A per BwOP SI-100 in order to check valve position using the indicating lights at 1PM06J. Energizing 1SI8802A is NOT necessary since it is in their correct position and energizing 1SI8802A would make BOTH trains of ECCS inoperable and unnecessarily place Unit 1 in Tech Spec 3.5.2.

10. Verify/close 1SI8802A, SI to At 1PM06J, perform the SAT UNSAT N/A Hot Legs 1A and 1D Isol vlv. following: Comments:

(step F.8.b.2)

  • VERIFY/CLOSE 1SI8802A CUE: If asked to verify 1SI8802A position locally, as NLO report 1SI8802A is CLOSED.

Examiners note: Student may elect to have an NLO do a prestart check of 1A SI pump prior to starting. If so, provide the following CUE:

CUE: NLO reports that the 1A SI Pump is ready for a start.

  • 11. Start 1A SI pump. At 1PM06J, perform the SAT UNSAT N/A (step F.8.b.3) following: Comments:

CUE: If dispatched as NLO o Announce pump start on to monitor pump start plant page locally, report

  • Start 1A SI Pump.

satisfactory start of o Check 1A SI Pump Run 1A SI pump shortly Light LIT.

after pump started.

o Check 1A SI Pump amps.

  • 12. Fill 1C Accumulator. At 1PM06J, perform the SAT UNSAT N/A (step F.8.b.4) following: Comments:
  • 13. Stop filling accumulator At 1PM06J, perform the SAT UNSAT N/A when level is within Tech following: Comments:

Spec limits.

  • CLOSE 1SI8878C when (step F.8.b.5) Accumulator Level is Note: Per the initiating >38%, but prior to cue, direction was exceeding 63%.

given to restore

  • Inform US 1C SI level to >38% but < Accumulator level 63%. restored within Tech CUE: As US, acknowledge Spec limits.

report of 1C SI Accumulator level restoration.

4 SIM-204

PERFORMANCE STEP STANDARD Circle applicable

14. Stop 1A SI pump. At 1PM06J, perform the SAT UNSAT N/A (step F.8.b.6) following: Comments:
  • Stop 1A SI Pump.

o Check 1A SI Pump Stop Light LIT.

15. Depressurize SI pump Depressurize the fill SAT UNSAT N/A discharge header to less header to less than 50 Comments:

than 50 psig. psig:

(step F.8.b.7 - F.8.b.8)

  • At 1PM11J, open 1SI8964
  • When pressure is less than 50 psig, perform the following at 1PM11J:
  • CLOSE 1SI8964
  • 16. Restore 1A SI pump to Cold At 1PM06J, perform the SAT UNSAT N/A Legs. following: Comments:

(step F.8.b.9)

  • OPEN 1SI8821A CUE: Acknowledge exit LCOAR 1BwOL 3.5.2.
17. Isolate SI pump from At 1PM06J, close SAT UNSAT N/A Accumulator. Fill/Test line Isolation Comments:

(step F.11 & F.12) valves:

  • 1SI8871
  • 1SI8888
18. Inform US that it may be Inform US of the SAT UNSAT N/A necessary to initiate 1BwOS following potential Comments:

SI-1A, and to contact requirements:

chemistry for Accumulator

  • 1BwOS SI-1a samples, and exit LCOAR for level.

CUE: US will evaluate the

  • Exit LCOAR from need to perform 1BwOS Accumulator level.

SI-1a and will inform chemistry, and exit LCOAR.

5 SIM-204

PERFORMANCE STEP STANDARD Circle applicable Examiners note: If 1C SI accumulator rises enough to cause annunciator 1-5-B2 to alarm during accumulator fill, examinee will perform JPM steps 19-23 to lower 1C SI accumulator pressure. If annunciator 1-5-B2 is not in alarm, end JPM here and mark steps 19-23 N/A.

19. Refer to BwAR 1-5-C2 Locate and open SAT UNSAT N/A CUE: When student locates BwAR 1-5-C2 and perform Comments:

correct procedure, the following:

provide copy. o Monitor 1PI-964 and CUE: If asked as US, 965 to determine confirm that the LCOAR pressure is high.

(1BwOL 3.5.1) has been o Monitor SER points entered, LCO 3.4.13 0578 and 2045 to has been reviewed, and determine level is AAR 1BwOS SI-1a is low.

being reviewed.

  • Monitor 1LI-954 and 955 to determine level is stable.

o Notify US to enter LCO 3.5.1.

20. Refer to BwOP SI-9, Lowering Perform the following SAT UNSAT N/A SI accumulator pressure.
  • Locate and open BwOP Comments:

CUE: After examinee locates SI-9.

copy of procedure, provide a copy and

  • Determine step F.1 is inform them all the applicable step.

prerequisites, precautions, limitations and actions are met

CUE: If asked, as US inform pressure to 625 psig:

examinee that there are no personnel in o Verify / Close 1AOV-Unit 1 containment. SI8880, N2 Supply Isolation valve o Verify / Close 1SIHCV943, Vent control valve

  • Throttle open 1SIHCV943, Vent control valve o Monitor 1PI-964/965 6

SIM-204

PERFORMANCE STEP STANDARD Circle applicable

  • 22. Secure lowering 1B SI Perform the following SAT UNSAT N/A accumulator pressure.
  • Verify 1C SI Comments:

accumulator pressure 612-637 psig

23. Exit LOCAR 1BwOL 3.5.1 Inform US that pressure SAT UNSAT N/A is within the Tech Spec Comments:

limit, the alarm cleared, CUE: US acknowledges and the LCOAR may be pressure restored and exited.

exits LCOAR.

CUE: THIS COMPLETES THIS JPM.

RECORD STOP TIME COMMENTS:

7 SIM-204

TASK CONDITIONS:

1. You are the Unit 1 Extra NSO.
2. RCS heat up is in progress per 1BwGP 100-1.
3. Unit 1 is in Mode 3, RCS temperature is 360°F and RCS pressure is 375 psig.
4. All systems and controls are normal for the present conditions.

INITIATING CUES:

1. Annunciator 1-5-C1, ACCUM 1C LEVEL HIGH/LOW, has been is lit.
2. The US has directed you to raise the 1C accumulator level to > 38% but within the Technical Specification limit by using the 1A SI pump. Other control room operators are maintaining all other plant conditions. NLOs have been briefed and are standing by as needed.
3. Inform the US when you have restored 1C SI accumulator level.
4. There a NO personnel in Unit 1 Containment.

8 SIM-204

SIMULATOR SETUP GUIDE:

  • Verify/perform TQ-BR-201-0113, BRAIDWOOD TRAINING DEPARTMENT SIMULATOR EXAMINATION SECURITY ACTIONS CHECKLIST.
  • Establish the conditions of IC 5, BOL hot shutdown, plant heat up in progress, 340°F, 375 psig.
  • Complete items on Simulator Ready for Training Checklist.
  • Place simulator in RUN.
  • Place 1B CV pump, 1A SI pump, and 1B SI pump in NAT.
  • Remove placards from 1SI8808A-D C/S.
  • Allow the RCS to heat up above 350°F.
  • Modify SIMACC[3] TO 57,280 to lower 1C SI Accumulator level to 30%.
  • Place RCS Heatup Limits graphic display on right hand MCR CRT.
  • Verify/remove 1A SI pump data from HMI terminal screens.
  • Replace 1SI8808A-D placards when all examinees have completed JPM.

COMMENTS:

  • Provide copy of BwAR 1-5-C1, Rev. 8E2
  • Provide copy of BwAR 1-5-C2, Rev 6E3
  • Provide copy of BwOP SI-5, Rev. 22
  • Provide copy of BwOP SI-9, Rev 11 (Final) 9 SIM-204

TASK TITLE: Swap Essential Service Water Pumps JPM No.: SIM-S403 REV: NRC2006301 TPO No.: 4C.SX-03 K&A No.: 075000A4.01 TASK No.: R-SX-004, Operate the SX system K&A IMP: 3.2/3.2 TRAINEE: SRO EVALUATOR: DATE:

The Trainee: PASSED this JPM. TIME STARTED:

FAILED TIME FINISHED:

JPM TIME: MINUTES CRITICAL ELEMENTS: (*) 4, 6, 8 APPROX COMPLETION TIME: 25 MINUTES CRITICAL TIME: NA EVALUATION METHOD: LOCATION:

X PERFORM IN PLANT SIMULATE X SIMULATOR GENERAL

REFERENCES:

1. BwOP SX-7, Rev. 16, Swapping Essential Service Water Pumps.

MATERIALS:

1. BwOP SX-7, Rev. 16, Swapping Essential Service Water Pumps.

TASK STANDARDS:

1. Manually open 1SX016B prior to completing BwOP SX-7, step F.2.
2. Start the 1B SX pump prior to securing the 1A SX pump.

TASK CONDITIONS:

1. You are the Assist NSO.
2. Both Units are at 100% power.
3. Unit 2 has placed the 2A SX pump in service 5 minutes ago and requests that Unit 1 swap operating SX trains. 1B SX pump has been shutdown for 2 weeks.
4. NLOs have been briefed and are standing by to assist in the field.

INITIATING CUES:

1. The US has directed you to start the 1B SX pump and shutdown the 1A SX pump per BwOP SX-7.
2. Inform the US when you have completed the pump swap.

1 SIM-S403

RECORD START TIME PERFORMANCE STEP STANDARD Circle applicable

1. Refer to BwOP SX-7. Locate and open BwOP SX- SAT UNSAT N/A CUE: When examinee locates 7. Comments:

correct procedure, provide copy.

CUE: All Prerequisites, Precautions, Limitations and Actions have been met.

2. Verify 1B SX pump suction Perform the following at SAT UNSAT N/A valve open. 1PM06J: Comments:

CUE: If requested, NLO

  • Verify/Open 1SX001B.

reports that 1SX001B is open.

3 Verify 1PR03J in service Perform the following at SAT UNSAT N/A the RM-11 console Comments:

o Verify 1PR03J cursor status indicates normal (green) on grid 1, grid 5, or grid 6.

  • 4. Verify RCFC 1B and 1D inlet Perform the following at SAT UNSAT N/A and outlet valves open. 1PM06J: Comments:
  • Place control switch for 1SX016B to OPEN.

o Verify/Open 1SX027B.

5. Start 1A and 1B SX pump Aux. Direct NLO to locally SAT UNSAT N/A Oil pumps. start 1A and 1B SX pump Comments:

Aux. Oil pumps.

(1SX01PA/B-C)

Note: Simulator operator to start both Unit 1SX o At 1PM06J verify 1A pump aux. oil pumps and 1B SX pump Aux.

when called. Oil pump run lights lit.

2 SIM-S403

PERFORMANCE STEP STANDARD Circle applicable

  • 6. Start 1B SX pump. Perform the following at SAT UNSAT N/A CUE: If contacted as Unit 2 1PM06J: Comments:

operator, acknowledge o Announce pump swap upcoming SX pump over plant page swap.

  • Start 1B SX pump by CUE: If dispatched as NLO taking the control to monitor 1B SX pump switch to CLOSE until start locally, report pump starts.

satisfactory start of 1B SX pump shortly after pump started.

7. Check running SX pumps Perform the following at SAT UNSAT N/A parameters. 1PM06J: Comments:
  • Check ammeters for 1A and 1B SX pumps
  • Determines 1A and 1B SX pumps amps approximately equal.
  • Determines 1A and 1B SX pumps discharge pressure < 112 psig.
  • 8. Stop 1A SX pump. Perform the following at SAT UNSAT N/A CUE: If dispatched as NLO 1PM06J: Comments:

to monitor 1A SX pump

  • Stops 1A SX pump by stop locally, report placing the control satisfactory stop of switch to TRIP.

1A SX pump shortly

  • Determines step F.7 is after pump stopped. NOT applicable (1B SX pump and 2A SX pump are running)
9. Check 1B SX pump local Direct NLO to check the SAT UNSAT N/A operating conditions. following local operating Comments:

CUE: As NLO, report all conditions:

local operating

  • SX pump lube oil conditions for the temperature: 50-130 pump and strainer are °F.

normal.

  • SX pump seals not leaking.
  • SX pump bearing bracket drain holes not plugged.
  • Oil flow in bearing oil return sightglass.
  • 1SX01FB, strainer control switch for 1B SX pump in AUTO.

CUE: As NLO, report 1A SX pump is not rotating.

  • 1A SX pump is not reverse rotating.

3 SIM-S403

PERFORMANCE STEP STANDARD Circle applicable

11. Stop Aux. Oil pumps. Perform the following: SAT UNSAT N/A
  • Direct NLO to Stop Comments:

Aux. Oil pumps for 1A and 1B SX pumps CUE: As NLO, report 1A & 1B SX pump Aux Oil pumps off as

  • Verify 1A and 1B SX they are secured. pumps Aux. Oil pump run lights OFF at 1PM06J.
12. Startup 1B and 1D RCFC and Perform the following at SAT UNSAT N/A Shutdown 1A and 1C RCFC. 1PM06J: Comments:
  • Verify All RCFCs are CUE: All RCFCs are required already running.

for containment

  • Determine all RCFC cooling. required for CNMT cooling
13. Ensure SX Chem Feed system Direct NLO to perform SAT UNSAT N/A aligned properly. BwOP CF-36 as required. Comments:

CUE: As NLO, acknowledge (N/A if examinee request. determines step not required)

14. Inform US SX pump swap Inform US SX pump swap Inform US SX pump swap complete complete complete CUE: Acknowledges report.

CUE: THIS COMPLETES THIS JPM.

RECORD STOP TIME COMMENTS:

4 SIM-S403

TASK CONDITIONS:

1. You are the Assist NSO.
2. Both Units are at 100% power.
3. Unit 2 has placed the 2A SX pump in service 5 minutes ago and requests that Unit 1 swap operating SX trains. 1B SX pump has been shutdown for 2 weeks.
4. NLOs have been briefed and are standing by to assist in the field.

INITIATING CUES:

1. The US has directed you to start the 1B SX pump and shutdown the 1A SX pump per BwOP SX-7.
2. Inform the US when you have completed the pump swap.

5 SIM-S403

SIMULATOR SETUP GUIDE:

  • Verify/perform TQ-BR-201-0113, BRAIDWOOD TRAINING DEPARTMENT SIMULATOR EXAMINATION SECURITY ACTIONS CHECKLIST.
  • Establish the conditions of IC 21, 100% power, steady state, equilibrium xenon.
  • Complete items on Simulator Ready for Training Checklist
  • Place simulator in RUN.
  • Verify/start 1A SX pump
  • Verify/stop 1B SX pump
  • Close 1SX016B RCFC 1B and 1D inlet isolation valve.
  • Remove SX Pump Trends from the HMI.
  • Run caep SIM-S403 from disk and verify the following actuate:
  • trgset 1 "ZLO1SX01PB(3)==1"
  • trg 1 "IMF SW04 (0 3) 15000"
  • trgset 2 "ZDI1SX01PA(1)==1"
  • trg 2 "DMF SW04"
  • To start/stop SX Pump Aux Oil Pumps, use the following remote functions:
  • RF SW03 ON / OFF
  • RF SW04 ON / OFF COMMENTS:
  • Provide copy of BwOP SX-7, Rev. 16 (Final) 6 SIM-S403

TASK TITLE: Synchronize 1A EDG to Bus 141 and respond to Gov. Adj. malfunction.

JPM No.: SIM-608 REV: NRC2006301 TPO No.: 4C.DG-06 K&A No.: 064000A4.06 TASK No.: R-DG-015, Operate the EDG K&A IMP: 3.9/3.9 TRAINEE: SRO EVALUATOR: DATE:

The Trainee: PASSED this JPM. TIME STARTED:

FAILED TIME FINISHED:

JPM TIME: MINUTES CRITICAL ELEMENTS: (*) 3, 4, 6 APPROX. COMPLETION TIME: 18 MINUTES CRITICAL TIME: NA EVALUATION METHOD: LOCATION:

X PERFORM IN PLANT SIMULATE X SIMULATOR GENERAL

REFERENCES:

1. BwOP DG-11, Rev. 30, Diesel Generator Startup
2. 1BwOSR 3.8.1.2-1, Rev. 15, Unit One 1A Diesel Generator Operability Surveillance MATERIALS:
1. BwOP DG-11, Rev. 30, Diesel Generator Startup (steps 1-8 completed)
2. BwOP DG-11T1, Rev. 6, Diesel Generator Start/Stop Log (partially completed)
3. 1BwOSR 3.8.1.2-1, Rev. 15 (sections 1.0, 2.0, 4.0 completed.)

TASK STANDARDS:

1. Synchronize 1A Diesel Generator to bus 141
2. Recognize a failure of the Governor Adjust switch
3. Open 1A DG Output Circuit Breaker prior to completion of BwOP DG-11, step F.9.l.

TASK CONDITIONS:

1. You are the extra NSO.
2. All conditions are normal for current mode on Unit 1.
3. The 1A Diesel Generator was SLOW started from the control room per BwOP DG-11 step F.4, and has been running unloaded for approximately fifteen minutes.

Step 9 is ready to be performed.

4. 1BwOSR 3.8.1.2-1 is in progress, and complete through step F.4.0.

INITIATING CUES:

1. Using the partially completed procedures provided, (CUE: Hand examinee copy of 1BwOSR 3.8.1.2-1, BwOP DG-11, and BwOP DG-11T1) you have been directed by the Unit Supervisor to complete Section F.5.0 of 1BwOSR 3.8.1.2-1.
2. Inform the US when you have completed section F.5.0 of 1BwOSR 3.8.1.2-1.

1 SIM-608

RECORD START TIME Note: Provide the partially completed copies of 1BwOSR 3.8.1.2-1, BwOP DG-11, and BwOP DG-11T1 to the examinee.

PERFORMANCE STEP STANDARD Circle applicable

1. Refer to 1BwOSR 3.8.1.2-1, Refer to copy of 1BwOSR SAT UNSAT N/A 1A DG Operability Monthly 3.8.1.2-1 provided Comments:

Surveillance. (Section F.

  • Determine it is 5.0) necessary to parallel and load 1A DG using BwOP DG-11.
2. Refer to BwOP DG-11 Refer to BwOP DG-11 SAT UNSAT N/A CUE: All Prerequisites,
  • Determine step F.9 to Comments:

Precautions, Limitations and be used to parallel Actions are met and load 1A DG 2

SIM-608

PERFORMANCE STEP STANDARD Circle applicable

  • 3. Parallel the 1A Diesel Perform the following at SAT UNSAT N/A Generator 1PM01J: Comments:

CUE: If asked, this o VERIFY DG Frequency surveillance is NOT ~60Hz and Voltage being performed in ~4160V conjunction with the o Adjust DG frequency 24-hour load run of to 60 Hz using Gov.

surveillance 1BwVSR Adj. Control.

3.8.1.14-1.

o Adjust DG voltage to 4160V using Volt Adj. Control.

o VERIFY approximately the same voltage exists across each phase o Check voltage on phases A-B, B-C, and A-C using the DIESEL GEN.

VOLTMETER SELECT Switch.

  • Turn Sync Selector Switch to ON for ACB 1413.
  • Adjust Incoming (DG) voltage (1EI-AP104B) slightly higher (0-4.0 volts) than running voltage (1EI-AP104A) using the Volt Adj.

Control.

  • Adjust Generator Speed such that the synchroscope (1SI-AP104) is rotating SLOWLY in the FAST direction using the Gov. Adj. Control.
  • When the synchroscope (1SI-AP104) is slightly before the 12 o'clock position, CLOSE ACB 1413.

o Verify synchroscope (1SI-AP104) "Locks in" at 12 o'clock position.

3 SIM-608

PERFORMANCE STEP STANDARD Circle applicable Note: Alternate path begins here

  • 4 Attempt to load the 1A Perform the following at Diesel Generator 1PM01J:
  • Attempt to load 1A DG by going to RAISE on the Gov Adj. Control
  • Determine 1A DG OUTPUT KW (1JI-DG002) NOT rising Examiners note: The following step does not have to be performed prior to tripping ACB 1413. If the examinee trips ACB 1413 prior to turning the Synchroscope off mark this step as N/A.
5. Turn the Synchroscope OFF. Perform the following at SAT UNSAT N/A 1PM01J: Comments:

o Place the Sync Selector Switch for DG 1A Feed to 4KV BUS 141 in OFF position.

  • 6. Open 1A D/G output breaker. Perform the following at SAT UNSAT N/A CUE: Examinee will be 1PM01J: Comments:

unable to load the 1A

  • OPEN ACB 1413 DG. Procedure o Inform US of problem guidance (note prior encountered.

to step F.9.f) is to open ACB 1413.

CUE: As US, acknowledge report of 1A DG failure to load.

CUE: THIS COMPLETES THIS JPM.

RECORD STOP TIME COMMENTS:

4 SIM-608

TASK CONDITIONS:

1. You are the extra NSO.
2. All conditions are normal for current mode on Unit 1.
3. The 1A Diesel Generator was SLOW started from the control room per BwOP DG-11 step F.4, and has been running unloaded for approximately fifteen minutes. Step 9 is ready to be performed.
4. 1BwOSR 3.8.1.2-1 is in progress, and complete through step F.4.0.

INITIATING CUES:

1. Using the partially completed procedures provided, you have been directed by the Unit Supervisor to complete Section F.5.0 of 1BwOSR 3.8.1.2-1.
2. Inform the US when you have completed section F.5.0 of 1BwOSR 3.8.1.2-1.

5 SIM-608

SIMULATOR SETUP GUIDE:

  • Verify/perform TQ-BR-201-0113, BRAIDWOOD TRAINING DEPARTMENT SIMULATOR EXAMINATION SECURITY ACTIONS CHECKLIST.
  • Establish the conditions of IC 21, 100% power, steady state, equilibrium xenon.
  • Complete items on Simulator Ready for Training Checklist
  • Place simulator in RUN.
  • Place 1A DG Auto Reclose Circuit Arm switch to SURV TEST
  • Start 1A DG
  • Adjust 1A DG (incoming) voltage lower than running voltage
  • Adjust DG frequency to 60.2 Hz
  • Place synch switch handle in ACB 1414
  • Run caep SIM-608 from disk and verify the following actuate:
  • trgset 1 "ZDI1HSDG026(3)==1"
  • trg 1 "IOR ZDI1HSDG019 2"
  • trgset 2 "ZDI1HSDG028(3)==1"
  • trg 2 "IOR ZDI1HSDG022 2"
  • If running the JPM repetitively, perform the following:
  • Delete Override DOR ZDI1HSDG022
  • Delete Override DOR ZDI1HSDG019
  • Reset Trigger 1 and 2
  • Adjust DG voltage lower than running voltage.
  • Adjust DG frequency to 60.2 Hz.
  • Place synch switch handle in ACB 1414 COMMENTS:
  • Provide copy of 1BwOSR 3.8.1.2-1, rev 15, with sections 1.0, 2.0, 4.0 completed.
  • Provide marked up copy of BwOP DG-11, rev 30, with steps F.1, F.4, F.7 and F.8 place-kept and unit and train designators filled in.
  • Provide copy of BwOP DG-11T, rev 6, with 1A DG start data completed (Final) 6 SIM-608

TASK TITLE: Respond to RCP Thermal Barrier Leak with CC Valve Failure JPM No.: SIM-801 REV: NRC2006301 TPO No.: 4D.OA-51 K&A No.: 008000A3.03 TASK No.: R-OA-061, Respond to a loss of CC K&A IMP: 3.0/3.1 to RCP oil/thermal barrier coolers TRAINEE: SRO EVALUATOR: DATE:

The Trainee: PASSED this JPM. TIME STARTED:

FAILED TIME FINISHED:

JPM TIME: MINUTES CRITICAL ELEMENTS: (*) 7, 8 APPROX COMPLETION TIME 10 MINUTES CRITICAL TIME: NA EVALUATION METHOD: LOCATION:

X PERFORM IN PLANT SIMULATE X SIMULATOR GENERAL

REFERENCES:

1. 1BwOA PRI-6, Rev. 101, Component Cooling Malfunction
2. BwAR 1-7-E4, Rev. 51E2, RCP THERM BARR CC WTR FLOW HIGH LOW MATERIALS:
1. Copy of BwAR 1-7-E4, Rev. 51E2 TASK STANDARDS:
1. Determine 1B RCP Thermal Barrier is leaking.
2. Isolate RCP thermal barrier leakage by closing 1CC9438 prior to overfilling CC surge tank.
3. Isolate 1B RCP thermal barrier and restore CC cooling to unaffected RCP thermal barriers.

TASK CONDITIONS:

1. You are the Assist NSO.
2. Unit 1 is at 100% power.
3. Annunciator 1-7-E4 RCP THERM BARR CC WTR FLOW HIGH LOW has just alarmed.

INITIATING CUES:

1. Perform actions in response to annunciator 1-7-E4.
2. Inform the Unit Supervisor when you have completed actions in response to annunciator 1-7-E4.

1 SIM-801

RECORD START TIME Examiners note: Examinee may take the control switch for 1CC685 to CLOSE at any time (see JPM step 6), when it is noted that the valve did not automatically close on high flow.

Examiners note: Examinee may refer to BwAR 1-7-E4 which directs responses per 1BwOA Pri-6 (below) and 1BwOA PRI-1. If examinee notes reference to 1BWOA PRI-1, provide CUE:

Another Operator will initiate actions of 1BwOA-PRI-1, you are to perform actions of 1BwOA PRI-6.

Examiners note: RCP thermal barrier leakage will cause a high alarm on 1PR09J, Unit 1 CC Heat Exchanger Radiation Monitor and cause automatic closure of 1CC017, CC Surge Tank Vent Valve. If examinee begins to address the 1PR09J alarm, provide CUE: Another Operator will initiate actions in response to 1PR09J alarm.

Examiners note: RCP thermal barrier leakage will cause annunciator 1-9-D3, CHG LINE FLOW HIGH/LOW. If examinee begins to address annunciator, provide CUE: Another Operator will perform actions in response to annunciator 1-9-D3.

PERFORMANCE STEP STANDARD Circle applicable

1. Refer to BwAR 1-7-E4 Locate and open 1BwAR 1- SAT UNSAT N/A CUE: When examinee locates 7-E4 Comments:

correct procedure, o Refer to SER provide copy. o Determine RCP thermal barrier CC water flow high in alarm 2 Refer to 1BwOA PRI-6, Locate and open 1BwOA SAT UNSAT N/A Component Cooling PRI-6 Comments:

Malfunction

  • Notify Shift Manager Note: Examinee will use to evaluate for simulator copy of Emergency Plan 1BwOA PRI-6 for JPM conditions performance.

CUE: Acknowledge request for emergency plan evaluation.

3. Check surge tank level > 13% Perform the following at SAT UNSAT N/A and increasing 1PM06J: Comments:
  • Check CC Surge tank level:
  • Determine CC surge tank level > 13%
  • Determine CC Surge tank level is rising
  • Go to 1BwOA PRI-6, Attachment B, step 1
  • Determine CC Surge tank level is rising
  • Go to 1BwOA PRI-6, Attachment B, Step 5 2

SIM-801

PERFORMANCE STEP STANDARD Circle applicable

4. Check for leakage from RCP Perform the following at SAT UNSAT N/A Thermal Barrier 1PM05J/1PM06J: Comments:
  • Check for leakage from RCP Thermal Barrier:

o Annunciator 1-7-E4 LIT

  • Determine annunciator 1 E4 LIT OR o Seal Injection Flows any abnormally high
  • Determine 1B RCP has abnormally high seal flows
5. Check seal injection flow Perform the following at SAT UNSAT N/A between 8 and 13 gpm per 1PM05J: Comments:

pump

  • Determine 1B RCP seal injection flow > 13 gpm
  • Adjust 1CV121 AND 1CV182 to obtain between 8 and 13 gpm seal injection flow per RCP (as possible)
6. Check 1CC685 Closed Perform the following at SAT UNSAT N/A 1PM06J: Comments:
  • Check 1CC685 Closed
  • Determine 1CC685 is OPEN
  • Place control switch for 1CC685 to CLOSE 3

SIM-801

PERFORMANCE STEP STANDARD Circle applicable Note: Alternate path begins here

  • 7. Isolate RCP thermal barrier Perform the following at leakage 1PM06J:

CUE: As US, acknowledge

  • Determine 1CC685 did failure of 1CC685 to not close close.
  • Manually close 1CC9438
  • 8. Restore CC to unaffected Perform the following: SAT UNSAT N/A RCPs by locally closing RCP Determine 1B RCP is Comments:

Thermal Barrier CC outlet affected RCP valve to isolate affected RCP

  • Determine 1CC9569B closure required CUE: SM desires affected RCP to be isolated.
  • Dispatch operator to enter Unit 1 Note: Inform examinee time Containment to locally compression will be close 1CC9496B used and provide the following cue:
  • After 1CC9496B closed, reopen 1CC9438 CUE: As NLO, report 1CC9496B closed.
9. Check CC surge tank status Perform the following: SAT UNSAT N/A
  • Check CC surge tank Comments:

level between 50% and 65%

o Dispatch NLO to CUE: As NLO, acknowledge restore CC surge tank request to restore CC level between 50% and surge tank level. 65% in necessary

10. Refer to Tech Specs Refer to Tech Specs SAT UNSAT N/A CUE: As US, acknowledge
  • Determine Tech Spec Comments:

T.S. 3.6.3 entry for 3.6.3 applies for 1CC685. 1CC685.

11. Return to procedure and step Perform the following: SAT UNSAT N/A in effect o Inform US 1BwOA PRI-6 Comments:

CUE: Acknowledge report actions complete CUE: THIS COMPLETES THIS JPM.

RECORD STOP TIME COMMENTS:

4 SIM-801

TASK CONDITIONS:

1. You are the Assist NSO.
2. Unit 1 is at 100% power.
3. Annunciator 1-7-E4 RCP THERM BARR CC WTR FLOW HIGH LOW has just alarmed.

INITIATING CUES:

1. Perform actions in response to annunciator 1-7-E4.
2. Inform the Unit Supervisor when you have completed actions in response to annunciator 1-7-E4.

5 SIM-801

SIMULATOR SETUP GUIDE:

  • Verify/perform TQ-BR-201-0113, BRAIDWOOD TRAINING DEPARTMENT SIMULATOR EXAMINATION SECURITY ACTIONS CHECKLIST.
  • Establish the conditions of IC 21, 100% power, steady state, equilibrium xenon.
  • Complete items on Simulator Ready for Training Checklist
  • Place simulator in RUN.
  • Run caep SIM-801 from disk and verify the following actuate:
  • IMF CC09 231
  • IMF CC07B 20
  • IOR ZDI1CC685 OPEN
  • TRGSET 1 "ZDI1CC9438(1) == 1"
  • TRG 1 "DMF CC09"
  • Verify 1BwOA PRI-6 place keeping marks are removed.
  • To close 1CC9496B, perform the following:
  • Insert IRF CC45 0
  • To drain CC surge tank, perform the following:
  • Insert IRF CC15 100(modify RF to 0 when desired level attained)
  • Insert IRF CC16 100(modify RF to 0 when desired level attained)
  • If running the JPM repetitively, perform the following:
  • MRF CC45 50
  • Reset trigger 1
  • Restore RCP seal injection to normal band
  • Restore CC surge tank level to normal band
  • IMF CC09 231 COMMENTS:
  • Provide copy of BwAR 1-7-E4, rev 51E2 (Final) 6 SIM-801

TASK TITLE: Perform Waste Gas Release Channel Checks JPM No.: SIM-901 REV: NRC2006301 TPO No.: 4C.GW-01 K&A No.: 071000A4.25 TASK No.: R-GW-001, Perform gaseous release K&A IMP: 3.2/3.2 TRAINEE: SRO EVALUATOR: DATE:

The Trainee: PASSED this JPM. TIME STARTED:

FAILED TIME FINISHED:

JPM TIME: MINUTES CRITICAL ELEMENTS: (*) 5, 9 APPROX COMPLETION TIME: 30 MINUTES CRITICAL TIME: NA EVALUATION METHOD: LOCATION:

X PERFORM IN PLANT SIMULATE X SIMULATOR GENERAL

REFERENCES:

1. BwOP GW-500T1, Rev. 26, Gas Decay Tank Release Form MATERIALS:
1. BwOP GW-500T1, Rev. 26, Gas Decay Tank Release Form completed through step D.17.

TASK STANDARDS:

1. Perform Gas Decay Tank pre-release channel checks in accordance with BwOP GW-500T1.
2. Operate the RM-11 for setpoint adjustment/testing.

TASK CONDITIONS:

1. You are an extra NSO.
2. Both Units are at full power.
3. 0PR02J, Gas Decay Tank Monitor, is operable.

INITIATING CUES:

1. The Unit Supervisor has directed you to perform a portion of the 0F Gas Decay Tank release package, completed through section D.17, and has directed you to complete steps D.18 through D.21. (Cue: Hand examinee copy of procedure).

All previous sections of the release package have been successfully completed.

2. Inform the Unit Supervisor when you have completed steps D.18 through D.21.

1 SIM-901

RECORD START TIME PERFORMANCE STEP STANDARD Circle applicable

1. Review BwOP GW-500T1 Review BwOP GW-500T1 SAT UNSAT N/A Comments:
2. Select the High Alarm Perform the following: SAT UNSAT N/A setpoint for 0PA202.
  • PLACE the RM-11 Comments:

(steps D.18 - 19.a) console in the SUPERVISOR mode o DEPRESS Grid 3 key

  • KEY in 0202
  • DEPRESS the SEL key o VERIFY 0PA202 selected
  • DEPRESS CHAN ITEM key
  • KEY in 9
  • DEPRESS the SEL key Examiners note: The following procedure step is not required to be performed if 0PA202 is NOT in HIGH ALARM.
3. Verify/enter High Alarm Perform the following: SAT UNSAT N/A setpoint for 0PA202 o Refer to step C.3.c Comments:

suggested by Health Physics is section C.3.c. o VERIFY/ENTER the new High Alarm setpoint (step D.19.b) from step C.3.c Note: If examinee requests (6.06E-03) independent o DEPRESS the ENTER key verification of steps, provide the o VERIFY the new ALERT following cue. alarm setpoint is displayed CUE: Verification has been provided. o OBTAIN VERIFICATION 2

SIM-901

PERFORMANCE STEP STANDARD Circle applicable

4. Select and enter the Alert Perform the following: SAT UNSAT N/A Alarm setpoint for 0PA202. o DEPRESS Grid 3 key Comments:

(step D.19.c) o KEY in 0202 o DEPRESS the SEL key o VERIFY 0PA202 selected o DEPRESS CHAN ITEM key

  • KEY in 10
  • DEPRESS the SEL key o Refer to step C.3.c o VERIFY/ENTER the new Alert Alarm setpoint 3.03E-03 o DEPRESS the ENTER key
  • VERIFY the new ALERT alarm setpoint is displayed CUE: Verification has been o OBTAIN VERIFICATION provided.

3 SIM-901

PERFORMANCE STEP STANDARD Circle applicable

  • 5. Perform the following to Perform the following: SAT UNSAT N/A verify 0RE-PR002B will cause
  • Contact the local Comments:

0GW014 to automatically operator to:

close.

  • Verify/Place 0GW014 (steps D.19.d-q) C/S in OPEN CUE: As local operator
  • Place 0GW014 report 0GW014 C/S is controller to 100%

in open open CUE: As local operator o DEPRESS Grid 3 key report 0GW014 controller is at o KEY in 0202 100%. o DEPRESS the SEL key o VERIFY 0PA202 selected o DEPRESS CHAN ITEM key o KEY in 9 o Record the current 0PA202 current activity activity reading setting________

  • ENTER a new HIGH alarm setpoint below the current activity value 0PA202 new Hi Alarm setting_________ o RECORD the new HIGH alarm setpoint that was entered
  • DEPRESS the ENTER key o ACKNOWLEDGE the alarm at the RM-11 console CUE: As local operator o Contact the local report 0GW014 Auto operator to:

Closed o VERIFY 0GW014 AUTO CUE: As local operator CLOSED report 0GW014 control o PLACE 0GW014 switch is in closed control switch in CUE: As local operator CLOSED report 0GW014 o PLACE 0GW014 controller is at 0%. controller at 0%

demand o DEPRESS Grid 3 key o KEY in 0202 o DEPRESS the SEL key o VERIFY 0PA202 selected o DEPRESS CHAN ITEM key o KEY in 9

  • ENTER the HIGH alarm setpoint determined in step C.3.c (6.06 E-03) o OBTAIN VERIFICATION CUE: Verification has been provided.

4 SIM-901

PERFORMANCE STEP STANDARD Circle applicable

6. Select the High Alarm Perform the following: SAT UNSAT N/A setpoint for 0PA202. o DEPRESS Grid 3 key Comments:

(step D.20.a)

  • KEY in 0102
  • DEPRESS the SEL key o VERIFY 0PB102 selected
  • DEPRESS CHAN ITEM key
  • KEY in 9
  • DEPRESS the SEL key Examiners note: The following procedure step is not required to be performed if 0PA202 is NOT in HIGH ALARM.
7. Verify/enter High Alarm Perform the following: SAT UNSAT N/A setpoint for 0PB102 o Refer to step C.3.c Comments:

suggested by Health Physics is section C.3.c. o VERIFY/ENTER the new High Alarm setpoint (step D.20.b) from step C.3.c (6.06E-04) o DEPRESS the ENTER key o VERIFY the new ALERT alarm setpoint is displayed CUE: Verification has been provided. o OBTAIN VERIFICATION

8. Select and enter the Alert Perform the following: SAT UNSAT N/A Alarm setpoint for 0PB102. o DEPRESS Grid 3 key Comments:

(step D.20.c) o KEY in 0102 o DEPRESS the SEL key o VERIFY 0PB102 selected o DEPRESS CHAN ITEM key

  • KEY in 10
  • DEPRESS the SEL key o Refer to step C.3.c
  • VERIFY/ENTER the new Alert Alarm setpoint (6.06E-05) o DEPRESS the ENTER key o VERIFY the new ALERT alarm setpoint is displayed CUE: Verification has been o OBTAIN VERIFICATION provided.

5 SIM-901

PERFORMANCE STEP STANDARD Circle applicable

  • 9. Perform the following to Perform the following: SAT UNSAT N/A verify 0RE-PR002A will cause
  • Contact the local Comments:

0GW014 to automatically operator to:

close.

  • Verify/Place 0GW014 (steps D.20.d-q) C/S in OPEN CUE: As local operator
  • Place 0GW014 report 0GW014 C/S is controller to 100%

in open open CUE: As local operator o DEPRESS Grid 3 key report 0GW014 controller is at o KEY in 0102 100%. o DEPRESS the SEL key o VERIFY 0PB102 selected o DEPRESS CHAN ITEM key

  • KEY in 9 o Record the current 0PB102 current activity activity reading setting________
  • ENTER a new HIGH alarm setpoint below the current activity value 0PB102 new Hi Alarm setting_________ o RECORD the new HIGH alarm setpoint that was entered
  • DEPRESS the ENTER key o ACKNOWLEDGE the alarm at the RM-11 console CUE: As local operator o Contact the local report 0GW014 Auto operator to:

Closed o VERIFY 0GW014 AUTO CUE: As local operator CLOSED report 0GW014 control o PLACE 0GW014 switch is in closed control switch in CUE: As local operator CLOSED report 0GW014 o PLACE 0GW014 controller is at 0%. controller at 0%

demand o DEPRESS Grid 3 key o KEY in 0102 o DEPRESS the SEL key o VERIFY 0PB102 selected o DEPRESS CHAN ITEM key o KEY in 9

  • ENTER the HIGH alarm setpoint determined in step C.3.c (6.06 E-04)

CUE: Verification has been provided. o OBTAIN VERIFICATION 6

SIM-901

PERFORMANCE STEP STANDARD Circle applicable

10. Place RM-11 in NORMAL MODE
  • PLACE the RM-11 SAT UNSAT N/A console in the NORMAL Comments:

mode

11. Inform US pre-release Inform US steps D.18 channel checks complete through D.21 are CUE: Acknowledge report. completed CUE: THIS COMPLETES THIS JPM.

RECORD STOP TIME COMMENTS:

7 SIM-901

TASK CONDITIONS:

1. You are an extra NSO.
2. Both Units are at full power.
3. 0PR02J, Gas Decay Tank Monitor, is operable.

INITIATING CUES:

1. The Unit Supervisor has directed you to perform a portion of the 0F Gas Decay Tank release package, completed through section D.17, and has directed you to complete steps D.18 through D.21. All previous sections of the release package have been successfully completed.
2. Inform the Unit Supervisor when you have completed steps D.18 through D.21.

8 SIM-901

SIMULATOR SETUP GUIDE:

  • Verify/perform TQ-BR-201-0113, BRAIDWOOD TRAINING DEPARTMENT SIMULATOR EXAMINATION SECURITY ACTIONS CHECKLIST.
  • Establish the conditions of IC 21, 100% power, steady state, equilibrium xenon.
  • Complete items on Simulator Ready for Training Checklist.
  • Place simulator in RUN.
  • Adjust 0PR02J radiation level as follows:
  • Record as found values of monitored item RMK0PR02ABKD ______________.
  • Set monitor item RMK0PR02ABKD = 1.31 E-8
  • Record as found values of monitored item RMK0PR02BBKD ______________.
  • Set monitor item RMK0PR02BBKD = 1.31 E-8
  • Adjust 0PR02J setpoints as follows.
  • Record 0PA102 High Alarm current setpoint ___________________.
  • Set 0PA102 High Alarm Setpoint = 6.06 E-04 (channel item #9).
  • Record 0PB102 Alert Alarm current setpoint ___________________.
  • Set 0PA102 Alert Alarm Setpoint = 6.06 E-05 (channel item #10).
  • Record 0PA202 High Alarm current setpoint ___________________.
  • Set 0PA202 High Alarm Setpoint = 6.06 E-03 (channel item #9).
  • Record 0PA202 Alert Alarm current setpoint ___________________.
  • Set 0PA202 Alert Alarm Setpoint = 3.03 E-03 (channel item #10).
  • Select grid on the RM-11 console
  • AT CONCLUSION OF JPM(S), RESTORE 0PR02J MONITORED ITEMS ALARM SETPOINTS TO ORIGINAL AS FOUND VALUES COMMENTS:

Provide copy of BwOP GW-500T1, Rev. 26 (Final) 9 SIM-901