Letter Sequence Other |
|---|
TAC:MC7611, Eliminate Second Completion Times Limiting Time from Discovery of Failure to Meet an LCO (Approved, Closed) |
Results
Other: ML053050028, ML053200289, ML060230431, ML060230432, ML060230436, ML061070587, ML061240255, ML061240259, ML061240264, ML061240266, ML061240269
|
MONTHYEARML0515304482005-05-20020 May 2005 R. E. Ginna Nuclear Power Plant, Partial Site Release Project stage: Request ML0524501562005-09-0808 September 2005 Request for Additional Information Regarding Release of Part of Site for Unrestricted Use Project stage: RAI ML0525704402005-09-15015 September 2005 Supplemental Request for Additional Information Regarding Release of Part of Site for Part of Site for Unrestricted Use, R. E. Ginna Nuclear Power Plant Project stage: RAI ML0530503032005-11-0909 November 2005 Summary of September 28, 2005, Meeting with the Public Regarding Proposed Release of Part of Site for Unrestricted Use (Tac No. MC7602) Project stage: Meeting ML0530500282005-11-16016 November 2005 Notice of Consideration of Issuance of Amendment to Facility Operating License and Opportunity for a Hearing Project stage: Other ML0532002892005-11-17017 November 2005 Note to File - Closure of TAC No. MC7607 for Monticello Improved Technical Specification (ITS) Conversion, Beyond Scope Issue (Bsi) 3.3.3.1, Doc L.2, Post-Accident Monitoring (PAM) Instrumentation Project stage: Other ML0602304322005-11-29029 November 2005 ITS Conversion Beyond Scope Issue 8 Project stage: Other ML0602304312006-01-23023 January 2006 ITS Conversion Beyond Scope Issue 7 Project stage: Other ML0602304362006-01-23023 January 2006 ITS Conversion Beyond Scope Issue 1h Project stage: Other ML0609505482006-04-0707 April 2006 Draft Safety Evaluation for the Conversion to Improved Technical Specifications (TAC Nos. MC7505, MC7597 Through MC7611, and MC8887) Project stage: Draft Approval L-MT-06-036, Copy of Improved Technical Specifications and Improved Technical Specifications Bases Pages2006-05-0404 May 2006 Copy of Improved Technical Specifications and Improved Technical Specifications Bases Pages Project stage: Request L-MT-06-039, Replacement Page for Improved TS 3.5.12006-05-12012 May 2006 Replacement Page for Improved TS 3.5.1 Project stage: Request ML0610705872006-05-25025 May 2006 Environmental Assessment and Finding of No Significant Impact for the Proposed Conversion to the Improved Technical Specifications Project stage: Other ML0612402552006-06-0505 June 2006 Attachment 2 - Table a - Administrative Changes for Monticello, Amendment 146 for the Conversion to the Improved Technical Specifications with Beyond-Scope Issues Project stage: Other ML0612402592006-06-0505 June 2006 Attachment 3 - Table M - More Restrictive Changes for Monticello, Amendment 146 for the Conversion to the Improved Technical Specifications with Beyond-Scope Issues Project stage: Other ML0612402642006-06-0505 June 2006 Attachment 4 - Table L - Less Restrictive Changes for Monticello, Amendment 146 for the Conversion to the Improved Technical Specifications with Beyond-Scope Issues Project stage: Other ML0612402662006-06-0505 June 2006 Attachment 5 - Table La - Removed Details for Monticello, Amendment 146 for the Conversion to the Improved Technical Specifications with Beyond-Scope Issues Project stage: Other ML0612402692006-06-0505 June 2006 Attachment 6 - Table R - Relocated Specifications for Monticello, Amendment 146 for the Conversion to the Improved Technical Specifications with Beyond-Scope Issues Project stage: Other ML0610705772006-06-0505 June 2006 Issuance of Licensing Amendment 146 for the Conversion to the Improved Technical Specifications with Beyond-Scope Issues Project stage: Approval 2005-09-08
[Table View] |
Text
CeD NRC ITS TRACKING NRC Reviewer II 200510281133 Conference Call Requested? No Categoryl Discussion ITS Section:
DOC Numhgr:
Jv FNallner:
agtNm1!wr(s):
l ITS Information 5.0 L.5 None 55 ITS lITS~
cr:
Balscsl lJ) uNumberl BSI 8 None This is a Beyond Scope Issue (TAC No. MC7611)
CTS 6.8.B.2 specifies that the integrated leak test requirements for each system outside containment that could contain highly radioactive fluids; during a serious transient or accident must be performed at a refueling cycle interval or less. CTS 6.8.B also states that CTS 4.0.B is applicable (25% grace period is Comment allowed).
ITS 5.5.2.b specifies that the same test must be performed at least once per 24 months and also states that the provisions of ITS SR 3.0.2 are applicable.
You request increasing the CTS surveillance frequency from 18 months to 24 months, with a maximum of 30 months accounting for the allowable grace period.
There were no questions or comments by NRC staff regarding this issue.
Issue Datel10/28/2005 Resolution requires change to:
N~one Close Date DockeLResponseReiquired No W Rcsponses Date Created: 10/28/2005 11:33 AM by Terry Beltz Last Modified: 11/29/2005 01:37 PM http://www.excelservices.com/exceldbs/itstrackmontice] lo.nsf/l fddcea 1 Od3bdbb585256e85000 138e4/7b... 1/23/2006
Vl lsl rt\\iew B3v\\NRC Ow Nn rl 3:elr
\\Z-y~lte
-Numllbe LICE'NSEIE COMMENTS II) l200510281133 Validation Required? No RespqnseSubmitted 11/03/2005 l
[Cornmer'tj Monticello acknowledges that there are no questions or comments concerning this Beyond Scope Issue.
Date Created: 11/03/2005 03:20 PM by Jerry Jones Last Modified: 11/03/2005 03:20 PM 1
http://www.excelservices.com/exceldbs/itstrack-montice~llo.nsf/I fddcea I 0d3bdbb585256e85000 13 8e4/Oc... 1/23/2006