Summary of the Public Meeting to Discuss FENOC Fleet Performance as Well as Performance and Challenges at the FENOC Nuclear Power Plants
ML060200579
Person / Time
Site: Beaver Valley, Davis Besse, Perry
Issue date: 01/13/2006
From: Bellamy R
NRC/RGN-I/DRP/PB7
To:
Bellamy R Rgn-I/DRP/Br7/610-337-5200
Shared Package
ML060130520 List:
References
Download: ML060200579 (5)


Text

January 13, 2006 LICENSEE: First Energy Nuclear Operating Company (FENOC)

FACILITIES: Beaver Valley Nuclear Power Plant, Units 1 and 2, Perry Nuclear Power Plant, Unit 1, and Davis-Besse Nuclear Power Plant, Unit 1

SUBJECT:

SUMMARY

OF THE JANUARY 10, 2006, PUBLIC MEETING TO DISCUSS FENOC FLEET PERFORMANCE AS WELL AS PERFORMANCE AND CHALLENGES AT THE FENOC NUCLEAR POWER PLANTS On January 10, 2006, the Nuclear Regulatory Commission (NRC) held a public meeting at the Beaver Valley Nuclear Power Station Training Building, Shippingport, Pennsylvania. The meeting was held between NRC Region I and Region III management and staff, and site and corporate representatives of First Energy Nuclear Operating Company (FENOC). The purpose of the meeting was to discuss the performance of the FENOC fleet, which includes Beaver Valley Units 1 and 2 in Pennsylvania (located in NRC Region I), and the Perry and Davis-Besse plants in Ohio (located in NRC Region III). The meeting was a followup to a similar meeting held on November 16, 2004, in Painesville, Ohio. The meeting notice can be found in ADAMS as ML053570234. A list of meeting attendees and a copy of the licensee presentation are attached.

After introductory comments by NRC senior management from Regions I and III, FENOC presented an overview of fleet operation, fleet organizational philosophy, and the progress over the last year in FENOC developing as a fleet of nuclear power plants. FENOC then presented a review of the 2005 performance at each site, including top focus areas, and challenges and plans for 2006. A common theme of improving site performance through safe, secure, reliable, event-free operation was emphasized.

The meeting provided a useful forum to discuss common themes at the FENOC plants with the NRC Regions and the Office of Nuclear Reactor Regulation. The meeting concluded with a

discussion of plans to continue these meetings involving the NRC regions and program offices and all plants in the FENOC fleet on an annual basis.

/RA/

Ronald R. Bellamy, Chief Projects Branch 7 Division of Reactor Projects Docket Nos: 50-334, 50-412, 50-440, and 50-346 License Nos: DPR-66, NPF-73, NPF-58, and NPF-3 encl: Meeting attendees Licensee presentation

discussion of plans to continue these meetings involving the NRC regions and program offices and all plants in the FENOC fleet on an annual basis.

/RA/

Ronald R. Bellamy, Chief Projects Branch 7 Division of Reactor Projects Docket Nos: 50-334, 50-412, 50-440, and 50-346 License Nos: DPR-66, NPF-73, NPF-58, and NPF-3 encl: Meeting attendees Licensee presentation Distribution:

S. Collins, RA M. Dapas, DRA R. Bellamy, DRP R. Fuhrmeister, DRP S. Lee, RI OEDO M. Satorius, RIII, DRP C. Haney, NRR C. Holden, NRR C. Lipa, RIII, DRP M. Landau, NRR R. Laufer, NRR T. Colburn, PM, NRR R. Guzman, NRR P. Cataldo - Senior Resident Inspector P. Garrett - Resident OA DOCUMENT NAME: E:\Filenet\ML060200579.wpd SISP Review Complete: RRB (Reviewers Initials)

After declaring this document An Official Agency Record it will be released to the Public.

To receive a copy of this document, indicate in the box: "C" = Copy without attachment/enclosure "E" = Copy with attachment/enclosure "N" = No copy OFFIC RI/DRP E

NAME RBellamy/RRB DATE 01/13/06 OFFICIAL RECORD COPY

MEETING ATTENDEES BEAVER VALLEY NUCLEAR POWER PLANT, UNITS 1 AND 2 PERRY NUCLEAR POWER PLANT, UNIT 1 DAVIS-BESSE NUCLEAR POWER PLANT, UNIT 1 JANUARY 10, 2006 NRC Staff Marc Dapas, Region I, Deputy Regional Administrator Mark Satorius, Region III, Director of Division Reactor Projects Catherine Haney, NRR, Director, Division of Operator Reactor Licensing Cornelius Holden, NRR, Deputy Director, Division of Operator Reactor Licensing Ronald Bellamy, Region I, Chief, Projects Branch 7 Christine Lipa, Region III, Chief, Projects Branch 4 Mindy Landau, NRR, Acting Branch Chief, Project Licensing Branch III-2 Paul Cataldo, BVPS Senior Resident Inspector Galen Smith, BVPS Resident Inspector Neil Sheehan, Region I, Public Affairs Officer FENOC Staff Gary Leidich, President Danny Pace, Senior Vice President Bill Pearce, Vice President, Perry Bob Schrauder, Director, Davis-Besse Jim Lash, Vice President, BV Greg Halnon, Director, Regulatory Affairs Rich Anderson, Vice President, Operations Vito Kaminskas, Director, Operations Support Bill Kanda, Director, Organizational Effectiveness Clark Price, Davis-Besse Lew Myers, Steam Generator Replacement Project Ralph Hansen, BV Manager, Nuclear Oversight Jeannie Rinckel, Vice President, Fleet Oversight Larry Freeland, BV Director, Performance Improvement Alfred Coyia, Perry Director, Performance Improvement Jim Shaw, Perry Director, Engineering Steve Sarver, BV Fleet Licensing Anthony Dometrovich, BV Regulatory Compliance Jim Mauck, BV Regulatory Compliance Stanley F. Baker, BV Radiation Protection Manager David W. Jenkins, Legal Michelle Meredith, BV Communications Representative Greg Davie, BV Training Roy Brosi, BV Site Projects David Kunsemiller, BV License Renewal Project Tom Saska, Plant Maintenance

Other attendees:

Joseph Spanik, Beaver County Commissioner John P. Jones, Jr., Hancock County EMA David Mix, Ohio Board of Radiation Protection Rudy Sacchet, Ohio EMA, Columbiana County Larry Ryan, Pennsylvania Bureau of Radiation Protection James Janos, Hancock County, West Virginia DHS & EM William Green, Shippingport Borough Brad Goetz, IBEW Local 1413 Larry Tscherne, IBEW 245 Steve Arnold, Ottawa County Jesse Witt, Ottawa County Dick Miller, Bechtel Tom Henry, The (Toledo) Blade Ray Wacker, IBEW Executive Board Local 29 Regis A. Collins, Vanport Emergency Management Agency Andy Randza, Red Cross Amy Icenhour, Red Cross (Beaver-Lawrence Chapter)

Stephanie Waite, Beaver County Times Wes Hill, BC Emergency Services Ken Husk, Raccoon Township Stanley Stickles, Raccoon Township