r-INDIANA MICHIGAN POWER Indiana Michigan Power Company Nuclear Generation Group One Cook Place Bridgman, Ml 49106 aep.com December 28, 2005 AEP:NRC:5055-15 10 CFR 50.55a Docket Nos.: 50-315 50-316 U. S. Nuclear Regulatory Commission ATTN: Document Control Desk Mail Stop O-P1-17 Washington, DC 20555-0001 Donald C. Cook Nuclear Plant Units 1 and 2 COMMITMENT DUE DATE EXTENSION
Reference:
Letter from Daniel P. Fadel, Indiana Michigan Power Company, to U. S. Nuclear Regulatory Commission Document Control Desk, "Donald C. Cook Nuclear Plant Units 1 and 2, Proposed Alternative to the American Society of Mechanical Engineers Code Section XI Weld Inspection Requirements," AEP:NRC:5055-10, Accession Number ML052780450, dated September 22, 2005.
The referenced letter contained Indiana Michigan Power Company's (I&M's) proposed alternative to the American Society of Mechanical Engineers Code,Section XI requirements for the minimum number of Class 1 and 2 piping welds to be examined during the next Unit 1 and Unit 2 refueling outages. The proposal was requested because of I&M's intention to adopt a risk-informed inservice inspection (RI-ISI) program during the current third 10-year inservice inspection interval.
The RI-ISI program, when implemented, would reduce the number of welds requiring examination.
In requesting the proposed alternative, I&M committed to submit the RI-ISI program by December 31, 2005. I&M's RI-ISI program is to be based on Code Case N-716, and the Grand Gulf Nuclear Station is the pilot plant for a Code Case N-716 based RI-ISI program. The Grand Gulf program will not be submitted prior to December 31, 2005.
Therefore, I&M is revising its commitment date.
The attachment to this letter provides I&M's commitment. Should you have any questions, please contact Mr. Michael K Scarpello, Regulatory Affairs Supervisor, at (269) 466-2649.
Sincerely, el P
re s Engineering Vice President'
-AC4-47
U. S. Nuclear Regulatory Commission AEP:NRC:5055-15 Page 2 RV/rdw c:
R. Aben - Department of Labor and Economic Growth J. L. Caldwell - NRC Region III K. D. Curry - AEP Ft. Wayne, w/o attachment J. T. King - MPSC, wlo attachment MDEQ - WHMD/RPMWS, w/o attachment NRC Resident Inspector P. S. Tam - NRC Washington DC
Attachment to AEP:NRC:5055-15 Regulatory Commitment The following table identifies those actions committed to by Indiana Michigan Power Company (I&M) in this document. Any other actions discussed in this submittal represent intended or planned actions by I&M. They are described to the Nuclear Regulatory Commission (NRC) for the NRC's information and are not regulatory commitments.