ML053400164

From kanterella
Jump to navigation Jump to search
Summary of a Telephone Conference Call Held on June 28, 2005, Between the NRC and Firstenergy Nuclear Operating Company
ML053400164
Person / Time
Site: Beaver Valley
Issue date: 12/02/2005
From: Ashley D
NRC/NRR/ADRO/DLR/RLRA
To:
Office of Nuclear Reactor Regulation
ashley D, NRR/DLR/RLRB, 415-3191
References
Download: ML053400164 (7)


Text

December 2, 2005 LICENSEE:

FirstEnergy Nuclear Operating Company FACILITY:

Beaver Valley Power Station, Units 1 and 2

SUBJECT:

SUMMARY

OF A TELEPHONE CONFERENCE CALL HELD ON JUNE 28, 2005, BETWEEN THE U.S. NUCLEAR REGULATORY COMMISSION AND FIRSTENERGY NUCLEAR OPERATING COMPANY, CONCERNING CLARIFICATION OF INFORMATION CONTAINED IN THE NRC LETTER DATED MARCH 24, 2005, RESULTS OF ACCEPTANCE REVIEW OF THE BEAVER VALLEY POWER STATION, UNITS 1 AND 2, LICENSE RENEWAL APPLICATION The U.S. Nuclear Regulatory Commission staff (NRC or the staff) and representatives of FirstEnergy Nuclear Operating Company (FENOC) held a telephone conference call on June 28, 2005, to discuss and clarify the staffs comments concerning the Beaver Valley Power Station, Units 1 and 2, previous license renewal application. The conference call was useful in clarifying the staffs examples of deficiencies found in the license renewal application. The following items were discussed: (1) Components in scope - Section 2; (2) Fatigue Monitoring Program; (3) Application tables and notes; (4) Steam Generator Tube Inspection; (5) Risk Assessment - profiles and unit differences; (6) Boric Acid Program - management vs. detection; (7) Stress corrosion cracking vs. fatigue; and (8) Checklist items. provides a listing of the telephone conference call participants.

The applicant had an opportunity to comment on this summary.

/RA/

Donnie J. Ashley, Project Manager License Renewal Branch A Division of License Renewal Office of Nuclear Reactor Regulation Docket Nos.: 50-334 and 50-412

Enclosure:

As stated cc w/encl: See next page

ML053400164 DOCUMENT NAME: E:\\Filenet\\ML053400164.wpd OFFICE DLR:RLRA:PM DLR:LA DLR:RLRA:BC NAME DAshley MJenkins LLund (JEads for)

DATE 12/01 /05 11/30 /05 12/02/05

cc:

David W. Jenkins, Attorney FirstEnergy Nuclear Operating Company FirstEnergy Corporation 76 South Main Street Akron, OH 44308 L. R. Freeland, Manager Regulatory Compliance (BV-A)

FirstEnergy Nuclear Operating Company Beaver Valley Power Station Post Office Box 4, BV-A Shippingport, PA 15077 Commissioner James R. Lewis West Virginia Division of Labor 749-B, Building No. 6 Capitol Complex Charleston, WV 25305 Director, Utilities Department Public Utilities Commission 180 East Broad Street Columbus, OH 43266-0573 Director, Pennsylvania Emergency Management Agency 2605 Interstate Dr.

Harrisburg, PA 17110-9364 Ohio EPA-DERR ATTN: Zack A. Clayton Post Office Box 1049 Columbus, OH 43266-0149 Dr. Judith Johnsrud National Energy Committee Sierra Club 433 Orlando Avenue State College, PA 16803 B. F. Sepelak, Supv Regulatory Compliance (BV-A)

FirstEnergy Nuclear Operating Company Beaver Valley Power Station Post Office Box 4 Shippingport, PA 15077 Mr. L. William Pearce, Vice President FirstEnergy Nuclear Operating Company Beaver Valley Power Station Post Office Box 4 Shippingport, PA 15077 J. H. Lash, Director-Site Operations (BV-A)

FirstEnergy Nuclear Operating Company Beaver Valley Power Station Post Office Box 4 Shippingport, PA 15077 Rich Janati, Chief Division of Nuclear Safety Bureau of Radiation Protection Department of Environmental Protection Rachel Carson State Office Building P.O. Box 8469 Harrisburg, PA 17105-8469 Mayor of the Borough of Shippingport P.O. Box 3 Shippingport, PA 15077 Regional Administrator, Region I U.S. Nuclear Regulatory Commission 475 Allendale Road King of Prussia, PA 19406 Resident Inspector U.S. Nuclear Regulatory Commission Post Office Box 298 Shippingport, PA 15077 R.G. Mende, Director, Performance Improvement (BV-IPAB)

FirstEnergy Nuclear Operating Company Beaver Valley Power Station Post Office Box 4 Shippingport, PA 15077

Beaver Valley Power Station cc:

Mr. James Ross Nuclear Energy Institute 1776 I Street, NW, Suite 400 Washington, DC 20006-3708 Roger Rucker, PM License Renewal (BV-A)

FirstEnergy Nuclear Operating Company Beaver Valley Power Station Post Office Box 4 Shippingport, PA 15077

DISTRIBUTION: Summary of telecon held on 6/28/2005 with FirstEnergy, Dated: December 2, 2005 Adams Accession No.: ML053400164 HARD COPY DLR RF E-MAIL:

RidsNrrDlr RidsNrrDe G. Bagchi K. Manoly J. Calvo R. Jenkins J. Fair RidsNrrDss D. Thatcher R. Pettis G. Galletti K. Winsberg (RidsOgcMailCenter)

R. Weisman M. Mayfield A. Murphy S. Smith (srs3)

S. Duraiswamy Y. L. (Renee) Li DLR Staff C. Holden R. Laufer T. Colburn D. Shum R. Lorson, RI M. Modes, RI M. Sykes, RI P. Eselgroth, RI P. Cataldo, RI G. Smith, RI Lawyer OPA

Enclosure LIST OF PARTICIPANTS FOR A TELEPHONE CONFERENCE CALL BETWEEN THE U.S. NUCLEAR REGULATORY COMMISSION AND FIRSTENERGY NUCLEAR OPERATING COMPANY June 28, 2005 Participants Affiliations Donnie Ashley U.S. Nuclear Regulatory Commission (NRC)

Bob Palla NRC Kaihwa Hsu NRC Carolyn Lauron NRC Leslie Miller NRC Kenneth Chang NRC Kimberly Corp NRC Roger Rucker FirstEnergy Nuclear Operating Company (FENOC)

Steve Dort FENOC John Thomas FENOC Jim Hester FENOC Don Kosloff FENOC Gary Smith FENOC Lance Garrett FENOC