August 30, 2005 Mr. Dale E. Young, Vice President Crystal River Nuclear Plant (NA1B)

ATTN: Supervisor, Licensing &

Regulatory Programs 15760 West Power Line Street Crystal River, FL 34428-6708

SUBJECT:

MID-CYCLE PERFORMANCE REVIEW AND INSPECTION PLAN - CRYSTAL RIVER NUCLEAR PLANT

Dear Mr. Young:

On August 3, 2005, the NRC staff completed its performance review of the Crystal River Nuclear Plant for the first half of the calendar year 2005 assessment cycle. Our technical staff reviewed performance indicators (PIs) for the most recent quarter and inspection results over the previous twelve months. The purpose of this letter is to inform you of our assessment of your safety performance during this period and our plans for future inspections at your facility.

This performance review and the enclosed inspection plan do not include physical protection information. A separate letter designated and marked as Exempt from Public Disclosure in Accordance with 10 CFR 2.390, will include the physical protection review and a resultant inspection plan.

Plant performance for the most recent quarter was within the Licensee Response Column of the NRCs Action Matrix, based on all inspection findings being classified as having very low safety significance (Green) and all PIs indicating performance at a level requiring no additional NRC oversight (Green). Therefore, we plan to conduct only baseline inspections at your facility through March 31, 2007. We also plan on conducting several non-baseline inspections, which include pressurizer penetration nozzles and steam space piping connections in U.S. pressurizer water reactors, and transportation of reactor control rod drives in type A packages.

The enclosed inspection plan details the inspections, less those related to physical protection, scheduled through March 31, 2007. The inspection plan is provided to minimize the resource impact on your staff and to allow for the resolution of any scheduling conflicts and personnel availability well in advance of inspector arrival onsite. Routine resident inspections are not listed due to their ongoing and continuous nature. The inspections in the last twelve months of the inspection plan are tentative and may be revised at the end-of-cycle review meeting.

In accordance with 10 CFR 2.390 of the NRCs Rules of Practice, a copy of this letter and its enclosure will be made available electronically for public inspection in the NRC Public Document Room or from the Publicly Available Records (PARS) component of NRC's document system (ADAMS). ADAMS is accessible from the NRC Web site at http://www.nrc.gov/reading-rm/adams.html (the Public Electronic Reading Room).

FPC 2

If circumstances arise which cause us to change the inspection plan, we will contact you to discuss the change as soon as possible. Please contact me at (404) 562-4560 with any questions you may have regarding this letter or the inspection plan.

Sincerely,

\\RA\\

Joel T. Munday, Chief Reactor Projects Branch 3 Division of Reactor Projects Docket No. 50-302 License No. DPR-72

Enclosure:

Crystal River Inspection/Activity Plan cc w/encl: (See page 3)

FPC 3

cc w/encl:

Daniel L. Roderick Director Site Operations Crystal River Nuclear Plant (NA2C)

Electronic Mail Distribution Jon A. Franke Plant General Manager Crystal River Nuclear Plant (NA2C)

Electronic Mail Distribution Terry D. Hobbs Manager Nuclear Assessment Crystal River Nuclear Plant (NA2C)

Electronic Mail Distribution Michael J. Annacone Engineering Manager Crystal River Nuclear Plant (NA2C)

Electronic Mail Distribution R. Alexander Glenn Associate General Counsel (MAC - BT15A)

Florida Power Corporation Electronic Mail Distribution Steven R. Carr Associate General Counsel - Legal Dept.

Progress Energy Service Company, LLC Electronic Mail Distribution Attorney General Department of Legal Affairs The Capitol Tallahassee, FL 32304 William A. Passetti Bureau of Radiation Control Department of Health Electronic Mail Distribution Craig Fugate, Director Division of Emergency Preparedness Department of Community Affairs Electronic Mail Distribution Chairman Board of County Commissioners Citrus County 110 N. Apopka Avenue Inverness, FL 36250 Jim Mallay Framatome Technologies Electronic Mail Distribution Distribution w/encl: (See page 4)

OFFICE RII:DRP SIGNATURE SON NAME SNinh:rcm DATE 8/30/05 8/ /2005 8/ /2005 8/ /2005 8/ /2005 8/ /2005 8/ /2005 E-MAIL COPY?

YES NO YES NO YES NO YES NO YES NO YES NO YES NO