Brunswick Inspection / Activity Plan 09/01/2005 - 03/31/2007 Inspection Type Inspection Activity Planned Dates Start End No. of Staff on Site Title Unit Number Page 1 of 2 08/30/2005 07:26:46 Report 22 2
EB1SSDPC - SSDPC PRE-INSPECTION VISIT Baseline Inspections 10/03/2005 10/07/2005 Safety System Design and Performance Capability IP 7111121 1, 2 5
EB1SSDPC - SAFETY SYSTEM DESIGN & PERF. CAPABILITY Baseline Inspections 10/31/2005 11/04/2005 Safety System Design and Performance Capability IP 7111121 1, 2 Baseline Inspections 11/14/2005 11/18/2005 Safety System Design and Performance Capability IP 7111121 1, 2 1
PS2 EP
- EP INSPECTION Baseline Inspections 11/14/2005 11/18/2005 Alert and Notification System Testing IP 7111402 1, 2 Baseline Inspections 11/14/2005 11/18/2005 Emergency Response Organization Augmentation Testing IP 7111403 1, 2 Baseline Inspections 11/14/2005 11/18/2005 Emergency Action Level and Emergency Plan Changes IP 7111404 1, 2 Baseline Inspections 11/14/2005 11/18/2005 Correction of Emergency Preparedness Weaknesses and Deficiencies IP 7111405 1, 2 Baseline Inspections 11/14/2005 11/18/2005 Performance Indicator Verification IP 71151 1, 2 3
PB4-PI&R
- PROBLEM IDENTIFICATION & RESOLUTION Baseline Inspections 11/28/2005 12/02/2005 Identification and Resolution of Problems IP 71152B 1, 2 3
PB4-PI&R
- PROBLEM IDENTIFICATION & RESOLUTION Baseline Inspections 12/12/2005 12/16/2005 Identification and Resolution of Problems IP 71152B 1, 2 2
EB3-ISI
- U1 INSERVICE INSPECTION Baseline Inspections 03/13/2006 03/17/2006 Inservice Inspection Activities - BWR IP 7111108G 2
3 EB1-MODS
- MODIFICATIONS/10CFR50.59 Baseline Inspections 04/03/2006 04/07/2006 Evaluation of Changes, Tests, or Experiments IP 7111102 1, 2 Baseline Inspections 04/03/2006 04/07/2006 Permanent Plant Modifications IP 7111117B 1, 2 1
PS1-RP
- RP PUBLIC PRE-INSP VISIT Baseline Inspections 08/07/2006 08/09/2006 Access Control to Radiologically Significant Areas IP 7112101 1, 2 4
PS1-RP
- RP PUBLIC INSPECTION Baseline Inspections 08/28/2006 09/01/2006 Access Control to Radiologically Significant Areas IP 7112101 1, 2 Baseline Inspections 08/28/2006 09/01/2006 Radiation Monitoring Instrumentation and Protective Equipment IP 7112103 1, 2 Baseline Inspections 08/28/2006 09/01/2006 Radioactive Gaseous and Liquid Effluent Treatment and Monitoring Systems IP 7112201 1, 2 Baseline Inspections 08/28/2006 09/01/2006 Radiological Environmental Monitoring Program (REMP) And Radioactive Material Control P IP 7112203 1, 2 Baseline Inspections 08/28/2006 09/01/2006 Performance Indicator Verification IP 71151 1, 2 3
PS2-EP
- EP EXERCISE Baseline Inspections 11/06/2006 11/10/2006 Exercise Evaluation IP 7111401 1, 2 Baseline Inspections 11/06/2006 11/10/2006 Emergency Action Level and Emergency Plan Changes IP 7111404 1, 2 Baseline Inspections 11/06/2006 11/10/2006 Performance Indicator Verification IP 71151 1, 2 2
- REQUAL INSPECTION Baseline Inspections 11/13/2006 11/17/2006 Licensed Operator Requalification Program IP 7111111B 1, 2 This report does not include INPO and OUTAGE activities.
This report shows only on-site and announced inspection procedures.
Enclosure
Brunswick Inspection / Activity Plan 09/01/2005 - 03/31/2007 Inspection Type Inspection Activity Planned Dates Start End No. of Staff on Site Title Unit Number Page 2 of 2 08/30/2005 07:26:46 Report 22 1
EB3-HS
- HEAT SINK Baseline Inspections 12/04/2006 12/08/2006 Heat Sink Performance IP 7111107B 1, 2 3
OL PREP
- INITIAL EXAM PREP Not Applicable 01/22/2007 01/26/2007 BRUNSWICK/EXAM AT POWER FACILITIES V23226 1
1 PSB1
- RP OCCUPATIONAL PRE-INSP VISIT Baseline Inspections 02/05/2007 02/07/2007 Access Control to Radiologically Significant Areas IP 7112101 1, 2 3
OL EXAM
- INITIAL EXAM Not Applicable 02/12/2007 02/16/2007 BRUNSWICK/EXAM AT POWER FACILITIES V23226 1
Not Applicable 02/26/2007 03/02/2007 BRUNSWICK/EXAM AT POWER FACILITIES V23226 1
2 EB3-MR
- MR EFFECTIVENESS Baseline Inspections 02/26/2007 03/02/2007 Maintenance Effectiveness IP 7111112B 1, 2 3
PSB1
- RP BASELINE INSP-WK1 Baseline Inspections 03/05/2007 03/09/2007 Access Control to Radiologically Significant Areas IP 7112101 1, 2 Baseline Inspections 03/05/2007 03/09/2007 ALARA Planning and Controls IP 7112102 1, 2 Baseline Inspections 03/05/2007 03/09/2007 Radioactive Material Processing and Transportation IP 7112202 1, 2 Baseline Inspections 03/05/2007 03/09/2007 Performance Indicator Verification IP 71151 1, 2 3
PSB1
- RP OCCUPATIONAL INSP-WK2 Baseline Inspections 03/17/2007 03/23/2007 Access Control to Radiologically Significant Areas IP 7112101 1, 2 Baseline Inspections 03/17/2007 03/23/2007 ALARA Planning and Controls IP 7112102 1, 2 Baseline Inspections 03/17/2007 03/23/2007 Radioactive Material Processing and Transportation IP 7112202 1, 2 Baseline Inspections 03/17/2007 03/23/2007 Performance Indicator Verification IP 71151 1, 2 This report does not include INPO and OUTAGE activities.
This report shows only on-site and announced inspection procedures.