Dominion Energy Kewaunee, Inc.

N490 Highway 42, Kewaunee, WI 54216-9511 Dominior U. S. Nuclear Regulatory Commission Serial No.05-499 Attention: Document Control Desk KPS/LIC/TM: R1 Washington, DC 20555 Docket No. 50-305 AUG 04 2005 License No. DPR-43 DOMINION ENERGY KEWAUNEE, INC.

KEWAUNEE POWER STATION RESPONSE TO REQUEST FOR ADDITIONAL INFORMATION REGARDING RISK-INFORMED INSERVICE INSPECTION PROGRAM PLAN (TAC NO. MC2537)

In a letter from Michael G. Gaffney (Nuclear Management Company, LLC) to Document Control Desk (NRC), "Response To Request For Additional Information Regarding Risk-Informed Inservice Inspection Program Plan (TAC No. MC2537)" dated June 17, 2005, the Nuclear Management Company, LLC (NMC) responded to a request for additional information concerning the Kewaunee Power Station (KPS) Inservice Inspection Program for the Fourth Inspection Interval submittal dated December 16, 2003.

On July 19, 2005, a conference call was held between the Nuclear Regulatory Commission (NRC) staff and Dominion Energy Kewaunee, Inc. (DEK) staff to discuss the June 17, 2005, response. Specifically, the NRC staff had a question concerning NMC's response to question 3.10(b). The question stated and NMC's response follows:

b) Please confirm that none of the piping-related nondestructive examination (NDEs) to be performed for the Appendix F augmented inspection programs is being credited toward the count of NDEs (locations) for RI-ISI. Otherwise, please describe which programs you intend to do this with, how many welds from each program you intend to credit toward the count of NDEs for Rl-ISI, and why you feel that the prescribed augmented inspection NDE will adequately suffice for the examination method(s) required under RI-ISI.

KNPP Response 3.10 (b)

This is to confirm that none of the additional examinations, with the exception of the Flow Accelerated Corrosion (FAC) Program per Nuclear Regulatory Commission Generic Letter 89-08 requirements, performed in the Appendix F Augmented Examinations of the Kewaunee Nuclear Power Plant Fourth Ten-Year ISI Program 2004-2014 will be credited to the Risk Informed Program.

During the teleconference, question 3.10(b) and the response provided were discussed.

DEK staff determined they had misunderstood the question and hereby submits the following response to NRC question 3.10(b):

?1\ IV

Serial No.05-499 Page 2 of 2 DEK Response 3.10(b)

This is to confirm that none of the additional examinations performed in the Appendix F Augmented Examination Program of the Kewaunee Power Station Fourth Ten-Year ISI Program 2004-2014 will be credited to the count of Risk-Informed Program piping-related nondestructive examinations (NDEs).

If you have any further questions, please contact Gerald Riste at (920) 388-8424.

Very truly yours, Michael G. Gaffney Site Vice President Commitments made by this letter: NONE cc: Mr. J. L. Caldwell Administrator Region IlIl U.S. Nuclear Regulatory Commission 2443 Warrenville Road Suite 210 Lisle, IL 60532-4352 Mr. J. F. Stang Project Manager U.S. Nuclear Regulatory Commission Mail Stop 0-8-H-4a Washington, D. C. 20555 Mr. S. C. Burton NRC Senior Resident Inspector Kewaunee Power Station