Summary of Meeting on 7/6/05, W/Southern California Edison to Discuss Management of Inconel 600 Material at SONGS Unit 2 & 3 TAC MC7522 and MC7523
ML052090218
Person / Time
Site: San Onofre  Southern California Edison icon.png
Issue date: 07/27/2005
From: Bo Pham
NRC/NRR/DLPM/LPD4
To: Dan Collins
NRC/NRR/DLPM/LPD4
Pham B, NRR/DLPM, 415-8450
Shared Package
ML052090242 List:
References
TAC MC7522, TAC MC7523
Download: ML052090218 (6)


Text

July 27, 2005 MEMORANDUM TO: Daniel Collins, Acting Chief, Section 2 Project Directorate IV Division of Licensing Project Management Office of Nuclear Reactor Regulation

/RA/

FROM: Bo Pham, Project Manager, Section 2 Project Directorate IV Division of Licensing Project Management Office of Nuclear Reactor Regulation

SUBJECT:

SUMMARY

OF MEETING HELD ON JULY 6, 2005, WITH SOUTHERN CALIFORNIA EDISON TO DISCUSS MANAGEMENT OF INCONEL 600 MATERIAL AT SAN ONOFRE NUCLEAR GENERATING STATION (SONGS), UNITS 2 AND 3 (TAC NOS. MC7522 AND MC7523)

On July 6, 2005, Southern California Edison (SCE or the licensee) met with the U.S. Nuclear Regulatory Commission (NRC) staff to discuss its plans for managing Inconel 600 materials inspections during the next refueling outage at SONGS, Units 2 and 3.

The NRC opened with comments about this meeting being one of a few times where a licensee has come to provide an advance briefing of its inspection plans for upcoming outages. The NRC staff suggested that perhaps a telephone call after the next outage would allow everyone to gather feedback on the helpfulness of this briefing.

The licensee next gave its presentation, attached and available on the Agency Document Access and Management System (Accession No. ML052010117), which addressed SCEs plans for performing inspections on steam generators, reactor pressure vessel head, pressurizer heater sleeves, reactor coolant system penetrations, and reactor coolant system 82/182 butt welds.

The NRC staff had various questions throughout the presentation. Action items from the meeting include:

! SCE was asked to expedite its requests for relief for (1) reactor pressure vessel head nozzle no. 56 with a 78 percent through wall flaw in Unit 3, and (2) temper bead repair methodology for the reactor pressure vessel head vent nozzle. SCE agreed to provide an improved forecast of dates for submitting both items.

! SCE will confirm for the NRC staff if it has approval to implement leak-before-break methodology, especially for piping systems with 82/182 butt welds.

! SCE will confirm if there are any exceptions to the 100 percent bare metal visual inspections for butt welds.

D. Collins  ! SCE will inform the NRC about how it intends to address the potential for having flaws in the J-groove welds of the proposed new reactor vessel heads (reviewing industry experience at plants that have undertaken head replacement).

! SCE will confirm with the NRC whether any exceptions were taken to the Appendix VIII Performance Demonstration Initiative (PDI) inspections of the Alloy 82/182 butt welds.

! SCE will inform the NRC whether the PDI inspections are capable of sizing a flaw, and if SCE is using a manual inspection technique.

! SCE will provide the NRC with a copy of its current Alloy 600 program, and a copy of the updated program following the incorporation of MRP-126.

Members of the public did not have any comments during the meeting. A list of meeting attendees is attached.

Docket Nos. 50-361 and 50-362 Attachments: As stated cc w/atts: See next page

ML052090218 NRC-001 OFFICE PDIV-2/PM PDIV-2/LA PDIV-2/(A)SC NAME BPham DBaxley DCollins DATE 7/25/05 7/25/05 7/27/05 E:\Filenet\ML052090218.wpd ATTENDEES MEETING WITH SOUTHERN CALIFORNIA EDISON (SCE)

JULY 6, 2005 SCE B. Katz J. Rainsberry E. Scherer M. Short T. Raidy A. Matheny E. Schoonover J. Hedrick R. Cole NRC W. Bateman B. Pham B. Hardies D. Collins*

J. Tsao*

K. Karworski*

A. Black T. Chan*

M. Mitchell*

L. Lund*

PUBLIC S. Schoonover

  • Indicates part-time attendance

San Onofre Nuclear Generating Station Units 2 and 3 cc:

Mr. Daniel P. Breig, Plant Manager Mr. Ed Bailey, Chief Nuclear Generation Radiologic Health Branch Southern California Edison Company State Department of Health Services San Onofre Nuclear Generating Station Post Office Box 997414 (MS7610)

P. O. Box 128 Sacramento, CA 95899-7414 San Clemente, CA 92674-0128 Resident Inspector/San Onofre NPS Mr. Douglas K. Porter c/o U.S. Nuclear Regulatory Commission Southern California Edison Company Post Office Box 4329 2244 Walnut Grove Avenue San Clemente, CA 92674 Rosemead, CA 91770 Mayor Mr. David Spath, Chief City of San Clemente Division of Drinking Water and 100 Avenida Presidio Environmental Management San Clemente, CA 92672 P. O. Box 942732 Sacramento, CA 94234-7320 Mr. James T. Reilly Southern California Edison Company Chairman, Board of Supervisors San Onofre Nuclear Generating Station County of San Diego P.O. Box 128 1600 Pacific Highway, Room 335 San Clemente, CA 92674-0128 San Diego, CA 92101 Mr. James D. Boyd, Commissioner Eileen M. Teichert, Esq. California Energy Commission Supervising Deputy City Attorney 1516 Ninth Street (MS 31)

City of Riverside Sacramento, CA 95814 3900 Main Street Riverside, CA 92522 Mr. Ray Waldo, Vice President Southern California Edison Company Mr. Gary L. Nolff San Onofre Nuclear Generating Station Power Projects/Contracts Manager P.O. Box 128 Riverside Public Utilities San Clemente, CA 92764-0128 2911 Adams Street Riverside, CA 92504 Mr. Brian Katz Vice President, Nuclear Oversight and Regional Administrator, Region IV Regulatory Affairs.

U.S. Nuclear Regulatory Commission San Onofre Nuclear Generating Station 611 Ryan Plaza Drive, Suite 400 P.O. Box 128 Arlington, TX 76011-8064 San Clemente, CA 92764-0128 Mr. Michael Olson San Diego Gas & Electric Company P.O. Box 1831 San Diego, CA 92112-4150 April 2005

San Onofre Nuclear Generating Station Units 2 and 3 cc:

Mr. Steve Hsu Department of Health Services Radiologic Health Branch MS 7610, P.O. Box 997414 Sacramento, CA 95899 Adolfo Bailon Field Representative United States Senator Barbara Boxer 312 N. Spring St. Suite 1748 Los Angeles, CA. 90012 Mr. Harold B. Ray Executive Vice President Southern California Edison Company San Onofre Nuclear Generating Station P.O. Box 128, Mail Stop: D-3-F San Clemente, CA 92674-0128