r Committed to Nuclear Excellen e1 PUMT IM~

  • VIREE Point Beach Nuclear Plant U1R28 OCC Interactive Turnover Meeting Agenda Saturday, May 15, 2004 Start Time: 0600 NSB Cafeteria BRIEFING NOTES ATTENDEES Shift Outage Directors Shift Outage Managers (SOM)

Operations Coordinators (SOC)

Maintenance Coordinators (MOC)

Engineer/ Projects Coordinators (EOM)

Rad Protection Manager (RPM)

Site Safety Coordinator (SSC)

Shutdown Safety Assessor (SSA)

Site Management (SSM)

General Supervisors First Une Supervisors Agenda

1. Safety Issue Discussion (SSC)
2. Radiation Protection (RPM)
3. Operations Coordinator Turnover (SOC)
4. Shutdown Safety Assessment (SSA)

S. Maintenance Coordinator Turnover (MOC)

6. Engineering Coordinator Turnover (EOM)
7. Major Projects Update (EOM)
8. Schedule Review (SOM)
9. Management Expectations (SSM)
10. ACEMAN Assessment Results (SOM)
11. Shift Goals (SOM)

Items Included In Daily Package:

- Site Communication

- Safety Snippet

- Outage Alara Report

- Outage Status Report

- Shutdown Safety Assessment

- Defined Critical Path

- Work Activity Risk Assignment

- Outage Schedule  :::j F - -

k Wrmaintbreodwmd*d a -

Inamrd wita Freedom of liformaJ Yr A 1ex FA SA:- 1

- I

NCt N Conmmlttd to Nuclear Eciec SnMiEY O W~LiSel POMTr 1EF= - gums Point Beach Nuclear Plant U1R28 Refueling Outage

2. , ! Safet-YTokIc for week ofMay 9-15 Theme for the week' This week's theme covers Emergency Situations. Be it weather, fire or a medical emergency, are we ready to respond to those unexpected situations?

.DailyIySafety Snippet .

Sunday "You would be shocked if you found your emergency egress path blocked' Material Is beginning to come out of containment as a lot of work is wrapping up. Don't pile up tools and equipment Inthe walkway even for short periods of time. Always keep the egress paths open for use.

Monday

'f strong winds start to blow, do you know where to go?"

Do you know the proper location to go in the event of a tornado warning It you are in the trailers, turbine hall or PAB? NP1.9.21 covers the site's various shelter areas. Plan ahead and take the time now to review the NP with your group.

Tuesday mlake sure to cleanup or a fire may start during heat up.

OE15310 Indian Point 3 - An oil vapor extractor for the main boiler feed pump failed. The tag out used to repair the extractor resulted Inan increased leakage of oil from the pump bearings onto lagging. A special log was created to monitor the leakage, but no plan existed for dealing with the safety hazards.

Maintenance repaired the extractor; returning it to service. The next day a portion of oil soaked lagging on a main boiler feed pump caught fire and was quickly extinguished by an alert watchstander.

Wednesday "rake heed - Don't block emeryency equipment you may need."

Last week on the 66ft of containment, the NRC noticed we blocked access to 2 fire extinguishers mounted on the stairwell handrail. A scaffold was built Inthe area that made access questionable. We then added a number of bags of Insulation it made access Impossible. Just a question -Why is the NRC finding this Instead of us? .

Thursday

'What number do you call if your co-worker takes a serious fall?'

What Is the plant's emergency number? 2911. This number Is only to be used for emergency situations.

Two weeks ago a work group was having trouble getting through to operations to communicate a change In equipment status. Rather than waiting, the Individual Involved decided to contact the control room via the emergency number. Needless to say this was not an appropriate use of 2911.

Friday WAake sure your fire watch is alert to keep someone from getting hart" OE12607 - LaSalle - A worker using an acetylene torch for cutting through a structural member that was behind a metal wall panel. Wall Insulation behind the member began to burn. The alert fire watch extinguished the fire within one minute of It beginning and no significant damage occurred.

Saturday

'Debris buildup may result in an unplanned heat up" OE14899 River Bend Station - A small fire occurred under the exhaust piping on a diesel generator during testing. The fire was observed during routine checks of the generator and the control room was Immediately notified. The control room unloaded the generator while the operator extinguished the fire. The cause was Insulation debris that accumulated around the hot piping over time.

2

Point Beach Nuclear Plant Outage 1R28 Path Picture DAY 40 N Meets Supporting Operational Excellence Outage Radiation Performance fl,~inn'n P.Ana~t =y,.arjle 3- U S. I S £_ I ._ _

This indicator measures cumulative dose radiation exposure and Day 40 - May 13 Actual = 0.146 total number of personnel-contamination events (PCE's > 5000 Cumulative = 54.869 cpm) during refueling outages. The dose indicator is measured in Cumulative Forecast = 54.974 Rem and individual PCE events.

Daily PCE goal reforecast on 4/23. Daily dose reforecast on 5/S004.

Meets: <=75 Rem Actual Gum. Reactor Head Repair Dose for May 13th Is 0.854 vs. goal of 0.663.

Exceeds: <=71 Rem Dose: 54.869 Rem RV Head Total Dose Is 9.026.

Meets: <=18 Exceeds: <=12 Actual PCE's: 9

- - - S 0- S 0I CAw Stu Thomas I Personnel Contamination Events Cummulative Dose Exposure 20 18 IC U

Z0 i 6 16 14 Ca 12 I 10 8

I 4.-

I I

--I. -~t

. .. .oreas a,

0l a,

0)

~

- Actual

- . . .. Forecast Goal 4

2 0

0 2 4 6 8 10121416182022242628303234363840424446485052 0 2 46 8101214161&NM4683032436344648502

- 'Cammftfed to Ntuclear Exla e Outage Status Report Plant: Point Beach Unit I Day: Saturday Today's Date I Time: 5/15/04 0330 Outage Duration: Day 42 Of Refueling Outage Number UIR28 Safety Status Industrial - Within the last 12 hours1.388889e-4 days <br />0.00333 hours <br />1.984127e-5 weeks <br />4.566e-6 months <br /> OSHA Recordables 0 First Aid cases 0 Near misses 0 Total for this outage I Summary:

Radiological Dose to date 54.869 Projected to date

  • 54.974 Outage Goal s75 R Difference -.105
  • Reforecast on 5/8 Number of PCEs 9 Summary: Reactor Head Repair Dose for May 13"h is 0.854 vs. goal of 0.663. RV Head Total Dose is 9.026.

Nuclear Significant human performance errors and events in last 24 hours2.777778e-4 days <br />0.00667 hours <br />3.968254e-5 weeks <br />9.132e-6 months <br /> 0 Summary:

Plant Status Mode: Ea Hot Standby (Mfode 3) E Hot Shutdown (Mode4) E] Cold Shutdown (Modes) 0Refueling Shutdown (Mode 6)

RCS: Temperature: 82 Pressure: Vented to Atmosphere RV Level: Rod Latch Height Time to Boll: 30 hours3.472222e-4 days <br />0.00833 hours <br />4.960317e-5 weeks <br />1.1415e-5 months <br /> Shutdown Safety Assessment Protected Equipment:

AMajor Activities Completed In Last 24 Hours Critical Path and Near Critical Path Activities (Next 24 Hour

  • Complete Cooldown & Final NDE of Reactor Head Repair Area
  • Upper Internals Lift Rig Paint Stripping and NDE
  • UT Inspections Penetration #32 and #33
  • Supply IB03 from 1B04 - Preps
  • IXII XFMR Bkrs and Recover 480V Bus Alignment Significant Outstanding Issues Date Issue Due Responsibility 5/03/04 Reactor Vessel Head Repair Penetration #26 5/16/04 John Walsh 5/13/04 IP-1A RCP Motor Oil 5/15/04 Dan Laing 5/14/04 T-26 Steam Generator Blowdown Tank 5/17/04 Scott Manthei

.___ _ Upcoming Ma or Milestones Scheduled Ac ual Scheduled Actual Date L Time Date Time _ .Date Time Date Time Cooldown <200° 4/03/04 2100 4/03/04 2230 RCS Fill & Vent 4/23/04 1500 Head Lift 4/09/04 0900 4/21/04 1550 Heatup >2000 4/25/04 0900 .

Refueled 4/14/04 0300 5/02/04 1848 Reactor Critical _4/28/04 0800 RV Headset 4/18/04 1900 On-Line 4/30/04 0100 4

Point Beach Nuclear Plant PBNP SHUTDOWN SAFETY ASSESSMENT AND FIRE CONDITION CHECKLIST OUTAGE SAFETY ASSESSMENT UNIT: I DATE: May 15,2004 TIME: 0230 KEY SAFETY FUNCTIONS:

REACTIVITY: GREEN CORE COOLING: GREEN POWER AVAILABLE: GREEN INVENTORY: GREEN CONTAINMENT: YELLOW SFP COOLING: NA PROTECTED EQUIPMENT:

= _ _

COMMENTS: e j, RCS Time to Boil is 30 hours3.472222e-4 days <br />0.00833 hours <br />4.960317e-5 weeks <br />1.1415e-5 months <br />. Using NP 10.3.6 Time To Boil curves.

Fire Protection Condition IV: Credit is taken for fire rounds as fire prevention contingency PBr-1562 Rcirenccs: NP 10.3.6 Revision 2 10/30/02 5 Page 5 of 9 NP 10.2.1