July 18, 2005 Mr. Russell Bell Nuclear Energy Institute (NEI)
Suite 400 1776 I Street, N.W.
Washington, DC 20006-3708
SUBJECT:
COMMENT LETTER NUMBER 4 - NRC STAFF COMMENTS ON NEI 04-01, REVISION D, DRAFT GUIDELINE FOR COMBINED LICENSE APPLICANTS UNDER 10 CFR PART 52
Dear Mr. Bell:
By letter dated December 21, 2004, NEI submitted NEI 04-01 to facilitate the discussion with NRC concerning the information needed to evaluate a combined license application (ADAMS Accession Number ML050110295). Enclosed is a table (ADAMS Accession No. ML051930012) which includes NRC staff first-round comments on portions of NEI 04-01. The U.S. Nuclear Regulatory Commission (NRC) plans to issue additional first-round comment letters on NEI 04-01, Revision D, with the goal of issuing a complete set of first-round comments by the end of June 2005. Each comment has been numbered such that the NRC can track its resolution. The comments have been segregated into either comments the staff believes are needed to make the guidance reflective of NRC regulations and guidance or suggested changes to improve the guidance.
Please contact me at 301-415-2753 or jxc1@nrc.gov if you have any additional questions.
Sincerely,
/RA/
Joseph Colaccino, Senior Project Manager New Reactors Section New, Research and Test Reactors Program Division of Regulatory Improvement Programs Office of Nuclear Reactor Regulation Project No. 689
Enclosure:
As stated cc w/encl: See next page
ML051930012) which includes NRC staff first-round comments on portions of NEI 04-01. The U.S. Nuclear Regulatory Commission (NRC) plans to issue additional first-round comment letters on NEI 04-01, Revision D, with the goal of issuing a complete set of first-round comments by the end of June 2005. Each comment has been numbered such that the NRC can track its resolution. The comments have been segregated into either comments the staff believes are needed to make the guidance reflective of NRC regulations and guidance or suggested changes to improve the guidance.
Please contact me at 301-415-2753 or jxc1@nrc.gov if you have any additional questions.
Sincerely,
/RA/
Joseph Colaccino, Senior Project Manager New Reactors Section New, Research and Test Reactors Program Division of Regulatory Improvement Programs Office of Nuclear Reactor Regulation Project No. 689
Enclosure:
As stated cc w/encl: See next page Distribution: See next page ADAMS ACCESSION NO. ML051930006 OFFICE PM:RNRP SC:RNRP NAME JColaccino LDudes DATE 7/18/2005 7/14/2005
Distribution for Comment Letter No. 4 dated July 18, 2005 Hard Copy RNRP R/F JColaccino LDudes E-Mail PUBLIC JDyer (RidsNrrOd)
RBorchardt BSheron (RidsNrrAdpt)
FEltawila NRR/ADPT Secretary [RidsNrrAdpt]
NEI 04-01 Reviewers RNRP Group DMatthews BBoger CCarpenter SRichards DCoe TQuay JHannon JWermiel WBateman MMitchell JCalvo TJKim, EDO MJohnson CCasto MStutzke DRoberts PSekerak DJohnson RMcIntyre TFoley SAlexander TMensah (NRR Communication Coord)
ACRS (RidsAcrsMailCenter)
OPA MEl-Zeftway JBlake RGardner CPaulk LCampbell MItzkowitz, OGC GMizuno, OGC TKenyon PQualls DNelson, OE MChiramal PLoeser JJennings YLi RWeisman EKleeh SHom MAAshley External e-mail bhupinder.singh@hq.doe.gov tom.miller@hq.doe.gov Vanessa.Quinn@dhs.gov Kenneth.Wierman@dhs.gov James.Purvis@dhs.gov
July 19, 2005 Combination List:
cc:
Mr. Charles Brinkman Westinghouse Electric Co.
Washington Operations 12300 Twinbrook Pkwy., Suite 330 Rockville, MD 20852 Mr. David Lochbaum, Nuclear Safety Engineer Union of Concerned Scientists 1707 H Street, NW, Suite 600 Washington, DC 20006-3919 Mr. Paul Gunter Nuclear Information & Resource Service 1424 16th Street, NW, Suite 404 Washington, DC 20036 Mr. James Riccio Greenpeace 702 H Street, NW, Suite 300 Washington, DC 20001 Mr. Adrian Heymer Nuclear Energy Institute Suite 400 1776 I Street, NW Washington, DC 20006-3708 Mr. George Alan Zinke Project Manager Nuclear Business Development Entergy Nuclear M-ECH-683 1340 Echelon Parkway Jackson, MS 39213 Mr. Thomas P. Miller U.S. Department of Energy NE-20, Rm. A286 Headquarters-Germantown 19901 Germantown Road Germantown, MD 20874-1290 Ms. Marilyn Kray Vice President, Special Projects Exelon Generation 200 Exelon Way, KSA3-E Kennett Square, PA 19348 Mr. Laurence Parme Manager, GT-MHR Safety &
Licensing General Atomics Company P.O. Box 85608 San Diego, CA 92186-5608 Mr. Joseph D. Hegner Lead Engineer - Licensing Dominion Generation Early Site Permitting Project 5000 Dominion Boulevard Glen Allen, VA 23060 Mr. Edward L. Quinn MDM Services Corporations Utility Operations Division 28202 Cabot Road, Suite 205 Laguna Nigual, CA 92677 Ms. Lynn Connor Doc-Search Associates 2211 sw 1ST Ave - #1502 Portland, OR 97201 Mr. Paul Leventhal Nuclear Control Institute 1000 Connecticut Avenue, NW Suite 410 Washington, DC 20036 Ms. Patricia Campbell Morgan, Lewis & Bockius, LLP 1111 Pennsylvania Avenue, NW Washington, DC 20004 Mr. W. Edward Cummins AP600 and AP1000 Projects Westinghouse Electric Company P.O. Box 355 Pittsburgh, PA 15230-0355 Dr. Robert E. Gamble Manager, ESBWR GE Nuclear Energy 1989 Little Orchard St., M/C 365 San Jose, CA 95125-1030 July 19, 2005 Dr. Jack W. Roe Vice President Advanced Technologies & Laboratories International, Inc.
20010 Century Boulevard, Suite 500 Germantown, MD 20874 Mr. Stephen P. Frantz Morgan, Lewis, & Bockius, LLP 1111 Pennsylvania Avenue, NW Washington, DC 20004 Mr. Gary Wright, Manager Office of Nuclear Facility Safety Illinois Department of Nuclear Safety 1035 Outer Park Drive Springfield, IL 62704 Mr. Brendan Hoffman Research Associate on Nuclear Energy Public Citizens Critical Mass Energy and Environmental Program 215 Pennsylvania Avenue, SE Washington, DC 20003 Mr. Tom Clements 6703 Gude Avenue Takoma Park, MD 20912 Mr. Lionel Batty Nuclear Business Team Graftech 12300 Snow Road Parma, Ohio 44130 Mr. Ian M. Grant Canadian Nuclear Safety Commission 280 Slater Street, Station B P.O. Box 1046 Ottawa, Ontario K1P 5S9 Mr. Edward F. Sproat, III Vice President - Intl Projects Exelon Generation 200 Exelon Way Kennett Square, PA 19348 Mr. Glenn H. Archinoff AECL Technologies 481 North Frederick Avenue Suite 405 Gaithersburg, MD. 20877 Dr. Regis A. Matzie Senior Vice President and Chief Technology Officer Westinghouse Electric Company 2000 Day Hill Road Windsor, CT 06095-0500 Mr. Ed Wallace, General Manager Projects PBMR Pty LTD PO Box 9396 Centurion 0046 Republic of South Africa Mr. Dobie McArthur Director, Washington Operations General Atomics 1899 Pennsylvania Avenue, NW Suite 300 Washington, DC 20006 Mr. Russell Bell Nuclear Energy Institute Suite 400 1776 I Street, NW Washington, DC 20006-3708 Ms. Vanessa E. Quinn, Chief Radiological Emergency Preparedness Section Nuclear & Chemical Hazards Branch Federal Emergency Management Agency/DHS 500 C Street, SW Washington, D.C. 20472 Mr. Ron Simard 6170 Masters Club Drive Suwanee, GA 30024 July 19, 2005 Mr. Jerald S. Holm Framatome ANP, Inc.
3315 Old Forest Road P.O. Box 10935 Lynchburg, VA 24506-0935 Ms. Kathryn Sutton, Esq.
Morgan, Lewis & Bockius, LLP 1111 Pennsylvania Avenue, NW Washington, DC 20004 Ms. Anne W. Cottingham Winston & Strawn LLP 1700 K Street, NW Washington, DC 20006-3817 Mr. Robert E. Sweeney IBEX ESI 4641 Montgomery Avenue Suite 350 Bethesda, MD. 20814 E-Mail:
jerald.holm@framatome-anp.com mwetterhahn@winston.com gcesare@enercon.com whorin@winston.com rob.sweeney@ibexesi.com