May 24, 2005 LICENSEE: EXELON GENERATION COMPANY, LLC FACILITY:

BRAIDWOOD NUCLEAR GENERATING PLANT

SUBJECT:

SUMMARY

OF THE MAY 11, 2005, PUBLIC MEETING TO DISCUSS THE BRAIDWOOD END-OF-CYCLE PLANT PERFORMANCE ASSESSMENT On May 11, 2005, a public meeting was held at the Fossil Ridge Library, 386 Kennedy Road Braidwood, IL 60408. The meeting was between the Nuclear Regulatory Commission (NRC) and Braidwood management and staff. The purpose of the meeting was to discuss NRCs assessment of Braidwoods performance for the period of January 1, 2004, through December 31, 2004. Mr. Keith Polson, the Site Vice-President, was present on behalf of Exelon.

During the NRC presentation, an overall assessment of Braidwoods performance was provided. As explained in the Annual Assessment letter from NRC to Mr. Christopher M. Crane, dated March 2, 2005, (reference ADAMS accession number ML050620309), Braidwood Units 1 and 2 operated in a manner that preserved public health and safety and fully met all cornerstone objectives.

Following the NRC presentation, Mr. Dave Passehl introduced the new Braidwood Resident Inspector, Mr. Gregory Roach. In addition, Mr. Passehl introduced Mr. Rob Ruiz, who was named the temporary Resident Inspector until the onsite arrival of Mr. Roach.

The meeting notice and NRC presentation can be found in ADAMS as ML051030276 and ML051370585 respectively. A list of NRC and licensee meeting participants can be found in the attached Enclosure. There were no members of the public in attendance at this meeting.

/RA/

David Passehl, Chief Division of Reactor Projects Branch 3 Docket Nos. 50-456; 50-457 License Nos. NPF-72; NPF-77

Enclosure:

As Stated See Attached Distribution

May 24, 2005 LICENSEE: EXELON GENERATION COMPANY, LLC FACILITY:

BRAIDWOOD NUCLEAR GENERATING PLANT

SUBJECT:

SUMMARY

OF THE MAY 11, 2005, PUBLIC MEETING TO DISCUSS THE BRAIDWOOD END-OF-CYCLE PLANT PERFORMANCE ASSESSMENT On May 11, 2005, a public meeting was held at the Fossil Ridge Library, 386 Kennedy Road Braidwood, IL 60408. The meeting was between the Nuclear Regulatory Commission (NRC) and Braidwood management and staff. The purpose of the meeting was to discuss NRCs assessment of Braidwoods performance for the period of January 1, 2004, through December 31, 2004. Mr. Keith Polson, the Site Vice-President, was present on behalf of Exelon.

During the NRC presentation, an overall assessment of Braidwoods performance was provided. As explained in the Annual Assessment letter from NRC to Mr. Christopher M. Crane, dated March 2, 2005, (reference ADAMS accession number ML050620309), Braidwood Units 1 and 2 operated in a manner that preserved public health and safety and fully met all cornerstone objectives.

Following the NRC presentation, Mr. Dave Passehl introduced the new Braidwood Resident Inspector, Mr. Gregory Roach. In addition, Mr. Passehl introduced Mr. Rob Ruiz, who was named the temporary Resident Inspector until the onsite arrival of Mr. Roach.

The meeting notice and NRC presentation can be found in ADAMS as ML051030276 and ML051370585 respectively. A list of NRC and licensee meeting participants can be found in the attached Enclosure. There were no members of the public in attendance at this meeting.

/RA/

David Passehl, Chief Division of Reactor Projects Branch 3 Docket Nos. 50-456; 50-457 License Nos. NPF-72; NPF-77

Enclosure:

As Stated See Attached Distribution DOCUMENT NAME: G:\\Branch TSS\\EOC Mtg. Notices 2005\\Mtg. Summaries\\Braidwood.wpd To receive a copy of this document, indicate in the box "C" = Copy without attachment/enclosure "E" = Copy with attachment/enclosure "N" = No copy OFFICE RIII NAME DPassehl:co DATE 05/24/05 OFFICIAL RECORD COPY

Exelon Generation Company, LLC cc w/encl:

Site Vice President - Braidwood Station Plant Manager - Braidwood Station Regulatory Assurance Manager - Braidwood Station Chief Operating Officer Senior Vice President - Nuclear Services Vice President - Operations Support Vice President - Licensing and Regulatory Affairs Director Licensing Manager Licensing - Braidwood and Byron Senior Counsel, Nuclear, Mid-West Regional Operating Group Document Control Desk - Licensing Assistant Attorney General Illinois Department of Nuclear Safety State Liaison Officer Chairman, Illinois Commerce Commission

Exelon Generation Company, LLC ADAMS Distribution:

GYS GFD RidsNrrDipmIipb GEG KGO NXS CAA1 DRPIII DRSIII PLB1 JRK1

Enclosure Meeting Participants NRC D. Passehl, Chief, Branch 3, Division of Reactor Projects N. Shah, Senior Resident Inspector, Braidwood G. Roach, Resident Inspector, Braidwood R. Ruiz, Resident Inspector (temporary), Braidwood Exelon Generation Company Keith Polson, Site VP Neil Miller, Exelon Communications David Chrzanowski, Licensing Engineer Scott Butler, Licensing Engineer Dale Ambler, Regulatory Assurance Manager Illinois Emergency Management Agency Jeff Roman Rick Zuffa