Category:Letter
MONTHYEARIR 05000369/20240032024-11-0404 November 2024 Integrated Inspection Report 05000369/2024003 and 05000370/2024003 IR 05000413/20240032024-11-0404 November 2024 Integrated Inspection Report 05000413/2024003 and 05000414/2024003 IR 05000269/20240032024-10-31031 October 2024 Integrated Inspection Report 05000269/2024003 and 05000270/2024003 and 05000287/2024003 (2) ML24303A4212024-10-30030 October 2024 Mcguire Nuclear Station, Units 1 & 2, Notification of an NRC Fire Protection Team Inspection FPTI NRC 05000369/2025010, 05000370/2025010 and Request for Information RFI ML24255A3322024-10-16016 October 2024 SLRA - Revised SE Letter ML24297A6172024-10-11011 October 2024 PCA Letter to NRC Oconee Hurricane Helene ML24297A6222024-10-11011 October 2024 PCA Letter to NRC Catawba Hurricane Helene ML24269A0912024-10-0909 October 2024 Request for Withholding Information from Public Disclosure IR 05000369/20244022024-10-0808 October 2024 Security Baseline Inspection Report 05000369/2024402 05000370/2024402 IR 05000413/20240112024-10-0101 October 2024 Biennial Problem Identification and Resolution Inspection Report 05000413/2024011 and 05000414/2024011 ML24255A8312024-09-23023 September 2024 Project Manager Assignment ML24261B9782024-09-19019 September 2024 Notification of an NRC Fire Protection Team Inspection NRC Inspection Report 05000413-2024010, 05000414-2024010 and Request for Information IR 05000414/20240912024-09-0505 September 2024 Final Significance Determination of a White Finding and Nov and Assessment Followup Letter-NRC Inspection Report 05000414-2024091 IR 05000413/20240052024-08-26026 August 2024 Updated Inspection Plan for Catawba Nuclear Station (Report 05000413/2024005 & 05000414/2024005) IR 05000369/20240052024-08-26026 August 2024 Updated Inspection Plan for McGuire Nuclear Station, Units 1 and 2, (Report 05000369-2024005 and 05000370-2024005) ML24145A1782024-08-26026 August 2024 Issuance of Amendment Nos. 430, 432, and 431, to TS 5.5.2, Containment Leakage Rate Testing Program for a one-time Extension of the Type a Leak Rate Test Frequency IR 05000269/20240052024-08-26026 August 2024 Updated Inspection Plan for Oconee Nuclear Station, Units 1, 2 and 3 (Report 05000269/2024005, 05000270/2024005, and 05000287-2024005) ML24235A1542024-08-22022 August 2024 Notification of Target Set Inspection and Request for Information (NRC Inspection Report 05000413-2024402 and 05000414-2024402) IR 05000413/20240022024-08-0808 August 2024 Integrated Inspection Report 05000413-2024002 and 05000414-2024002 and Apparent Violation 05000287/LER-2024-001, Procedure Deficiency Results in Inadvertent Automatic Feedwater Isolation and Automatic Emergency Feedwater Actuation2024-08-0202 August 2024 Procedure Deficiency Results in Inadvertent Automatic Feedwater Isolation and Automatic Emergency Feedwater Actuation IR 05000413/20244032024-08-0101 August 2024 Information Request for the Cybersecurity Baseline Inspection, Notification to Perform Inspection 05000413/2024403; 05000414/2024403 IR 05000369/20244042024-08-0101 August 2024 Cover Letter Security Baseline Inspection Report 05000369/2024404 and 05000370/2024404 IR 05000369/20253012024-07-29029 July 2024 Notification of Licensed Operator Initial Examination 05000369/2025301 and 05000370/2025301 IR 05000369/20244032024-07-25025 July 2024 – Cyber Security Inspection Report 05000369/2024403 and 05000370/2024403 Rev IR 05000269/20240022024-07-25025 July 2024 Integrated Inspection Report 05000269/2024002 and 05000270/2024002 and 05000287/2024002 IR 05000369/20240022024-07-24024 July 2024 Integrated Inspection Report 05000369/2024002 and 05000370/2024002 ML24192A1312024-07-15015 July 2024 Licensed Operator Positive Fitness-For-Duty Test ML24183A0972024-07-12012 July 2024 ISFSI; Catawba 1, 2 & ISFSI; McGuire 1, 2 & ISFSI; Oconee 1, 2, 3 & ISFSI; Shearon Harris 1; H. B. Robinson 2 & ISFSI; and Radioactive Package Shipping Under 10 CFR 71 (71-266 & 71-345) – Review of QA Program Changes EPID L-2024-LLQ-0002 IR 05000369/20244012024-07-0303 July 2024 – Security Baseline Inspection Report 05000369/2024401 and 05000370/2024401 ML24183A2352024-06-29029 June 2024 Update 3 to Interim Report Regarding a Potential Defect with Schneider Electric Medium Voltage Vr Type Circuit Breaker Part Number V5D4133Y000 ML24179A1102024-06-27027 June 2024 Submittal of Updated Final Safety Analysis Report Revision 30, Technical Specifications Bases Revisions, Selected Licensee Commitment Revisions, 10 CFR 50.59 Evaluation Summary Report, and 10 CFR 54.37 Update, and Notification ML24178A0552024-06-26026 June 2024 Requalification Program Inspection – Catawba Nuclear Station ML24176A2802024-06-26026 June 2024 Notification of Target Set Inspection and Request for Information (NRC Inspection Report 05000369-2024404 and 05000370-2024404) IR 05000414/20240902024-06-24024 June 2024 NRC Inspection Report 05000414/2024090 and Preliminary White Finding and Apparent Violation ML24170A8632024-06-11011 June 2024 Flowserve June 11, 2024, Part 21 Notification - Redacted Version for Publishing IR 05000369/20240112024-06-0404 June 2024 Biennial Problem Identification and Resolution Inspection Report 05000369/2024011 and 05000370/2024011 ML24144A1162024-05-28028 May 2024 Notification of Inspection and Request for Information for NRC Problem Identification and Resolution Inspection ML24149A1772024-05-28028 May 2024 NRC Response to Duke Energy 2025 FOF Schedule Change Request (Catawba and McGuire) ML24141A0482024-05-17017 May 2024 EN 56958_1 Ametek Solidstate Controls, Inc IR 05000413/20240012024-05-10010 May 2024 Integrated Inspection Report 05000413/2024001 and 05000414/2024001 and Apparent Violation IR 05000369/20240012024-05-0808 May 2024 Integrated Inspection Report 05000369-2024001 and 05000370-2024001 and 07200038-2024001 IR 05000269/20240012024-05-0303 May 2024 Integrated Inspection Report 05000269/2024001, 05000270/2024001 and 05000287/2024001 ML24110A0382024-04-30030 April 2024 – Correction to Issuance of Amendment Nos. 330 and 309, Regarding Implementation of Technical Specifications Task Force (TSTF) Traveler TSTF 505, Revision 2, Provide Risk-Informed Extended Completion Times - Ritstf IR 05000269/20244022024-04-24024 April 2024 Security Baseline Inspection Report 05000269/2024402 and 05000270/2024402 and 05000287/2024402 ML24108A0792024-04-16016 April 2024 EN 57079 Paragon Energy Solutions Email Forwarding Part 21 Interim Report Re Potential Defect with Schneider Electric Medium Voltage Vr Type Circuit Breaker Part Number V5D4133Y000 ML24100A8742024-04-10010 April 2024 Information Request for the Cybersecurity Baseline Inspection, Notification to Perform Inspection 05000369/2024403; and 05000370/2024403 ML24095A1072024-04-0808 April 2024 – Review of the Spring 2023 Steam Generator Tube Inspection Report (C1R27) ML24052A3062024-04-0808 April 2024 Issuance of Amendment Nos. 331 & 310, Regarding Adoption of Title 10 of Code of Federal Regulations Section 50.69, Risk-Informed Categorization and Treatment of Structures, Systems and Components for Nuclear Power Plants IR 05000269/20244012024-03-28028 March 2024 – Security Baseline Inspection Report 05000269-2024401 and 05000270-2024401 and 05000287-2024401 ML24031A5402024-03-26026 March 2024 Issuance of Amendment Nos. 330 and 309 Regarding Implementation of TSTF 505,Rev. 2, Provide Risk-Informed Extended Completion Times - RITSTF Initiative 4B 2024-09-05
[Table view] |
Text
May 4, 2005 Mr. D. M. Jamil Vice President Catawba Nuclear Station Duke Energy Corporation 4800 Concord Road York, SC 29745
SUBJECT:
PROJECT MANAGER REORGANIZATION FOR THE DUKE ENERGY SITES
Dear Mr. Jamil:
This letter is being sent to inform you of a reorganization in Project Directorate II-1 that will affect the Duke Energy sites. As of May 2, 2005, Mr. Sean Peters has been assigned as the U.S. Nuclear Regulatory Commissions primary Project Manager (PM) for McGuire Nuclear Station, Units 1 and 2. Mr. Peters will continue as the primary PM for Catawba Nuclear Station, Units 1 and 2, and Mr. Leonard Olshan will continue as the primary PM for Oconee Nuclear Station, Units 1, 2, and 3.
We envision that Mr. Peters and Mr. Olshan will act as a team responsible for licensing actions and activities for the three Duke Energy sites, with Mr. Olshan having the overall lead. Either Mr. Olshan or Mr. Peters may have the lead and signature authority for a particular licensing action, depending on priorities and resource availabilities.
Mr. Olshan can be reached at (301) 415-1419 and Mr. Peters can be reached at (301) 415-1842.
Sincerely,
/RA/
John A. Nakoski, Chief, Section 1 Project Directorate II Division of Licensing Project Management Office of Nuclear Reactor Regulation Dockets Nos. 50-413, 50-414, 50-369, 50-370, 50-269, 50-270, and 50-287 cc: See next page
May 4, 2005 Mr. D. M. Jamil Vice President Catawba Nuclear Station Duke Energy Corporation 4800 Concord Road York, SC 29745
SUBJECT:
PROJECT MANAGER REORGANIZATION FOR THE DUKE ENERGY SITES
Dear Mr. Jamil:
This letter is being sent to inform you of a reorganization in Project Directorate II-1 that will affect the Duke Energy sites. As of May 2, 2005, Mr. Sean Peters has been assigned as the U.S. Nuclear Regulatory Commissions primary Project Manager (PM) for McGuire Nuclear Station, Units 1 and 2. Mr. Peters will continue as the primary PM for Catawba Nuclear Station, Units 1 and 2, and Mr. Leonard Olshan will continue as the primary PM for Oconee Nuclear Station, Units 1, 2, and 3.
We envision that Mr. Peters and Mr. Olshan will act as a team responsible for licensing actions and activities for the three Duke Energy sites, with Mr. Olshan having the overall lead. Either Mr. Olshan or Mr. Peters may have the lead and signature authority for a particular licensing action, depending on priorities and resource availabilities.
Mr. Olshan can be reached at (301) 415-1419 and Mr. Peters can be reached at (301) 415-1842.
Sincerely,
/RA/
John A. Nakoski, Chief, Section 1 Project Directorate II Division of Licensing Project Management Office of Nuclear Reactor Regulation Dockets Nos. 50-413, 50-414, 50-369, 50-370, 50-269, 50-270, and 50-287 cc: See next page DISTRIBUTION: See next page ADAMS Number: ML051260128 NRR-106 OFFICE PDII-1/PM PDII-1/LA PDII-1/SC PDll/PD NAME SPeters CHawes JNakoski EHackett DATE 04/29/05 05/02/05 05/02/05 05/04/05 OFFICIAL RECORD COPY
SUBJECT:
PROJECT MANAGER REORGANIZATION FOR THE DUKE ENERGY SITES Date: May 4, 2005 DISTRIBUTION:
PUBLIC PDII-1 R/F RidsNrrDlpmLpdii RidsNrrDlpmLpdii1 CHawes RidsRgn2MailCenter(MErnestes)
RidsNrrPMSPeters RidsNrrPMLOlshan RidsOgcRp RidsAcrsAcnwMailCenter
McGuire Nuclear Station Catawba Nuclear Station Oconee Nuclear Station cc:
Ms. Lisa F. Vaughn Mr. Richard M. Fry, Director Duke Energy Corporation Division of Radiation Protection 422 S. Church St. NC Dept. of Env., Health, & Nat. Resources Mail Code - PB05E 3825 Barrett Dr.
P.O. Box 1244 Raleigh, NC 27609-7721 Charlotte, NC 28201-1244 Ms. Karen E. Long County Manager of Mecklenburg County Asst. Attorney General 720 E. Fourth St. NC Department of Justice Charlotte, NC 28202 P.O. Box 629 Raleigh, NC 27602 Mr. C. Jeffrey Thomas, Manager Regulatory Compliance Mr. R. L. Gill, Jr., Manager McGuire Nuclear Station Nuclear Regulatory Issues & Industry Duke Energy Corporation Affairs 12700 Hagers Ferry Road Duke Energy Corporation Huntersville, NC 28078 526 S. Church St.
Mail Stop EC05P Anne Cottingham, Esq. Charlotte, NC 28202 Winston and Strawn LLP 1700 L St., NW NCEM REP Program Manager Washington, DC 20006 4713 Mail Service Center Raleigh, NC 27699-4713 Senior Resident Inspector U.S. Nuclear Regulatory Commission Mr. T. Richard Puryear 12700 Hagers Ferry Road Owners Group (NCEMC)
Huntersville, NC 28078 Catawba Nuclear Station Duke Energy Corporation Mr. Peter R. Harden, IV, Vice President 4800 Concord Road Customer Relations and Sales York, SC 29745 Westinghouse Electric Company 6000 Fairview Road, 12th Floor Mr. Lee Keller, Manager Charlotte, NC 28210 Regulatory Compliance Catawba Nuclear Station Dr. John M. Barry Duke Energy Corporation Mecklenburg County 4800 Concord Road Department of Environmental Protection York, SC 29745 700 N. Tryon St.
Charlotte, NC 28202 NC Municipal Power Agency Number 1 1427 Meadowwood Boulevard P.O. Box 29513 Raleigh, NC 27626-0513
McGuire Nuclear Station Catawba Nuclear Station Oconee Nuclear Station cc:
County Manager of York County Mr. B. G. Davenport, Manager York County Courthouse Regulatory Compliance York, SC 29745 Oconee Nuclear Site Duke Energy Corporation Piedmont Municipal Power Agency 7800 Rochester Highway - MS ONO3RC 121 Village Dr. Seneca, SC 29672 Greer, SC 29651 Mr. Dhiaa Jamil Saluda River Electric Vice President P.O. Box 929 Catawba Nuclear Station Laurens, SC 29360 Duke Energy Corporation 4800 Concord Road Henry Porter, Assistant Director - DWM York, SC 29745 Bureau of Solid and Hazardous Waste Dept of Health & Env. Control Mr. G. R. Peterson, Vice President 2600 Bull St. McGuire Nuclear Station Columbia, SC 29201-1708 Duke Energy Corporation 12700 Hagers Ferry Road NC Electric Membership Corporation Huntersville, NC 28078 P.O. Box 27306 Raleigh, NC 27611 Mr. Ronald A. Jones, Vice President Oconee Nuclear Station Senior Resident Inspector Duke Energy Corporation U.S. Nuclear Regulatory Commission 7800 Rochester Highway 4830 Concord Road Seneca, SC 29672 York, SC 29745 Henry Barron, Group Vice President Manager, LIS Nuclear Generation & Chief Nuclear Officer NUS Corporation P.O. Box 1006-EC07H 2650 McCormick Dr., 3rd Floor Charlotte, NC 28201-1006 Clearwater, FL 34619-1035 Mr. William R. McCollum Senior Resident Inspector Senior Vice President U.S. Nuclear Regulatory Commission Duke Energy Corporation 7812B Rochester Highway 526 S. Church St.
Seneca, SC 29672 Charlotte, NC 28201-1006 Mr. Michael A. Schoppman Framatome ANP 1911 N. Ft. Myer Dr.
Suite 705 Rosslyn, VA 22209