|
---|
Category:Letter
MONTHYEARIR 05000277/20240032024-11-0404 November 2024 Integrated Inspection Report 05000277/2024003 and 05000278/2024003 RS-24-093, Response to Request for Additional Information - Alternative Request to Utilize Code Case OMN-32, Alternative Requirements for Range and Accuracy of Pressure, Flow, and Differential Pressure Instruments Used in Pump Tests2024-10-10010 October 2024 Response to Request for Additional Information - Alternative Request to Utilize Code Case OMN-32, Alternative Requirements for Range and Accuracy of Pressure, Flow, and Differential Pressure Instruments Used in Pump Tests ML24284A2842024-10-10010 October 2024 (Wcgs), Revision of One Form That Implements the Radiological Emergency Response Plan (RERP) ML24281A1012024-10-0707 October 2024 Senior Reactor and Reactor Operator Initial License Examinations ML24275A2442024-10-0303 October 2024 Reassignment of the U.S. Nuclear Regulatory Commission Branch Chief, Division of Operating Reactor Licensing ML24240A1692024-09-18018 September 2024 Cy 2023 Summary of Decommissioning Trust Fund Status ML24221A2582024-09-0606 September 2024 Response to Request for Re-Engagement Regarding the Subsequent License Renewal Environmental Review for Peach Bottom Atomic Power Station, Units 2 and 3 ML24255A8642024-09-0606 September 2024 Rscc Wire & Cable LLC Dba Marmon Industrial Energy & Infrastructure - Part 21 Retraction of Final Notification 05000277/LER-2024-003, Automatic Reactor Scram Following Main Turbine Trip Due to Degraded Condenser Vacuum2024-09-0505 September 2024 Automatic Reactor Scram Following Main Turbine Trip Due to Degraded Condenser Vacuum IR 05000277/20240052024-08-29029 August 2024 Updated Inspection Plan for Peach Bottom Atomic Power Station, Units 2 and 3 (Report 05000277/2024005 and 05000278/2024005) ML24239A3972024-08-23023 August 2024 Rssc Wire & Cable LLC Dba Marmon - Part 21 Final Notification - 57243-EN 57243 ML24235A0342024-08-23023 August 2024 U.S. Nuclear Regulatory Commission’S Analysis of Constellation Energy Generation’S Decommissioning Funding Status Report IR 05000277/20240102024-08-23023 August 2024 Fire Protection Team Inspection Report 05000277/2024010 and 05000278/2024010 IR 05000277/20240022024-08-14014 August 2024 Integrated Inspection Report 05000277/2024002 and 05000278/2024002 IR 05000482/20240052024-08-14014 August 2024 Updated Inspection Plan for Wolf Creek Generating Station (Report 05000482/2024005) ML24225A1692024-08-12012 August 2024 10 CFR 50.46 Annual Report ML24222A6772024-08-0909 August 2024 Response to Request for Additional Information for Application to Revise Technical Specifications to Adopt TSTF-591-A, Revise Risk Informed Completion Time (RICT) Program Revision 0 and Revise 10 CFR 50.69 License Condition ML24214A3232024-08-0101 August 2024 Response to Request for Additional Information - Request for Alternative Schedule to Complete Decommissioning Beyond 60 Years of Permanent Cessation of Operations ML24208A0962024-07-25025 July 2024 57243-EN 57243 - Rssc Wire & Cable LLC, Dba Marmon - Part 21 Notification ML24206A1252024-07-24024 July 2024 Revision of Three Procedures and Two Forms That Implement the Radiological Emergency Response Plan (RERP) ML24191A0612024-07-0606 July 2024 Independent Spent Fuel Storage Installation (ISFSI) - Annual Radioactive Effluent Release Report ML24178A4142024-06-26026 June 2024 Revision of One Procedure and One Form That Implement the Radiological Emergency Response Plan (RERP) ML24178A3672024-06-26026 June 2024 Correction to 2023 Annual Radioactive Effluent Release Report – Report 47 ML24177A1512024-06-24024 June 2024 Post Accident Monitoring Instrumentation Report ML24166A1172024-06-20020 June 2024 Regulatory Audit Summary Regarding Proposed Alternative Schedule to Complete Decommissioning Beyond 60 Years RS-24-061, Constellation Energy Generation, LLC, Response to NRC Regulatory Issue Summary 2024-01, Preparation and Scheduling of Operator Licensing Examinations2024-06-14014 June 2024 Constellation Energy Generation, LLC, Response to NRC Regulatory Issue Summary 2024-01, Preparation and Scheduling of Operator Licensing Examinations IR 05000277/20243012024-06-13013 June 2024 Initial Operator Licensing Examination Report 05000277/2024301 and 05000278/2024301 RS-24-058, Regarding Subsequent License Renewal Environmental Review2024-06-0505 June 2024 Regarding Subsequent License Renewal Environmental Review ML24151A6482024-06-0303 June 2024 Changes in Reactor Decommissioning Branch Project Management Assignments for Some Decommissioning Facilities ML24150A2722024-05-29029 May 2024 Annual Radiological Environmental Operating Report 81, January 1, 2023 Through December 31, 2023 ML24150A0032024-05-28028 May 2024 Request for Exemptions from 10 CFR 50.82(a)(8)(i)(A) and 10 CFR 50.75(h)(1)(iv) and Proposed Amendment to the Decommissioning Trust Agreement ML24079A0762024-05-23023 May 2024 Issuance of Amendments to Adopt TSTF 264 RS-24-055, 2023 Corporate Regulatory Commitment Change Summary Report2024-05-17017 May 2024 2023 Corporate Regulatory Commitment Change Summary Report IR 05000277/20240012024-05-13013 May 2024 Integrated Inspection Report 05000277/2024001 and 05000278/2024001 ML24134A1792024-05-13013 May 2024 Supplemental Information in Support of Request for Alternative Schedule to Complete Decommissioning Beyond 60 Years of Permanent Cessation of Operations IR 05000277/20245012024-05-0808 May 2024 Emergency Preparedness Biennial Exercise Inspection Report 05000277/2024501 and 05000278/2024501 ML24121A1832024-04-30030 April 2024 Pre-Submittal Meeting Presentation Material Peach Bottom ECCS Compensated Level System Replacement Project RS-24-041, Alternative Request to Utilize Code Case OMN-32, Alternative Requirements for Range and Accuracy of Pressure, Flow, and Differential Pressure Instruments Used in Pump Tests2024-04-30030 April 2024 Alternative Request to Utilize Code Case OMN-32, Alternative Requirements for Range and Accuracy of Pressure, Flow, and Differential Pressure Instruments Used in Pump Tests ML24118A0032024-04-27027 April 2024 2023 Annual Radioactive Effluent Release Report - Report 47 ML24120A2762024-04-23023 April 2024 Independent Spent Fuel Storage Installation (ISFSI) Facility - Annual Radioactive Effluent Release Report 66 January 1, 2023 Through December 31, 2023 CNL-24-033, Central Emergency Control Center Emergency Plan Implementing Procedure Revisions2024-04-17017 April 2024 Central Emergency Control Center Emergency Plan Implementing Procedure Revisions ML24107A2462024-04-15015 April 2024 Submittal of Changes to Technical Specifications Bases ML24103A2042024-04-12012 April 2024 Constellation Energy Generation, LLC, Application to Revise Technical Specifications to Adopt TSTF-591-A, Revise Risk Informed Completion Time (RICT) Program Revision 0 and Revise 10 CFR 50.69 License Condition ML24102A0472024-04-11011 April 2024 Operator Licensing Examination Approval 05000277/LER-2024-002, Uncoordinated DC Circuits Cause Unanalyzed Condition2024-04-0808 April 2024 Uncoordinated DC Circuits Cause Unanalyzed Condition RS-24-002, Constellation Energy Generation, LLC - Annual Property Insurance Status Report2024-04-0101 April 2024 Constellation Energy Generation, LLC - Annual Property Insurance Status Report RS-24-023, Report on Status of Decommissioning Funding.2024-03-22022 March 2024 Report on Status of Decommissioning Funding. IR 05000277/20244022024-03-12012 March 2024 Cybersecurity Inspection Report 05000277/2024402 and 05000278/2024402 (Cover Letter Only) ML24061A2642024-03-0101 March 2024 Revision of Two Procedures That Implement the Radiological Emergency Response Plan (RERP) for Wolf Creek Generating Station (WCGS) Commissioners ML24060A1192024-02-29029 February 2024 Notification of Conduct of a Fire Protection Team Inspection 2024-09-06
[Table view] Category:License-Application for (Amend/Renewal/New) for DKT 30
MONTHYEARRS-21-063, Application to Adopt TSTF-554, Revision 1, Revise Reactor Coolant Leakage Requirements2021-06-30030 June 2021 Application to Adopt TSTF-554, Revision 1, Revise Reactor Coolant Leakage Requirements RS-20-016, County, Nine Mile Point, Peach Bottom Atomic and Quad Cities - Application to Revise Technical Specifications to Adopt TSTF-566, Revise Actions for Inoperable RHR Shutdown Cooling Systems2020-04-13013 April 2020 County, Nine Mile Point, Peach Bottom Atomic and Quad Cities - Application to Revise Technical Specifications to Adopt TSTF-566, Revise Actions for Inoperable RHR Shutdown Cooling Systems RS-19-022, License Amendment Request - Clarifying Changes for Certain Emergency Action Levels Based on Emergency Preparedness Program Frequently Asked Questions (Epfaqs)2019-03-0101 March 2019 License Amendment Request - Clarifying Changes for Certain Emergency Action Levels Based on Emergency Preparedness Program Frequently Asked Questions (Epfaqs) ML0818203482008-06-25025 June 2008 License Amendment Request - Revision to Technical Specification 4.3.1.1.a Concerning k-infinity ML0803802222008-02-0101 February 2008 License Amendment Request - Revise LPRM Calibration Frequency Supplemental Response Global Nuclear Fuel Report - Gnf S-0000-0080-3313, Rev. 0, Pb LPRM Calibration Interval Extension Support ML0725701582007-09-0606 September 2007 License Amendment Request - Application of Alternative Source Term OSM Cover Letter ML0511804422005-04-28028 April 2005 Request for Amendment to Technical Specifications to Add Requirement to Modify Linear Heat Generation Rate Limit ML0407800732004-02-27027 February 2004 Application for Amendment to Change TS Supporting Activation of Trip Outputs of Previously-Installed Oscillation Power Range Monitor (OPRM) Portion of Power Range Neutron Monitoring System 2021-06-30
[Table view] Category:40
MONTHYEARRS-24-023, Report on Status of Decommissioning Funding.2024-03-22022 March 2024 Report on Status of Decommissioning Funding. WM 23-0009, Financial Assurance Requirements for Decommissioning Nuclear Power Reactors 10 CFR 50.75(f)(1)2023-05-10010 May 2023 Financial Assurance Requirements for Decommissioning Nuclear Power Reactors 10 CFR 50.75(f)(1) ML23090A0482023-03-31031 March 2023 Decommissioning Status Report - 2022 LR-N23-0006, Report on Status of Decommissioning Funding for Reactors and Independent Spent Fuel Storage Installations2023-03-24024 March 2023 Report on Status of Decommissioning Funding for Reactors and Independent Spent Fuel Storage Installations RS-23-049, Constellation Energy Generation, LLC, Report on Status of Decommissioning Funding for Reactors and Independent Spent Fuel Storage Installations2023-03-23023 March 2023 Constellation Energy Generation, LLC, Report on Status of Decommissioning Funding for Reactors and Independent Spent Fuel Storage Installations IR 05000277/19570012022-08-19019 August 2022 631999-Termination License 50-27757-01 for G. Scott Crowther Dba Crowther Associates RS-22-042, Report on Status of Decommissioning Funding for Shutdown Reactors2022-03-23023 March 2022 Report on Status of Decommissioning Funding for Shutdown Reactors LR-N24-0040, Attachment 3: Decommissioning Cost Analysis for Peach Bottom Atomic Power Station, Units 2 and 32021-12-31031 December 2021 Attachment 3: Decommissioning Cost Analysis for Peach Bottom Atomic Power Station, Units 2 and 3 ML24150A0052021-12-31031 December 2021 Attachment 2: Decommissioning Cost Analysis Analysis for Hope Creek Generating Station ML24150A0042021-12-31031 December 2021 Attachment 1: Decommissioning Cost Analysis for the Salem Generating Station RS-21-063, Application to Adopt TSTF-554, Revision 1, Revise Reactor Coolant Leakage Requirements2021-06-30030 June 2021 Application to Adopt TSTF-554, Revision 1, Revise Reactor Coolant Leakage Requirements LR-N21-0015, Report on Status of Decommissioning Funding for Reactors and Independent Spent Fuel Storage Installations2021-03-25025 March 2021 Report on Status of Decommissioning Funding for Reactors and Independent Spent Fuel Storage Installations RS-21-032, Amended Decommissioning Trust Agreements2021-02-25025 February 2021 Amended Decommissioning Trust Agreements RS-21-030, Report on Status of Decommissioning Funding for Reactors and Independent Spent Fuel Storage Installations2021-02-24024 February 2021 Report on Status of Decommissioning Funding for Reactors and Independent Spent Fuel Storage Installations NMP1L3371, Summary of Changes, Quality Assurance Topical Report, NO-AA-10 & Decommissioning Quality Assurance Program, NO-DC-102021-02-10010 February 2021 Summary of Changes, Quality Assurance Topical Report, NO-AA-10 & Decommissioning Quality Assurance Program, NO-DC-10 ML20279A5772020-11-23023 November 2020 U.S. Nuclear Regulatory Commission'S Analysis of Public Service Enterprise Group Nuclear, LLC Decommissioning Plans Update for Salem Generating Station, Hope Creek Generating Station and Peach Bottom Independent Sfsis RS-20-016, County, Nine Mile Point, Peach Bottom Atomic and Quad Cities - Application to Revise Technical Specifications to Adopt TSTF-566, Revise Actions for Inoperable RHR Shutdown Cooling Systems2020-04-13013 April 2020 County, Nine Mile Point, Peach Bottom Atomic and Quad Cities - Application to Revise Technical Specifications to Adopt TSTF-566, Revise Actions for Inoperable RHR Shutdown Cooling Systems RS-20-039, Report on Status of Decommissioning Funding for Shutdown Reactors2020-03-31031 March 2020 Report on Status of Decommissioning Funding for Shutdown Reactors RS-19-045, Report on Status of Decommissioning Funding for Reactors and Independent Spent Fuel Storage Installations2019-04-0101 April 2019 Report on Status of Decommissioning Funding for Reactors and Independent Spent Fuel Storage Installations LR-N19-0014, Stations - Report on Status of Decommissioning Funding for Reactors and Independent Spent Fuel Storage Installations2019-03-25025 March 2019 Stations - Report on Status of Decommissioning Funding for Reactors and Independent Spent Fuel Storage Installations RS-19-022, License Amendment Request - Clarifying Changes for Certain Emergency Action Levels Based on Emergency Preparedness Program Frequently Asked Questions (Epfaqs)2019-03-0101 March 2019 License Amendment Request - Clarifying Changes for Certain Emergency Action Levels Based on Emergency Preparedness Program Frequently Asked Questions (Epfaqs) ML18093A3822018-03-30030 March 2018 Decommissioning Status Report - 2017 ML17271A0532017-09-29029 September 2017 2017 Summary of Annual Decommissioning Funding Status Reports for Reactors in Decommissioning ML17093A6972017-03-30030 March 2017 Decommissioning Status Report - 2016 RS-16-069, Unit 1 - Report on Status of Decommissioning Funding for Shutdown Reactors and Reactors within 5 Years of Shutdown2016-03-31031 March 2016 Unit 1 - Report on Status of Decommissioning Funding for Shutdown Reactors and Reactors within 5 Years of Shutdown ML16095A2392016-03-30030 March 2016 Decommissioning Status Report 2015 LR-N15-0047, Submits NRC Decommissioning Funding Status Reports2015-03-31031 March 2015 Submits NRC Decommissioning Funding Status Reports RS-15-094, (EGC) - Submittal of Report on Status of Decommissioning Funding for Reactors and Independent Spent Fuel Storage Installations2015-03-31031 March 2015 (EGC) - Submittal of Report on Status of Decommissioning Funding for Reactors and Independent Spent Fuel Storage Installations RS-14-093, Report on Status of Decommissioning Funding and Spent Fuel Management for Shutdown Reactors2014-03-31031 March 2014 Report on Status of Decommissioning Funding and Spent Fuel Management for Shutdown Reactors RS-13-106, (EGC) Amended 2011 Report on Status of Decommissioning Funding for Reactors and Correction to July 27, 2011 RAI Response2013-04-12012 April 2013 (EGC) Amended 2011 Report on Status of Decommissioning Funding for Reactors and Correction to July 27, 2011 RAI Response RS-13-100, Report on Status of Decommissioning Funding for Reactors2013-04-0101 April 2013 Report on Status of Decommissioning Funding for Reactors ML13092A3312013-03-29029 March 2013 Decommissioning Status Report - 2012 LR-N13-0059, NRC Decommissioning Funding Status Report2013-03-26026 March 2013 NRC Decommissioning Funding Status Report LR-N12-0406, PSEG Nuclear LLC - Decommissioning Funding Plan for the Independent Spent Fuel Storage Installations2012-12-17017 December 2012 PSEG Nuclear LLC - Decommissioning Funding Plan for the Independent Spent Fuel Storage Installations RS-10-055, Report on Status of Decommissioning Funding for Shutdown Reactors2010-03-29029 March 2010 Report on Status of Decommissioning Funding for Shutdown Reactors RS-09-041, Submittal of Exelon Generation Company, LLC, Report on Status of Decommissioning Funding for Reactors Owned by EGC2009-03-31031 March 2009 Submittal of Exelon Generation Company, LLC, Report on Status of Decommissioning Funding for Reactors Owned by EGC LR-N09-0074, Letter from Jeffrie Keenan of PSEG Nuclear L.L.C., NRC Decommissioning Funding Status Report for Salem, Hope Creek & Peach Bottom Generating Stations2009-03-31031 March 2009 Letter from Jeffrie Keenan of PSEG Nuclear L.L.C., NRC Decommissioning Funding Status Report for Salem, Hope Creek & Peach Bottom Generating Stations ML0818203482008-06-25025 June 2008 License Amendment Request - Revision to Technical Specification 4.3.1.1.a Concerning k-infinity ML0803802222008-02-0101 February 2008 License Amendment Request - Revise LPRM Calibration Frequency Supplemental Response Global Nuclear Fuel Report - Gnf S-0000-0080-3313, Rev. 0, Pb LPRM Calibration Interval Extension Support ML0725701582007-09-0606 September 2007 License Amendment Request - Application of Alternative Source Term OSM Cover Letter LR-N07-0067, Units 2 & 3 - Decommissioning Funding Status Report2007-03-30030 March 2007 Units 2 & 3 - Decommissioning Funding Status Report ML0613902022006-05-17017 May 2006 NRC Decommissioning Funding Status Report, Salem, Hope Creek, and Peach Bottom ML0511804422005-04-28028 April 2005 Request for Amendment to Technical Specifications to Add Requirement to Modify Linear Heat Generation Rate Limit ML0407800732004-02-27027 February 2004 Application for Amendment to Change TS Supporting Activation of Trip Outputs of Previously-Installed Oscillation Power Range Monitor (OPRM) Portion of Power Range Neutron Monitoring System LR-N02-0116, NRC Decommissioning Funding Status Report for Hope Creek, Salem & Peach Bottom Stations2002-03-28028 March 2002 NRC Decommissioning Funding Status Report for Hope Creek, Salem & Peach Bottom Stations 2024-03-22
[Table view] Category:70
MONTHYEARRS-24-023, Report on Status of Decommissioning Funding.2024-03-22022 March 2024 Report on Status of Decommissioning Funding. WM 23-0009, Financial Assurance Requirements for Decommissioning Nuclear Power Reactors 10 CFR 50.75(f)(1)2023-05-10010 May 2023 Financial Assurance Requirements for Decommissioning Nuclear Power Reactors 10 CFR 50.75(f)(1) ML23090A0482023-03-31031 March 2023 Decommissioning Status Report - 2022 LR-N23-0006, Report on Status of Decommissioning Funding for Reactors and Independent Spent Fuel Storage Installations2023-03-24024 March 2023 Report on Status of Decommissioning Funding for Reactors and Independent Spent Fuel Storage Installations RS-23-049, Constellation Energy Generation, LLC, Report on Status of Decommissioning Funding for Reactors and Independent Spent Fuel Storage Installations2023-03-23023 March 2023 Constellation Energy Generation, LLC, Report on Status of Decommissioning Funding for Reactors and Independent Spent Fuel Storage Installations IR 05000277/19570012022-08-19019 August 2022 631999-Termination License 50-27757-01 for G. Scott Crowther Dba Crowther Associates RS-22-042, Report on Status of Decommissioning Funding for Shutdown Reactors2022-03-23023 March 2022 Report on Status of Decommissioning Funding for Shutdown Reactors LR-N24-0040, Attachment 3: Decommissioning Cost Analysis for Peach Bottom Atomic Power Station, Units 2 and 32021-12-31031 December 2021 Attachment 3: Decommissioning Cost Analysis for Peach Bottom Atomic Power Station, Units 2 and 3 ML24150A0052021-12-31031 December 2021 Attachment 2: Decommissioning Cost Analysis Analysis for Hope Creek Generating Station ML24150A0042021-12-31031 December 2021 Attachment 1: Decommissioning Cost Analysis for the Salem Generating Station RS-21-063, Application to Adopt TSTF-554, Revision 1, Revise Reactor Coolant Leakage Requirements2021-06-30030 June 2021 Application to Adopt TSTF-554, Revision 1, Revise Reactor Coolant Leakage Requirements LR-N21-0015, Report on Status of Decommissioning Funding for Reactors and Independent Spent Fuel Storage Installations2021-03-25025 March 2021 Report on Status of Decommissioning Funding for Reactors and Independent Spent Fuel Storage Installations RS-21-032, Amended Decommissioning Trust Agreements2021-02-25025 February 2021 Amended Decommissioning Trust Agreements RS-21-030, Report on Status of Decommissioning Funding for Reactors and Independent Spent Fuel Storage Installations2021-02-24024 February 2021 Report on Status of Decommissioning Funding for Reactors and Independent Spent Fuel Storage Installations NMP1L3371, Summary of Changes, Quality Assurance Topical Report, NO-AA-10 & Decommissioning Quality Assurance Program, NO-DC-102021-02-10010 February 2021 Summary of Changes, Quality Assurance Topical Report, NO-AA-10 & Decommissioning Quality Assurance Program, NO-DC-10 ML20279A5772020-11-23023 November 2020 U.S. Nuclear Regulatory Commission'S Analysis of Public Service Enterprise Group Nuclear, LLC Decommissioning Plans Update for Salem Generating Station, Hope Creek Generating Station and Peach Bottom Independent Sfsis RS-20-016, County, Nine Mile Point, Peach Bottom Atomic and Quad Cities - Application to Revise Technical Specifications to Adopt TSTF-566, Revise Actions for Inoperable RHR Shutdown Cooling Systems2020-04-13013 April 2020 County, Nine Mile Point, Peach Bottom Atomic and Quad Cities - Application to Revise Technical Specifications to Adopt TSTF-566, Revise Actions for Inoperable RHR Shutdown Cooling Systems RS-20-039, Report on Status of Decommissioning Funding for Shutdown Reactors2020-03-31031 March 2020 Report on Status of Decommissioning Funding for Shutdown Reactors RS-19-045, Report on Status of Decommissioning Funding for Reactors and Independent Spent Fuel Storage Installations2019-04-0101 April 2019 Report on Status of Decommissioning Funding for Reactors and Independent Spent Fuel Storage Installations LR-N19-0014, Stations - Report on Status of Decommissioning Funding for Reactors and Independent Spent Fuel Storage Installations2019-03-25025 March 2019 Stations - Report on Status of Decommissioning Funding for Reactors and Independent Spent Fuel Storage Installations RS-19-022, License Amendment Request - Clarifying Changes for Certain Emergency Action Levels Based on Emergency Preparedness Program Frequently Asked Questions (Epfaqs)2019-03-0101 March 2019 License Amendment Request - Clarifying Changes for Certain Emergency Action Levels Based on Emergency Preparedness Program Frequently Asked Questions (Epfaqs) ML18093A3822018-03-30030 March 2018 Decommissioning Status Report - 2017 ML17271A0532017-09-29029 September 2017 2017 Summary of Annual Decommissioning Funding Status Reports for Reactors in Decommissioning ML17093A6972017-03-30030 March 2017 Decommissioning Status Report - 2016 RS-16-069, Unit 1 - Report on Status of Decommissioning Funding for Shutdown Reactors and Reactors within 5 Years of Shutdown2016-03-31031 March 2016 Unit 1 - Report on Status of Decommissioning Funding for Shutdown Reactors and Reactors within 5 Years of Shutdown ML16095A2392016-03-30030 March 2016 Decommissioning Status Report 2015 LR-N15-0047, Submits NRC Decommissioning Funding Status Reports2015-03-31031 March 2015 Submits NRC Decommissioning Funding Status Reports RS-15-094, (EGC) - Submittal of Report on Status of Decommissioning Funding for Reactors and Independent Spent Fuel Storage Installations2015-03-31031 March 2015 (EGC) - Submittal of Report on Status of Decommissioning Funding for Reactors and Independent Spent Fuel Storage Installations RS-14-093, Report on Status of Decommissioning Funding and Spent Fuel Management for Shutdown Reactors2014-03-31031 March 2014 Report on Status of Decommissioning Funding and Spent Fuel Management for Shutdown Reactors RS-13-106, (EGC) Amended 2011 Report on Status of Decommissioning Funding for Reactors and Correction to July 27, 2011 RAI Response2013-04-12012 April 2013 (EGC) Amended 2011 Report on Status of Decommissioning Funding for Reactors and Correction to July 27, 2011 RAI Response RS-13-100, Report on Status of Decommissioning Funding for Reactors2013-04-0101 April 2013 Report on Status of Decommissioning Funding for Reactors ML13092A3312013-03-29029 March 2013 Decommissioning Status Report - 2012 LR-N13-0059, NRC Decommissioning Funding Status Report2013-03-26026 March 2013 NRC Decommissioning Funding Status Report LR-N12-0406, PSEG Nuclear LLC - Decommissioning Funding Plan for the Independent Spent Fuel Storage Installations2012-12-17017 December 2012 PSEG Nuclear LLC - Decommissioning Funding Plan for the Independent Spent Fuel Storage Installations RS-10-055, Report on Status of Decommissioning Funding for Shutdown Reactors2010-03-29029 March 2010 Report on Status of Decommissioning Funding for Shutdown Reactors RS-09-041, Submittal of Exelon Generation Company, LLC, Report on Status of Decommissioning Funding for Reactors Owned by EGC2009-03-31031 March 2009 Submittal of Exelon Generation Company, LLC, Report on Status of Decommissioning Funding for Reactors Owned by EGC LR-N09-0074, Letter from Jeffrie Keenan of PSEG Nuclear L.L.C., NRC Decommissioning Funding Status Report for Salem, Hope Creek & Peach Bottom Generating Stations2009-03-31031 March 2009 Letter from Jeffrie Keenan of PSEG Nuclear L.L.C., NRC Decommissioning Funding Status Report for Salem, Hope Creek & Peach Bottom Generating Stations ML0818203482008-06-25025 June 2008 License Amendment Request - Revision to Technical Specification 4.3.1.1.a Concerning k-infinity ML0803802222008-02-0101 February 2008 License Amendment Request - Revise LPRM Calibration Frequency Supplemental Response Global Nuclear Fuel Report - Gnf S-0000-0080-3313, Rev. 0, Pb LPRM Calibration Interval Extension Support ML0725701582007-09-0606 September 2007 License Amendment Request - Application of Alternative Source Term OSM Cover Letter LR-N07-0067, Units 2 & 3 - Decommissioning Funding Status Report2007-03-30030 March 2007 Units 2 & 3 - Decommissioning Funding Status Report ML0613902022006-05-17017 May 2006 NRC Decommissioning Funding Status Report, Salem, Hope Creek, and Peach Bottom ML0511804422005-04-28028 April 2005 Request for Amendment to Technical Specifications to Add Requirement to Modify Linear Heat Generation Rate Limit ML0407800732004-02-27027 February 2004 Application for Amendment to Change TS Supporting Activation of Trip Outputs of Previously-Installed Oscillation Power Range Monitor (OPRM) Portion of Power Range Neutron Monitoring System LR-N02-0116, NRC Decommissioning Funding Status Report for Hope Creek, Salem & Peach Bottom Stations2002-03-28028 March 2002 NRC Decommissioning Funding Status Report for Hope Creek, Salem & Peach Bottom Stations 2024-03-22
[Table view] Category:Technical Specifications
MONTHYEARML23158A1952023-08-30030 August 2023 R. E. Ginna - Issuance of Amendments to Adopt TSTF-273-A, Revision 2, Safety Function Determination Program Clarifications ML22090A0862022-04-29029 April 2022 Amendments to Adopt TSTF-541,Rev.2,Add Exceptions to Surveillance Requirements for Valves,Dampers Locked in Actuated Position RS-22-049, Constellation Energy Generation, LLC, Supplemental Information to Correct Typographical Errors in Constellations Application to Revise Technical Specifications to Adopt TSTF-541 Revision 2, Add Exceptions to Surveillance Requirements for V2022-04-0404 April 2022 Constellation Energy Generation, LLC, Supplemental Information to Correct Typographical Errors in Constellations Application to Revise Technical Specifications to Adopt TSTF-541 Revision 2, Add Exceptions to Surveillance Requirements for Va ML21347A0382022-01-13013 January 2022 Issuance of Amendments to Revise Reactor Coolant Leakage Requirements JAFP-21-0089, Application to Revise Technical Specifications to Adopt TSTF-541 Revision 2, Add Exceptions to Surveillance Requirements for Valves and Dampers Locked in the Actuated Position2021-09-27027 September 2021 Application to Revise Technical Specifications to Adopt TSTF-541 Revision 2, Add Exceptions to Surveillance Requirements for Valves and Dampers Locked in the Actuated Position ML21033A5302021-04-0101 April 2021 Issuance of Amendments to Adopt Technical Specifications Task Force TSTF-566, Revise Actions for Inoperable RHR Shutdown Cooling Subsystems ML21013A0052021-02-0404 February 2021 Issuance of Amendments to Adopt Technical Specifications Task Traveler TSTF-568, Revise Applicability of BWR/4 TS 3.6.2.5 and TS 3.6.3.2 RS-20-016, County, Nine Mile Point, Peach Bottom Atomic and Quad Cities - Application to Revise Technical Specifications to Adopt TSTF-566, Revise Actions for Inoperable RHR Shutdown Cooling Systems2020-04-13013 April 2020 County, Nine Mile Point, Peach Bottom Atomic and Quad Cities - Application to Revise Technical Specifications to Adopt TSTF-566, Revise Actions for Inoperable RHR Shutdown Cooling Systems ML19266A6222019-10-29029 October 2019 Issuance of Amendment Nos. 328 and 331 Revising Technical Specifications 3.81, AC Sources - Operating, for a One-Time Extension of Completion Time ML19182A0062019-08-28028 August 2019 Issuance of Amendment Nos. 327 and 330 Reduce High Pressure Service Water System Design Pressure and Temporarily Extend Completion Times ML19078A0182019-05-24024 May 2019 Issuance of Amendment Nos. 235, 198, 14, 325, and 328 to Revise the Emergency Response Organization Staffing Requirements ML18263A2322018-10-25025 October 2018 Issuance of Amendment Nos. 321 and 324 to Adopt 10 CFR 50.69 (CAC Nos. MG0181 and MG0181; EPID L-2017-LLA-0281) ML18249A2402018-09-28028 September 2018 Issuance of Amendment Nos. 320 and 323 Regarding the Adoption of TSTF-500, DC Electrical Rewrite - Update to TSTF-360 ML18257A0172018-09-14014 September 2018 Response to Request for Additional Information Application to Revise Technical Specifications to Adopt Technical Specification Task Force (TSTF)-500, Revision 2, DC Electrical Rewrite Update to ... ML18173A0422018-06-23023 June 2018 Issuance of Amendment Nos. 318 & 321 to Revise Technical Specifications 3.8.1 and 3.8.3, One-Time Change Suspending EDG Surveillance Test Completion Requirements (Emergency Situation) RS-18-020, Application to Revise Technical Specifications to Modify the APRM Channel Adjustment Surveillance Requirement2018-06-15015 June 2018 Application to Revise Technical Specifications to Modify the APRM Channel Adjustment Surveillance Requirement ML16217A0082016-08-11011 August 2016 Correction to Amendment Nos. 308 and 312 Regarding Surveillance Requirements for High Pressure Coolant Injection System and Reactor Core Isolation Cooling System ML16162A1012016-06-0909 June 2016 Response to Request for Additional Information Regarding Proposed License Amendment Concerning Emergency Diesel Generator Fuel Oil Transfer Surveillance Requirements ML16084A9682016-05-0909 May 2016 Issuance of Amendments Inservice Leak and Hydrostatic Testing Operation ML16034A3722016-03-21021 March 2016 Issuance of Amendments Maximum Extended Load Line Limit Analysis Plus ML15343A1772016-02-0808 February 2016 Issuance of Amendment Safety Limit Minimum Critical Power Ratio Change ML15350A1792016-02-0101 February 2016 Issuance of Amendments Secondary Containment Access Openings ML15275A2652015-10-0202 October 2015 License Amendment Request, Proposed Changes to the Technical Specifications for High Pressure Coolant Injection and Reactor Core Isolation Cooling Surveillance Test Pressure and Clarification of Surveillance Requirements ML15196A5592015-09-0808 September 2015 Issuance of Amendments Extension of Type a and Type C Leak Rate Test Frequencies ML15189A1852015-08-11011 August 2015 Issuance of Amendment No. 305 Change to Replacement Steam Dryer License Condition ML15141A0582015-07-28028 July 2015 Issuance of Amendments Regarding Emergency Action Level Schemes (TAC Nos. MF4232-MF4251) ML15167A4562015-07-28028 July 2015 Issuance of Amendments Eliminate Main Steam Line Radiation Monitor Trip and Isolation Function ML15162A1392015-07-17017 July 2015 Issuance of Amendments Revise Technical Specification Definition for Recently Irradiated Fuel ML15154A6142015-06-30030 June 2015 Issuance of Amendments Adoption of Technical Specification Task Force (TSTF) Traveler TSTF-523, Generic Letter 2008-01, Managing Gas Accumulation ML15093A0532015-03-27027 March 2015 (PBAPS) Unit 1 Decommissioning Status Report - 2014 ML14363A2272015-03-11011 March 2015 Issuance of Amendments Revise Facility Operating License and the Technical Specifications to Incorporate Administrative Changes ML15055A5062015-02-23023 February 2015 License Amendment Request - Proposed Changes to the Technical Specifications to Address Administrative Control of Secondary Containment Access Openings ML15041A6302015-02-19019 February 2015 Correction to Amendments Regarding Adoption of Technical Specifications Task Force Traveler, TSTF-535, Revise Shutdown Margin Definition to Address Advanced Fuel Designs ML14247A5242014-09-0303 September 2014 License Amendment Request Revise Technical Specifications to Eliminate Main Steam Line Radiation Monitor Trip and Isolation Function ML14163A5892014-07-28028 July 2014 Issuance of Amendments Delete Non-Conservative Note from Limiting Condition for Operation 3.5.1 ML14192B1432014-07-11011 July 2014 License Amendment Request to Revise Facility Operating License and the Technical Specifications to Incorporate Administrative Changes ML14136A4852014-06-0505 June 2014 Issuance of Amendments Revise Normal Heat Sink Operability Requirements ML14160A6992014-06-0505 June 2014 Extended Power Uprate License Amendment Request - Supplement 27 Supplemental Information ML14079A1022014-05-0505 May 2014 Issuance of Amendments Safety Relief Valve and Safety Valve Lift Setpoint Tolerance ML14099A5372014-04-0808 April 2014 Response to Request for Additional Information - Revision of Normal Heat Sink Technical Specification to Remove the 24-Hour Average Temperature Limit with No Change to the Peak Maximum Temperature ML14092A3152014-03-28028 March 2014 Decommissioning Status Report for 2013 ML13109A4632013-06-18018 June 2013 Issuance of Amendments Revise Technical Specifications to Add Residual Heat Removal System Drywell Spray Function Requirements ML13018A2252013-01-17017 January 2013 Response to Request for Additional Information - Revision of Normal Heat Sink Technical Specification to Remove the 24-Hour Average Temperature Limit with No Change to the Peak Maximum Temperature ML12286A0122012-09-28028 September 2012 License Amendment Request - Extended Power Uprate ML12243A2862012-08-29029 August 2012 License Amendment Request to Add LCO 3.0.8 on the Lnoperability of Snubbers Using the Consolidated Line Item Improvement Process ML12200A3882012-07-18018 July 2012 Revision of Normal Heat Sink Technical Specification to Remove the 24-Hour Average Temperature Limit with No Change to the Peak Maximum Temperature ML1130814412011-11-0303 November 2011 License Amendment Request - Use of Neutron Absorbing Inserts in Spent Fuel Pool Storage Racks ML1116001802011-06-0808 June 2011 License Amendment Request - Safety Limit Minimum Critical Power Ratio Change ML1109700672011-04-0606 April 2011 License Amendment Request to Revise Operability Requirements and Actions for RCS Leakage Instrumentation ML0824703052008-08-28028 August 2008 Technical Specifications, TSTF Change Traveler TSTF-479 & TSTF-497 2023-08-30
[Table view] |
Text
Exelon Nuclear www exeloncoip.com 2 0 0 Exelon Way Kennett Square, PA 13348 10 CFR 50.90 April 28, 2005 U. S. Nuclear Regulatory Commission ATTN: Document Control Desk Washington, DC 20555-0001 Peach Bottom Atomic Power Station, Units 2 and 3 Renewed Facility Operating License Nos. DPR-44 and DPR-56 NRC Docket Nos. 50-277 and 50-278
Subject:
Request for Amendment to Technical Specifications to Add Requirement to Modify Linear Heat Generation Rate Limit Pursuant to 10 CFR 50.90, "Application for amendment of license or construction permit,"
Exelon Generation Company, LLC (EGC) requests an amendment to Appendix A, Technical Specifications (TS), of the Renewed Facility Operating Licenses listed above. The proposed changes modify TS 3.3.4.2 ("End of Cycle Recirculation Pump Trip (EOC-RPT)
Instrumentation"), TS 3.4.1 ("Recirculation Loops Operating"), and TS 3.7.6 ("Main Turbine Bypass System") to add a requirement for the linear heat generation rate (LHGR) limits specified in the Core Operating Limits Report (COLR).
TS 3.3.4.2, TS 3.4.1, and TS 3.7.6 for Peach Bottom Atomic Power Station (PBAPS), Units 2 and 3, currently require that the limits for average planar linear heat generation rate (APLHGR) and minimum critical power ratio (MCPR) be modified for an inoperable End of Cycle Recirculation Pump Trip (EOC-RPT) instrument function, single recirculation loop operation, or an inoperable Main Turbine Bypass System. The modified limits for APLHGR and MCPR are specified in the COLR. The proposed changes add a requirement to modify the LHGR limit as specified in the COLR. There is currently no TS requirement to adjust the LHGR limit for an inoperable End of Cycle Recirculation Pump Trip (EOC-RPT) instrument function, single recirculation loop operation, or an inoperable Main Turbine Bypass System. Administrative controls are in place at PBAPS, Units 2 and 3 to ensure that the LHGR limits are appropriately adjusted.
EGC requests approval of these changes by April 22, 2006. Once approved, the amendments shall be implemented within 60 days. The proposed changes have been reviewed by the Plant Operations Review Committee and approved by the Nuclear Safety Review Board.
Request for Amendment to TS to Add Requirement to Modify Linear Heat Generation Rate Limit April 28, 2005 Page 2 In accordance with 10 CFR 50.91, "Notice for public comment; State consultation,"
paragraph (b), EGC is notifying the State of Pennsylvania of this application for changes to the TS by transmitting a copy of this letter and its attachments to the designated State Official.
There are no commitments contained in this letter.
Should you have questions concerning this submittal, please contact Mr. Tom Loomis at (610) 765-5510.
I declare under penalty of perjury that the foregoing is true and correct.
Respectfully,
,41 Executed on Director, Licensing and Regulatory Affairs Exelon Generation Company, LLC Attachments: 1: Description of Proposed Changes, Technical Analysis, and Regulatory Analysis 2: Markup of Technical Specification Pages cc: S. J. Collins, Administrator, Region I, USNRC F. L. Bower, USNRC Senior Resident Inspector, PBAPS G. Wunder, Senior Project Manager, USNRC
ATTACHMENT 1 PEACH BOTTOM ATOMIC POWER STATION, UNITS 2 AND 3 FACILITY OPERATING LICENSE NOS. DPR-44 AND DPR-56 REQUEST FOR AMENDMENT TO TECHNICAL SPECIFICATIONS TO ADD REQUIREMENT TO MODIFY LINEAR HEAT GENERATION RATE LIMITS Description of Proposed Changes, Technical Analysis, and Regulatory Analysis
ATTACHMENT 1 Description of Proposed Changes, Technical Analysis, and Regulatory Analysis 1.o DESCRlPTION
2.0 PROPOSED CHANGE
3.0 BACKGROUND
4.0 TECHNICAL ANALYSIS
5.0 REGULATORY ANALYSIS
5.1 No Significant Hazards Consideration 5.2 Applicable Regulatory Requirementslcriteria 6.0 ENVIRON~ENTALCONSIDERATION
7.0 REFERENCES
Page 1 of 8
ATTACHMENT 1 Description of Proposed Changes, Technical Analysis, and Regulatory Analysis 1.O DESCRIPTION In accordance with 10 CFR 50.90, "Application for amendment of license or construction permit,"
Exelon Generation Company, LLC (EGC) requests an amendment to Appendix A, Technical Specifications (TS), to Renewed Facility Operating License Nos. DPR-44 and DPR-56 for Peach Bottom Atomic Power Station (PBAPS), Units 2 and 3. The proposed changes modify TS 3.3.4.2 ("End of Cycle Recirculation Pump Trip (EOC-RPT) Instrumentation"), TS 3.4.1
("Recirculation Loops Operating"), and TS 3.7.6 ("Main Turbine Bypass System") to add a requirement for the linear heat generation rate (LHGR) limits specified in the Core Operating Limits Report (COLR) to be met for an inoperable End of Cycle Recirculation Pump Trip (EOC-RPT) instrument function, single recirculation loop operation, or an inoperable Main Turbine Bypass System, respectively.
2.0 PROPOSED CHANGE
The proposed change adds a requirement for LHGR limits specified in the COLR. Specifically, the proposed change revises:
- 1. TS 3.3.4.2.b to add the following statement:
"3. LCO 3.2.3, "LINEAR HEAT GENERATION RATE (LHGR)," limits for an inoperable EOC-RPT as specified in the COLR."
- 2. TS 3.4.1 to add the following statement:
"c. LCO 3.2.3, "LINEAR HEAT GENERATION RATE (LHGR)," single loop operation limits specified in the COLR; and" The proposed change also re-designates existing Limiting Condition for Operation (LCO) 3.4.1 .c as LCO 3.4.1 .d to reflect the addition of the new requirement to meet the LHGR limit specified in the COLR during single recirculation loop operation.
- 3. TS 3.7.6 to add the following statement:
"c. LCO 3.2.3, "LINEAR HEAT GENERATION RATE (LHGR)," limits for an inoperable Main Turbine Bypass System, as specified in the COLR."
A markup of the affected TS pages is provided in Attachment 2. The revised TS pages with the proposed change incorporated will be provided prior to issuance.
3.0 BACKGROUND
PBAPS, Units 2 and 3, has implemented an updated version of the PANACEA computer program. This updated version of the program is referred to as PANACll. PANACl1 provides improved flexibility when designing and monitoring the reactor core. A similar request was Page 2 of 8
ATTACHMENT 1 Description of Proposed Changes, Technical Analysis, and Regulatory Analysis approved for LaSalle County Station, Units 1 and 2, Dresden Nuclear Power Station, Units 2 and 3, and Quad Cities Nuclear Power Station, Units 1 and 2 (Reference 7).
The need for the proposed TS change is a result of a change in the treatment of both the average planar linear heat generation rate (APLHGR) and the LHGR. The change in the three-dimensional core simulator used for core licensing calculations and core monitoring for PBAPS, Units 2 and 3 from PANAClO to PANACll (versions of the PANACEA computer program) accentuates the difference in the treatment of the APLHGR and LHGR limits. PANACEA is a static, three-dimensional coupled nuclear-thermal-hydrauliccomputer program representing a boiling water reactor core. The program was approved by the NRC as part of Amendment 26 to General Electrics Standard Application for Reactor Fuel (GESTAR) in Reference 1, and is used by General Electric during the core design process for detailed three-dimensional design and operational calculations of neutron flux, power distributions, and thermal performance as a function of control rod position, refueling pattern, coolant flow, reactor pressure, and other operational and design variables.
LHGR limits are derived based on fuel thermal and mechanical design requirements and are developed to assure that fuel thermal design limits (e.g., centerline melt) and fuel mechanical limits (e.g., 1% plastic strain) are not exceeded during normal operations and anticipated operational occurrences (AOOs). APLHGR limits are derived based on the results of Emergency Core Cooling System (ECCS) analyses and are developed to assure that the Peak Cladding Temperature (PCT) does not exceed 2200°F during limiting accidents.
The ECCS analyses also establish an APLHGR multiplier in order to limit the peak cladding temperature (PCT) increase for single recirculation loop operation. When the multiplier is developed, both the LHGR and MAPLHGR values are reduced in the ECCS analyses until the PCT passes the acceptance criterion.
PANAClO utilizes APLHGR multipliers for the conditions of an inoperable EOC-RPT instrument function, single recirculation loop operation, or an inoperable Main Turbine Bypass System. An LHGR multiplier is not required when monitoring or designing with PANAClO because composite ECCShhermal-mechanicalAPLHGR limits are used. The composite APLHGR limits are a conservative combination of the APLHGR limits based on ECCS requirements and equivalent APLHGR limits based on LHGR fuel thermal and mechanical design requirements.
These limits are developed as a function of fuel exposure. The composite APLHGR limit is derived by taking the more limiting of these two APLHGR limits, as a function of fuel exposure.
When using PANAC10, the APLHGR multiplier is sufficient to ensure that the PCT is bounded and that fuel thermal and mechanical design limits are not exceeded during AOOs.
When designing or monitoring with PANACll, LHGR is treated independently from APLHGR, providing more flexibility and improved accuracy. PANACll also utilizes an APLHGR multiplier.
However, the APLHGR limit used with PANACll is based on the ECCS PCT limit only. The fuel thermal-mechanical limits are addressed separately using an exposure dependent LHGR limit. Since ECCS and thermal-mechanical limits are analyzed and monitored separately, an LHGR multiplier is also required to ensure that fuel thermal and mechanical design limits are not exceeded during normal operations and AOOs.
Page 3 of 8
ATTACHMENT 1 Description of Proposed Changes, Technical Analysis, and Regulatory Analysis TS 3.3.4.2, 3.4.1,and 3.7.6currently list the core thermal limits that must be adjusted for an inoperable EOC-RPT instrument function, single recirculation loop operation, or an inoperable Main Turbine Bypass System. A revision to these TS is needed to ensure that the LHGR limit is also adjusted, since a LHGR multiplier is required to be consistent with the fuel thermal and mechanical design limits.
Although there is currently no TS requirement to adjust the LHGR limit during inoperable End of Cycle Recirculation Pump Trip (EOC-RPT) instrument function, single recirculation loop operation or an inoperable Main Turbine Bypass System, in accordance with Reference 1, administrative controls are in place at PBAPS, Units 2 and 3,to ensure that the LHGR limits are appropriately adjusted. In addition, PANAC11 will be used for future core reload designs.
4.0 TECHNICAL ANALYSIS
The LHGR is a measure of the heat generation rate of a fuel rod in a fuel assembly at any axial location. Limits on the LHGR are specified to ensure that fuel design limits are not exceeded anywhere in the core during normal operation, including anticipated operational occurrences (AOOs), and to ensure that the PCT during a postulated design basis LOCA does not exceed the limits specified in 10 CFR 50.46. Exceeding the LHGR limit could potentially result in fuel damage and subsequent release of radioactive materials. Fuel design limits are specified to ensure that fuel system damage, fuel rod failure, or inability to cool the fuel does not occur during normal operations and anticipated operating conditions.
The LHGR is a basic assumption in the fuel design analysis. Reference 3 defines a value of 1%
plastic strain of the fuel cladding as the limit below which fuel damage caused by overstraining of the fuel cladding is not expected to occur. The fuel has been designed to operate at rated core power with a specified LHGR limit to ensure that 1% plastic strain of the fuel cladding is not exceeded, and that fuel centerline melt does not occur during normal operation, including AOOs.
LHGR multipliers may be required for operation at off-rated or other operating conditions (i-e.,
inoperable End of Cycle Recirculation Pump Trip (EOC-RPT) instrument function, single recirculation loop operation (SLO), or an inoperable Main Turbine Bypass System) to ensure that fuel design limits are not exceeded anywhere in the core during normal operation, including anticipated operational occurrences. These multipliers are calculated in accordance with the methodologies described in GESTAR (Reference 6). The GESTAR methodology requires that the LHGR design limits are met for all operating conditions.
In addition, LOCA-based LHGR limits, including the SLO LHGR multiplier, are calculated in accordance with SAFEWGESTR methodology (i.e., Reference 4),which was approved by the NRC in Reference 3. The SAFER/GESTR methodology requires the following limits to be met when performing LOCA analyses:
1, 10 CFR 50 Appendix K licensing basis PCT less than 2200°F
- 2. Upper bound PCT (UBPCT) less than licensing basis PCT Page 4 of 8
ATTACHMENT 1 Description of Proposed Changes, Technical Analysis, and Regulatory Analysis The criteria for conservatism of the calculation with 10 CFR 50 Appendix K assumptions relative to UBPCT is assured by determining a LHGR and MAPLHGR multiplier that maintains the SLO PCT below the two-loop PCT. The fuel LHGR is significant in determining the PCT during LOCA analyses. At lower core flow conditions, such as during SLO, operation with the rated LHGR value could drive the PCT above the two-loop PCT. In order to prevent the SLO point from being the limiting operating point, the LHGR and MAPLHGR are reduced. The application of these LHGR and MAPLHGR limits at SLO conditions prevent the SLO point from being more limiting than the limiting power/flow point during normal two-loop plant operation.
TS 5.6.5, "CORE OPERATING LIMITS REPORT (COLR)," requires core operating limits to be established prior to each reload cycle, or prior to any remaining portion of a reload cycle, and documented in the COLR to ensure that all applicable limits of the safety analysis are met.
Therefore, calculation of the LHGR limit for an inoperable EOC-RPT instrument function, single recirculation loop operation, or an inoperable Main Turbine Bypass System is required on a cycle-specific basis.
5.0 REGULATORY ANALYSIS
5.1 No Sianificant Hazards Consideration EGC has evaluated whether or not a significant hazards consideration is involved with the proposed amendment by focusing on the three standards set forth in 10 CFR 50.92, "Issuance of amendment," as discussed below:
- 1. Does the proposed amendment involve a significant increase in the probability or consequences of an accident previously evaluated?
Response: No The probability of an evaluated accident is derived from the probabilities of the individual precursors to that accident. The consequences of an evaluated accident are determined by the operability of plant systems designed to mitigate those consequences. The LHGR is a measure of the heat generation rate of a fuel rod in a fuel assembly at any axial location. Limits on the LHGR are specified to ensure that fuel design limits are not exceeded anywhere in the core during normal operation, including anticipated operational occurrences, and to ensure that the peak cladding temperature (PCT) during a postulated design basis Loss-of-Coolant Accident (LOCA) does not exceed the limits specified in 10 CFR 50.46.
LHGR limits have been established consistent with the NRC-approved GESTAR methodology to ensure that fuel performance during normal, transient, and accident conditions is acceptable. The proposed changes establish a requirement for LHGR limits to be modified, as specified in the COLR, such that the fuel is protected for the conditions of an inoperable EOC-RPT instrument function, single recirculation loop operation, or an inoperable Main Turbine Bypass System and during any plant transients or anticipated operational occurrences that may occur while in these conditions.
Page 5 of 8
ATTACHMENT 1 Description of Proposed Changes, Technical Analysis, and Regulatory Analysis Modifying the LHGR limits for the above three (3) conditions does not increase the probability of an evaluated accident. The proposed change does not require any physical plant modifications, physically affect any plant components, or entail changes in plant operation. Therefore, no individual precursors of an accident are affected.
Limits on the LHGR are specified to ensure that fuel design limits are not exceeded anywhere in the core during normal operation, including anticipated operational occurrences, and to ensure that the PCT during a postulated design basis LOCA does not exceed the limits specified in 10 CFR 50.46. This will ensure that the fuel design safety criteria (i.e., less than 1% plastic strain of the fuel cladding and no fuel centerline melting) are met and that the core remains in a coolable geometry following a postulated design basis LOCA or any anticipated operational occurrence. Since the operability of plant systems designed to mitigate any consequences of accidents has not changed and all fuel design limits continue to be met, the consequences of an accident previously evaluated are not expected to increase.
Therefore, the proposed changes do not involve a significant increase in the probability or consequences of an accident previously evaluated.
- 2. Does the proposed amendment create the possibility of a new or different kind of accident from any accident previously evaluated?
Response: No Creation of the possibility of a new or different kind of accident would require the creation of one or more new precursors of that accident. New accident precursors may be created by modifications of the plant configuration, including changes in allowable modes of operation. The proposed changes do not involve any modifications of the plant configuration or allowable modes of operation. Requiring the LHGR limits to be modified for the conditions of inoperable EOC-RPT instrument function, single recirculation loop operation, or an inoperable Main Turbine Bypass System ensures that fuel design limits are not exceeded anywhere in the core during normal operation, including anticipated operational occurrences and that the assumptions of the LOCA analyses are met.
Therefore, the proposed changes do not create the possibility of a new or different kind of accident from any previously evaluated.
- 3. Does the proposed amendment involve a significant reduction in a margin of safety?
Response: No The margin of safety is established through equipment design, operating parameters, and the setpoints at which automatic actions are initiated. The proposed change will not adversely affect operation of plant equipment. The change will not result in a change to the setpoints at which protective actions are initiated. LHGR limits for the conditions of an inoperable EOC-RPT instrument function, single recirculation loop operation, or an Page 6 of 8
ATTACHMENT 1 Description of Proposed Changes, Technical Analysis, and Regulatory Analysis inoperable Main Turbine Bypass System are established to ensure that fuel design limits are not exceeded anywhere in the core during normal operation, including anticipated operational occurrences and that the PCT during a postulated design basis LOCA does not exceed the limits specified in 10 CFR 50.46. This will ensure that the core remains in a coolable geometry following a postulated design basis LOCA. The proposed change will ensure the appropriate level of fuel protection.
Therefore, the proposed changes do not involve a significant reduction in a margin of safety.
Based upon the above, EGC concludes that the proposed amendment presents no significant hazards consideration under the standards set forth in 10 CFR 50.92(c), accordingly, a finding of "no significant hazards consideration" is justified.
5.2 Applicable Reaulatow ReauirementsKriteria 10 CFR 50.36, "Technical specifications," provides the regulatory requirements for the content required in a licensee's TS. Criterion 2 of 10 CFR 50.36(c)(2)(ii) requires a limiting condition for operation to be established for a process variable, design feature, or operating restriction that is an initial condition of a design basis accident or transient analysis that either assumes the failure of or presents a challenge to the integrity of a fission product barrier.
10 CFR 50.46, "Acceptance criteria for emergency core cooling systems for light-water nuclear power reactors," establishes the acceptance criteria for the design basis LOCA. Specifically, paragraph (b)(1) requires the calculated maximum fuel element cladding temperature (i-e., PCT) to not exceed 2200°F.
The specific LHGR limits to be applied during single recirculation loop operation are evaluated each fuel cycle and documented in the COLR. The limits are established to ensure that the PCT during a design basis LOCA does not exceed 2200"F, thus the requirements of 10 CFR 50.46(b)(I) are satisfied.
The proposed change to TS ensures that the LHGR limit is adjusted for the conditions of an inoperable EOC-RPT instrument function, single recirculation loop operation, or an inoperable Main Turbine Bypass System. In addition, the LHGR limit satisfies Criterion 2 of 10 CFR 50.36(c)(2)(ii) for the reasons described above.
In conclusion, based on the considerations discussed above, (1) there is reasonable assurance that the health and safety of the public will not be endangered by operation in the proposed manner, (2) such activities will be conducted in compliance with the Commission's regulations, and (3) the issuance of the amendment will not be inimical to the common defense and security or to the health and safety of the public.
Page 7 of 8
ATTACHMENT 1 Description of Proposed Changes, Technical Analysis, and Regulatory Analysis
6.0 ENVIRONMENTAL CONSIDERATION
A review has determined that the proposed amendment would change a requirement with respect to installation or use of a facility component located within the restricted area, as defined in 10 CFR 20, "Standards for Protection Against Radiation," or would change an inspection or surveillance requirement. However, the proposed amendment does not involve: (i) a significant hazards consideration, (ii) a significant change in the types or significant increase in the amounts of any effluent that may be released offsite, or (iii) a significant increase in individual or cumulative occupational radiation exposure. Accordingly, the proposed amendment meets the eligibility criterion for categorical exclusion set forth in 10 CFR 51.22, "Criterion for categorical exclusion; identification of licensing and regulatory actions eligible for categorical exclusion or otherwise not requiring environmental review," paragraph (c)(9). Therefore, pursuant to 10 CFR 51.22, paragraph (b), no environmental impact statement or environmental assessment need be prepared in connection with the proposed amendment.
7.0 REFERENCES
- 1. Letter from S. A. Richards (U. S. NRC) to G. A. Watford (GE Nuclear Energy),
"Amendment 26 to GE Licensing Topical Report NEDE-24011-P-A, 'GESTAR II' Implementing Improved GE Steady-State Methods (TAC No. MA6481)," dated November 10,1999
- 2. NRC Administrative Letter 98-10, "Dispositioning of Technical Specifications that Are Insufficient to Assure Plant Safety," dated December 29, 1998
- 3. NUREG-0800, Section 4.2, Subsection Il.A.2(g), Revision 2, July 1981
- 4. NEDE-23785-1-PA, "The GESTR-LOCA and SAFER Models for the Evaluation of the Loss-of-Coolant Accident, Volume I l l , SAFEWGESTR Application Methodology,"
dated October 1984
- 5. Letter from C. 0. Thomas (U. S. NRC) to J. F. Quirk (General Electric), "Acceptance for Referencing of Licensing Topical Report NEDE-23785, Revision 1, Volume 111 (P),
'The GESTR-LOCA and SAFER Models for the Evaluation of the Loss-of-Coolant Accident,"' dated June 1, 1984
- 6. NEDE-24011-P-A-14, "GESTAR I I - General Electric Standard Application for Reactor Fuel," June 2000
- 7. Letter from D. V. Pickett (U. S. NRC) to C. M. Crane (Exelon Generation Company, LLC), "LaSalle County Station, Units 1 and 2 (TAC NOS. MC1293 and MC1294),
Dresden Nuclear Power Station, Units 2 and 3 (TAC NOS. MC1291 and MC1292),
Quad Cities Nuclear Power Station, Units 1 and 2 (TAC NOS. MCI295 and MC1296)
- Issuance of Amendments", dated October 4, 2004.
Page 8 of 8
ATTACHMENT 2 PEACH BOTTOM ATOMIC POWER STATION, UNITS 2 AND 3 FACILITY OPERATING LICENSE NOS. DPR-44 AND DPR-56 REQUEST FOR AMENDMENT TO TECHNICAL SPECIFICATIONS TO ADD REQUIREMENT TO MODIFY LINEAR HEAT GENERATION RATE LIMITS Markup Of Technical Specifications Paaes 3.3-31a 3.4-1 3.7-12
EOC-RPT Instrumentation 3.3.4.2 3.3 INSTRUMENTATION 3.3.4.2 End o f Cycle R e c i r c u l a t i o n Pump T r i p ( E O C - R P T ) I n s t r u m e n t a t i o n LCO 3.3.4.2 a. Two c h a n n e l s per t r i p system f o r each EOC-RPT i n s t r u m e n t a t i o n Function l i s t e d below s h a l l be O P E R A B L E :
- 1. T u r b i n e S t o p Valve (TSVI-Closure; a n d
- 2. Turbine Control Valve ( T C V ) F a s t ' C l o s u r e , T r i p O i 1 P r e s s u r e - Low.
OR
- b. The f o l l o w i n g l i m i t s a r e made a p p l i c a b l e :
I. LCO 3.2.1, "AVERAGE PLANAR L I N E A R HEAT G E N E R A T I O N RATE ( A P L H G R ) , " l i m i t s f o r i n o p e r a b l e EOC-RPT a s specified in the COLR;
- 2. LCO 3 . 2 . 2 " M I ~ I M U M C R I T I C A L POWER R A T I O C M C P R ) , "
p e r a b l e E O C - R P T as s p e c i f i e d i n t h e APPLICABILITY:
P- '
ACTIONS
_ " _ _ _ _ _ _ C _ _ _ _ _ r _
S e p a r a t e Condition e n t r y i s allowed f o r each channel, CONDITION R E Q U I R E D ACTION ' COMPLETION TIME A. One o r more channels Restore channel t o 7 2 hours2.314815e-5 days <br />5.555556e-4 hours <br />3.306878e-6 weeks <br />7.61e-7 months <br /> inoperable. OPERABLE s t a t u s ,
A.2 --------NOTE----.----
Not a p p l i c a b l e i f i n o p e r a b l e channel i s the result o f a n inoperable breaker.
Place channel !'n 72 hours8.333333e-4 days <br />0.02 hours <br />1.190476e-4 weeks <br />2.7396e-5 months <br /> trip.
(continued)
?BAPS UNIT 2 3.3-31a Amendment No. 247
EOC-RPT Instrumentation 3.3.4.2 3.3 I~STRUMENTATIO~
3.3.4.2 E n d o f Cycle R e c i r c u l a t i o n Pump T r i p ( E O C - R P T ) I n s t r u m e n t a t i o n LCO 3.3.4.2 a. Two channels per t r i p system f o r each E O C - R P T instrumentation Function l i s t e d below s h a l l be O P E R A B L E
- 1. Turbine Stop Valve (TSVi-Closure; a n d
- 2. Turbine Control Valve ( T C V ) Fast Closure, T r i p O i l Pressure-Low.
OR
- b. The following l i m i t s a r e made a p p l i c a b l e :
- 1. LCO 3 . 2 . 1 , " A V E R A G E PLANAR L I N E A R H E A T G E N E R A T I O N RATE (APLHGR), " inoperable EOC-RPT a s s p e c i f i e d in t h e C O L R ;
- 2. LCO 3 . 2 . 2 , "~INrMUMC R I T I C A L POWER RATIO ( M C P R ) , "
e r a b l e E O C - R P T a s spec-ified i n t h e APPLICABILITY:
i ACTIONS
~ -~
CONDITION REQUIRED ACTION COMPLETION TIME A. One o r more channels A. 1 Restore channel t o 7 2 hours2.314815e-5 days <br />5.555556e-4 hours <br />3.306878e-6 weeks <br />7.61e-7 months <br /> inoperable. OPERABLE status.
-OR A.2 --------NOTE---------
Not applicable i f i n o p e r a b l e channel i s the r e s u l t o f a n inoperable breaker.
Place c h a n n e l i n 72 hours8.333333e-4 days <br />0.02 hours <br />1.190476e-4 weeks <br />2.7396e-5 months <br /> trip.
PBAPS UNIT 3 3.3-31a Amendment No. 250
Recirculation Loops Operating 3.4.1 3.4 REACTOR COOLANT SYSTEM (RCS) 3.4.1 Recirculation Loops Operating LCO 3 . 4 . 1 Two recirculation loops with matched flows shall be in operation with core flow as a function of THERMAL POWER in the "Unrestricted" Region of Figure 3 . 4 . 1 - 1 .
-OR One recirculation loop shall be in operation with core flow as a function of THERMAL POWER in the "Unrestricted" Region of Figure 3 . 4 . 1 - 1 and with the following limits applied when the associated LCO is applicable:
- a. LCO 3 . 2 . 1 , "AVERAGE PLANAR LINEAR HEAT GENERATION RATE (APLXGR)," single loop operation limits specific in the COLR;
- b. LCO 3 . 2 . 2 , "MINIMUM CRITICAL POWER RATIO (MCPR)," single loop operation limits specified in the COLR; LCO 3 . 3 . 1 . 1 , "Reactor Protection System (RPS)
Instrumentation," Function 2 . 6 (Average Power Range I Monitors Simulated Thermal Power-High) , A7 lowable Value o f Table 3 . 3 . 1 . 1 - 1 i s reset for single loop operation.
............................ NOTE----------------------------
Required limit modifications for single recirculation loop operation may be delayed for up t o 12 hours1.388889e-4 days <br />0.00333 hours <br />1.984127e-5 weeks <br />4.566e-6 months <br /> after transition from two recirculation loop operation to single recirculation loop operation.
9 PBAPS UNIT 2 3.4-1 Amendment No. 232
Recirculation Loops Operating 3.4.1 3.4 REACTOR COOLANT SYSTEM (RCS) 3.4.1 Rec ircul at ion Loops Operat i ng LCO 3 . 4 . 1 Two recirculation loops with matched flows shall be in operation with core flow as a function of THERMAL POWER in the "Unrestricted" Region of Figure 3.4.1-1.
OR One recirculation loop shall be in operation with core flow as a function of THERMAL POWER in the "Unrestricted" Region of Figure 3.4.1-1 and with the following limits applied when the associated LCO is applicable:
- a. LCD 3.2.1; "AVERAGE PLANAR LINEAR HEAT GENERATION RATE (APLHGR)," single loop operation limits specific in the COLR;
- b. LCO 3.2.2, "MINI~UMCRITICAL POWER RATIO (MC loop operation limits specified in the COLR; LCO 3.3.1.1, "Reactor Protection System (RPS)
Instrumentation, Function 2.b (Average Power Range I'
--I I Monitors Simulated Thermal Power-High), Allowable Value of Table 3.3.1.1-1 is reset for single loop operation,
............................ NOTE----------------------------
Required limit modifications for single recirculation loop operation may be delayed for up t o 12 hours1.388889e-4 days <br />0.00333 hours <br />1.984127e-5 weeks <br />4.566e-6 months <br /> after transition from two recirculation loop operation to single recirculation loop operation.
APPLICABILITY: MODES 1 and 2.
PBAPS UNIT 3 3.4-1 Amendment No. 234
Main Turbine Bypass System 3.7.6 3.7 PLANT SYSTEMS 3.7.6 Main Turbine Bypass System LCO 3.7.6 The Main Turbine Bypass System shall be OPERABLE.
A. Requirements o f the A. 1 Satisfy the 2 hours2.314815e-5 days <br />5.555556e-4 hours <br />3.306878e-6 weeks <br />7.61e-7 months <br /> LCO not met. requirements o f the LCO .
B. Required Action and B. I Reduce THERMAL POWER 4 hbUrS associated Completion t o < 25% RTP.
Time not met.
PBAPS UNIT 2 3.7-12 amend men^ No, 210
Main Turbine Bypass System 3.7.6 3.7 PLANT SYSTEMS 3.7.6 Main Turbine Bypass System LCO 3.7.6 The Main Turbine Bypass System shall be OPERABLE.
OR The fol 1 owing 1 i m i ts are made appl i cab1 e :
- a. LCO 3.2.1, "AVERAGE PLANAR LINEAR HEAT G E N E ~ T I O NRATE (APLHGR)," limits for an inoperab n Turbine Bypass System, as specified in the COLR; APPLICABILITY:
_- I CONDITION I REQUIRED ACTION CO~PLETIONTIME A. Requirements o f the A. 1 Satisfy the 2 hours2.314815e-5 days <br />5.555556e-4 hours <br />3.306878e-6 weeks <br />7.61e-7 months <br /> LCO not met. requirements o f the LCO .
B. Required Action and B. 1 Reduce THERMAL POWER 4 hours4.62963e-5 days <br />0.00111 hours <br />6.613757e-6 weeks <br />1.522e-6 months <br /> associated Completion to .( 25% RTP.
Time not met.
PBAPS UNIT 3 3.7-12 A~endment No. 214