March 2005 Monthly Operating Reports for Oconee McGuire and Catawba
ML051100316
Person / Time
Site: Oconee, Mcguire, Catawba, McGuire  Duke Energy icon.png
Issue date: 04/13/2005
From: Barron H
Duke Power Co
To:
Document Control Desk, Office of Nuclear Reactor Regulation
References
Download: ML051100316 (26)


Text

HENRY B BARRON MkDuke Group VP, Nuclear Generation and

-WvPowere Chief Nuclear Officer Duke Power 526 South Church St.

Charlotte, NC 28202 Mailing Address:

EC07H / PO Box 1006 Charlotte, NC 28201-1006 704 382 2200 April 13, 2005 704 382 6056 fax hbarron @duke-energy. corn U.S. Nuclear Regulatory Commission Attention: Document Control Desk Washington, DC 20555

Subject:

Duke Energy Corporation Oconee Nuclear Station, Docket Nos. 50-269, -270, -287 McGuire Nuclear Station, Docket Nos. 50-369, -370 Catawba Nuclear Station, Docket Nos. 50-413, -414 Monthly Performance and Operation Status - March 2005 Please find attached information concerning the performance and operation status of the Oconee, McGuire and Catawba Nuclear Stations for the month of March 2005.

Please direct any questions or comments to Roger A. Williams at (704) 382-5346.

//_

Henry B. Barron Attachment

e- --qC www. dukepower. corn

U.S. Nuclear Regulatory Commission Monthly Performance and Operation Status April 13,2005 Page 2 xc: W. D. Travers, Regional Administrator U.S. Nuclear Regulatory Commission Sam Nunn Atlanta Federal Center 61 Forsythe Street SW, Suite 23T85 Atlanta, GA 30303-8931 L. N. 0lshan, Senior Project Manager (ONS)

U.S. Nuclear Regulatory Commission Mail Stop 0-8 H12 Washington, DC 20555 J. J. Shea, Project Manager (MNS)

U.S. Nuclear Regulatory Commission Mail Stop 0-8 H12 Washington, DC 20555 S. E. Peters, Project Manager (CNS)

U.S. Nuclear Regulatory Commission Mail Stop 0-8 H12 Washington, DC 20555 Ms. Margaret Aucoin Nuclear Assurance Corporation 3930 E. Jones Bridge Road #300 Norcross, GA 30092-2107 INPO Records Center 700 Galleria Parkway Atlanta, GA 30339-5957 Dottie Sherman, ANI Ubrary American Nuclear Insurers 95 Glastonbury Blvd.

Glastonbury, CT 06033 M. Shannon, Senior Resident Inspector, Oconee Nuclear Station J. Brady, Senior Resident Inspector, McGuire Nuclear Station E. Guthrie, Senior Resident Inspector, Catawba Nuclear Station

Operating Data Report Docket No. 50-269 Date April 12,2005 Completed By Roger Williams Telephone 704-382-5346 Operating Status

1. Unit Name: Oconee 1
2. Reporting Period: March 1, 2005 -March 31, 2005
3. Licensed Thermal Power (MWt): 2568 Notes: Year-to-date
4. Nameplate Rating (Gross MWe): 934 and cumulative capacity factors are
5. Design Electrical Rating (Net Mwe): 886 calculated using a
6. Maximum Dependable Capacity (Gross MWe): 886 weighted average for
7. Maximum Dependable Capacity(Net MWe): 846 maximum dependable
8. If Changes Occured in Capacity Ratings (Items Number 3-7) Since Last Report, Give Reasons: capacity.
9. Power Level To Which Restricted, If Any (Net MWe):
10. Reason for Restrictions, If any:

This Month YTD Cumulative

11. Hours in Reporting Period 744.0 2160.0 277969.0
12. Number of Hours Reactor was Critical 744.0 2160.0 220742.8
13. Reactor Reserve Shutdown Hours 0.0 0.0 0.0
14. Hours Generator On-Line 744.0 2160.0 217057.8
15. Unit Reserve Shutdown Hours 0.0 0.0 0.0
16. Gross Thermal Energy Generated (MWH) 1909359 5543182 538282807
17. Gross Electrical Energy Generated (MWH) 669246 1942389 186284917
18. Net Electrical Energy Generated (MWH) 641077 1861331 177240589
19. Unit Service Factor 100.0 100.0 78.1
20. Unit Availability Factor 100.0 100.0 78.1
21. Unit Capacity Factor (Using MDC Net) 101.9 101.9 74.7
22. Unit Capacity Factor (Using DER Net) 97.3 97.3 72.0
23. Unit Forced Outage Rate 0.0 0.0 8.9
24. Shutdown Scheduled Over Next 6 Months (Type, Date and Duration of Each)
25. If ShutDown At End Of Report Period, Estimated Date of Startup
26. Units in Test Status (Prior to Commercial Operation)

Forcast Achieved Initial Criticality Initial Electricity Commercial Operation NRC Calculated from Generator Nameplate Data:

1 037 937 KVA x 0.90 Pf=934 MW 3A - 4/1212005

Page: 1 of 1 UNIT SHUTDOWNS DOCKET NO. 50-269 UNIT NAME: Oconee 1 DATE: April 12.2005 COMPLETED BY: Roger Williams TELEPHONE: 704-382-5346 REPORT MONTH: March, 2005 No. Date: Type Duration (1) Reason (2) Method of Licensed Cause and Corrective Action to Prevent Recurrence F - Forced Hours Shutdown RIX Event Report S - Scheduled No.

No Outages for the Month Summary:

(1) Reason (2) Method A - Equipment failure (Explain) E - Operator Training/License Examination 1 - Manual 2 - Manual Trip/Scram B - Maintenance or Test F - Administrative 3 - Automatic Trip/Scram 4 - Continuation C - Refueling G - Operator Error (Explain) 5 - Other (Explain)

D - Regulatory restriction H - Other (Explain) 3C- 4112/2005

MONTHLY REFUELING INFORMATION REQUEST

1. Facility name: Oconee Unit 1
2. Scheduled next refueling shutdown: April 2005
3. Scheduled restart following refueling: May 2005 THE PROJECT MANAGER HAS BEEN ADVISED BY SEPARATE COMMUNICATION OF ANY T.S. CHANGE OR LICENSE AMENDMENT. THEREFORE, QUESTIONS 4 THROUGH 6 WILL NO LONGER BE MAINTAINED IN THIS REPORT.
4. Will refueling or resumption of operation thereafter require a technical specification change or other license amendment?

If yes, what will these be?

If no, has reload design and core configuration been reviewed by Safety Review Committee regarding unreviewed safety questions?

5. Scheduled date(s) for submitting proposed licensing action and supporting information.
6. Important licensing considerations (new or different design or supplier, unreviewed design or performance analysis methods, significant changes in design or new operating procedures).
7. Number of Fuel assemblies (a) in the core: 177 (b) in the spent fuel pool: 902*

(c) in the ISFSI: 2016**

8. Present licensed fuel pool capacity: 1312 Size of requested or planned increase: **
9. Projected date of last refueling which can be accommodated by present capacity: January 2005***

DUKE POWER COMPANY DATE: April 12.2005 Name of

Contact:

R. A. Williams Phone: (704) - 382-5346

  • Represents the combined total for Units 1 and 2
    • On March 29, 1990, received a site specific license for ISFSI which will store 2112 assemblies (88 modules). Forty (40) site specific modules were constructed and loaded.
      • In 1999 Oconee transitioned to its general license. Forty-four (44) general license modules were installed and 30 modules have now been loaded.

Additional modules will be installed on an as-needed basis.

        • Represents the combined total for Units 1, 2, and 3

Operating Data Report Docket No. 50-270 Date April 12.2005 Completed By Roger Williams Telephone 704-382-5346 Operating Status

1. Unit Name: Oconee 2
2. Reporting Period: March 1, 2005 -March 31, 2005
3. Licensed Thermal Power (MWt): 2568 Notes: Year-to-date 934 and cumulative
4. Nameplate Rating (Gross MWe):

capacity factors are

5. Design Electrical Rating (Net Mwe): 886 calculated using a
6. Maximum Dependable Capacity (Gross MWe): 886 weighted average for
7. Maximum Dependable Capacity(Net MWe): 846 maximum dependable
8. If Changes Occured in Capacity Ratings (Items Number 3-7) Since Last Report, Give Reasons: capacity.
9. Power Level To Which Restricted, If Any (Net MWe):
10. Reason for Restrictions, If any:

This Month YTD Cumulative

11. Hours in Reporting Period 744.0 2160.0 267889.0
12. Number of Hours Reactor was Critical 744.0 2160.0 218751.4
13. Reactor Reserve Shutdown Hours 0.0 0.0 0.0
14. Hours Generator On-Line 744.0 2160.0 216079.5
15. Unit Reserve Shutdown Hours 0.0 0.0 0.0
16. Gross Thermal Energy Generated (MWH) 1910592 5546264 535487598
17. Gross Electrical Energy Generated (MWH) 678687 1966831 184454932
18. Net Electrical Energy Generated (MWH) 652304 1889940 175854977
19. Unit Service Factor 100.0 100.0 80.7
20. Unit Availability Factor 100.0 100.0 80.7
21. Unit Capacity Factor (Using MDC Net) 103.6 103.4 77.0
22. Unit Capacity Factor (Using DER Net) 99.0 98.8 74.1
23. Unit Forced Outage Rate 0.0 0.0 8.1
24. Shutdown Scheduled Over Next 6 Months (Type, Date and Duration of Each)
25. If ShutDown At End Of Report Period, Estimated Date of Startup
26. Units in Test Status (Prior to Commercial Operation)

Forcast Achieved Initial Criticality Initial Electricity Commercial Operation NRC Calculated from Generator Nameplate Data:

1 037 937 KVA x 0.90 Pf=934 MW 3A - 4/12/2005

Page: 1 of 1 UNIT SHUTDOWNS DOCKET NO. 50-270 UNIT NAME: Oconee 2 DATE: April 12.2005 COMPLETED BY: Roger Williams TELEPHONE: 704-382-5346 REPORT MONTH: March. 2005 No. Date: Type Duration (1) Reason (2) Method of Licensed Cause and Corrective Action to Prevent Recurrence F - Forced Hours Shutdown R/X Event Report S - Scheduled No.

No Outages for the Month Summary:

(1) Reason (2) Method A - Equipment failure (Explain) E - Operator Training/License Examination 1 - Manual 2 - Manual Trip/Scram B - Maintenance or Test F - Administrative 3 - Automatic Trip/Scram 4 - Continuation C - Refueling G - Operator Error (Explain) 5 - Other (Explain)

D - Regulatory restriction H - Other (Explain) 3c- 4/12/2005

MONTHLY REFUELING INFORMATION REQUEST

1. Facility name: Oconee Unit 2
2. Scheduled next refueling shutdown: October. 2005
3. Scheduled restart following refueling: November. 2005 THE PROJECT MANAGER HAS BEEN ADVISED BY SEPARATE COMMUNICATION OF ANY T.S. CHANGE OR LICENSE AMENDMENT. THEREFORE, QUESTIONS 4 THROUGH 6 WILL NO LONGER BE MAINTAINED IN THIS REPORT.
4. Will refueling or resumption of operation thereafter require a technical specification change or other license amendment?

If yes, what will these be?

If no, has reload design and core configuration been reviewed by Safety Review Committee regarding unreviewed safety questions?

5. Scheduled date(s) for submitting proposed licensing action and supporting information.
6. Important licensing considerations (new or different design or supplier, unreviewed design or performance analysis methods, significant changes in design or new operating procedures).
7. Number of Fuel assemblies (a) in the core: 177 (b) in the spent fuel pool: 902*

(c) in the ISFSI: See unit 1 ****

8. Present licensed fuel pool capacity: 1312 Size of requested or planned increase: **
9. Projected date of last refueling which can be accommodated by present capacity: January 2005***

DUKE POWER COMPANY DATE: April 12.2005 Name of

Contact:

R. A. Williams Phone: (704) - 382-5346

  • Represents the combined total for Units 1 and 2
    • See footnote on Unit 1
      • In 1999 Oconee transitioned to its general license. Forty-four (44) general license modules were installed and 30 modules have now been loaded.

Additional modules will be installed on an as-needed basis.

        • See footnote on Unit 1

Operating Data Report Docket No. 50-287 Date April 12.2005 Completed By Roger Williams Telephone 704-382-5346 Operating Status

1. Unit Name: Oconee 3
2. Reporting Period: March 1, 2005 - March 31, 2005
3. Licensed Thermal Power (MWt): 2568 Notes: Year-to-date 934 and cumulative
4. Nameplate Rating (Gross MWe):

capacity factors are

5. Design Electrical Rating (Net Mwe): 886 calculated using a
6. Maximum Dependable Capacity (Gross MWe): 886 weighted average for
7. Maximum Dependable Capacity(Net MWe): 846 maximum dependable
8. If Changes Occured in Capacity Ratings (Items Number 3-7) Since Last Report, Give Reasons: capacity.
9. Power Level To Which Restricted, If Any (Net MWe):
10. Reason for Restrictions, If any:

This Month YTD Cumulative

11. Hours in Reporting Period 744.0 2160.0 265536.0
12. Number of Hours Reactor was Critical 744.0 2023.6 211396.6
13. Reactor Reserve Shutdown Hours 0.0 0.0 0.0
14. Hours Generator On-Line 744.0 1955.2 208528.7
15. Unit Reserve Shutdown Hours 0.0 0.0 0.0
16. Gross Thermal Energy Generated (MWH) 1910592 4900360 522217315
17. Gross Electrical Energy Generated (MWH) 679769 1747166 180903797
18. Net Electrical Energy Generated (MWH) 653531 1672060 172624000
19. Unit Service Factor 100.0 90.5 78.5
20. Unit Availability Factor 100.0 90.5 78.5
21. Unit Capacity Factor (Using MDC Net) 103.8 91.5 76.2
22. Unit Capacity Factor (Using DER Net) 99.1 87A 73.4
23. Unit Forced Outage Rate 0.0 7.5 8.7
24. Shutdown Scheduled Over Next 6 Months (Type, Date and Duration of Each)
25. If ShutDown At End Of Report Period, Estimated Date of Startup
26. Units in Test Status (Prior to Commercial Operation)

Forcast Achieved Initial Criticality Initial Electricity Commercial Operation NRC Calculated from Generator Nameplate Data:

1 037 937 KVA x 0.90 Pf=934 MW 3A - 4/12/2005

Page: 1 of 1 UNIT SHUTDOWNS DOCKET NO. 50-287 UNIT NAME: Oconee 3 DATE: April 12.2005 COMPLETED BY: Roger Williams TELEPHONE: 704-382-5346 REPORT MONTH: March. 2005 No. Date: Type Duration (1) Reason (2) Method of Licensed Cause and Corrective Action to Prevent Recurrence F - Forced Hours Shutdown R/X Event Report S - Scheduled No.

No Outages for the Month Summary:

(1) Reason (2) Method A - Equipment failure (Explain) E - Operator Training/License Examination 1 - Manual 2 - Manual Trip/Scram B - Maintenance or Test F - Administrative 3 - Automatic Trip/Scram 4 - Continuation C - Refueling G - Operator Error (Explain) 5 - Other (Explain)

D - Regulatory restriction H - Other (Explain) 3C- 4/12/2005

MONTHLY REFUELING INFORMATION REQUEST

1. Facility name: Oconee Unit 3
2. Scheduled next refueling shutdown: April 2006
3. Scheduled restart following refueling: May 2006 THE PROJECT MANAGER HAS BEEN ADVISED BY SEPARATE COMMUNICATION OF ANY T.S. CHANGE OR LICENSE AMENDMENT. THEREFORE, QUESTIONS 4 THROUGH 6 WILL NO LONGER BE MAINTAINED IN THIS REPORT.
4. Will refueling or resumption of operation thereafter require a technical specification change or other license amendment?

If yes, what will these be?

If no, has reload design and core configuration been reviewed by Safety Review Committee regarding unreviewed safety questions?

5. Scheduled date(s) for submitting proposed licensing action and supporting information.
6. Important licensing considerations (new or different design or supplier, unreviewed design or performance analysis methods, significant changes in design or new operating procedures).
7. Number of Fuel assemblies (a) in the core: 177 (b) in the spent fuel pool: 460 (c) in the ISFSI: See Unit 1 ****
8. Present licensed fuel pool capacity: 825 Size of requested or planned increase: **
9. Projected date of last refueling which can be accommodated by present capacity: January 2005***

DUKE POWER COMPANY DATE: April 12.2005 Name of

Contact:

R. A. Williams Phone: (704) - 382-5346

    • See footnote of Unit 1
      • In 1999 Oconee transitioned to its general license. Forty-four (44) general license modules were installed and 30 modules have now been loaded.

Additional modules will be installed on an as-needed basis.

    • See footnote on Unit 1

OCONEE NUCLEAR STATION MONTHLY OPERATING STATUS REPORT FEBRUARY 2005

1. Personnel Exposure -

The total station liquid release for FEBRUARY has been compared with the Technical Specifications maximum annual dose commitment and was less than 10 percent of this limit.

The total station gaseous release for FEBRUARY has been compared with the Technical Specifications maximum annual dose commitment and was less than 10 percent of this limit.

Operating Data Report Docket No. 50-369 Date April 12.2005 Completed By Roger Williams Telephone 704-382-5346 Operating Status

1. Unit Name: McGuire 1
2. Reporting Period: March 1, 2005 - March 31, 2005
3. Licensed Thermal Power (MWt): 3411 Notes: *Nameplate
4. Nameplate Rating (Gross MWe): 1305
  • Rating (GrossMWe)
5. Design Electrical Rating (Net Mwe): 1180 calculated as 1450.000
6. Maximum Dependable Capacity (Gross MWe): 1144 MVA * .90 power 1100 factor per Page Hii,
7. Maximum Dependable Capacity(Net MWe):

NUREG-0020.

8. If Changes Occured in Capacity Ratings (Items Number 3-7) Since Last Report, Give Reasons:
9. Power Level To Which Restricted, If Any (Net MWe):
10. Reason for Restrictions, If any:

This Month YTD Cumulative

11. Hours in Reporting Period 744.0 2160.0 204528.0
12. Number of Hours Reactor was Critical 744.0 2160.0 161292.1
13. Reactor Reserve Shutdown Hours 0.0 0.0 0.0
14. Hours Generator On-Line 744.0 2160.0 159967.0
15. Unit Reserve Shutdown Hours 0.0 0.0 0.0
16. Gross Thermal Energy Generated (MWH) 2536866 7361870 518784992
17. Gross Electrical Energy Generated (MWH) 890771 2586987 178938628
18. Net Electrical Energy Generated (MWH) 858992 2497917 171564738
19. Unit Service Factor 100.0 100.0 78.2
20. Unit Availability Factor 100.0 100.0 78.2
21. Unit Capacity Factor (Using MDC Net) 105.0 105.1 74.2
22. Unit Capacity Factor (Using DER Net) 97.8 98.0 71.1
23. Unit Forced Outage Rate 0.0 0.0 8.7
24. Shutdown Scheduled Over Next 6 Months (Type, Date and Duration of Each)
25. If ShutDown At End Of Report Period, Estimated Date of Startup
26. Units in Test Status (Prior to Commercial Operation)

Forcast Achieved Initial Criticality Initial Electricity Commercial Operation 3A - 4/12/2005

Page: 1 of 1 UNIT SHUTDOWNS DOCKET NO. 50-369 UNIT NAME: McGuire 1 DATE: April 12.2005 COMPLETED BY: Roger Williams TELEPHONE: 704-382-5346 REPORT MONTH: March. 2005 No. Date: Type Duration (1)Reason (2) Method of Licensed Cause and Corrective Action to Prevent Recurrence F - Forced Hours Shutdown R/X Event Report S - Scheduled No.

No Outages for the Month Summary:

(1) Reason (2) Method A - Equipment failure (Explain) E - Operator Training/License Examination 1 - Manual 2 - Manual Trip/Scram B - Maintenance or Test F - Administrative 3 - Automatic Trip/Scram 4 - Continuation C - Refueling G - Operator Error (Explain) 5 - Other (Explain)

D - Regulatory restriction H - Other (Explain) 3C- 4/12/2005

MONTHLY REFUELING INFORMATION REQUEST

1. Facility name: McGuire Unit 1
2. Scheduled next refueling shutdown: September 2005
3. Scheduled restart following refueling: October 2005 THE PROJECT MANAGER HAS BEEN ADVISED BY SEPARATE COMMUNICATION OF ANY T.S. CHANGE OR LICENSE AMENDMENT. THEREFORE, QUESTIONS 4 THROUGH 6 WILL NO LONGER BE MAINTAINED IN THIS REPORT.
4. Will refueling or resumption of operation thereafter require a technical specification change or other license amendment?

If yes, what will these be?

If no, has reload design and core configuration been reviewed by Safety Review Committee regarding unreviewed safety questions?

5. Scheduled date(s) for submitting proposed licensing action and supporting information.
6. Important licensing considerations (new or different design or supplier, unreviewed design or performance analysis methods, significant changes in design or new operating procedures).
7. Number of Fuel assemblies (a) in the core: 193 (b) in the spent fuel pool: 1091
8. Present licensed fuel pool capacity: 1463 Size of requested or planned increase: --
9. Projected date of last refueling which can be accommodated by present license capacity:

November 2005 DUKE POWER COMPANY DATE: April 12.2005 Name of

Contact:

R. A. Williams Phone: (704) - 382-5346

Operating Data Report Docket No. 50-370 Date April 12.2005 Completed By Roger Williams Telephone 704-382-5346 Operating Status

1. Unit Name: McGuire 2
2. Reporting Period: March 1, 2005 -March 31, 2005
3. Licensed Thermal Power (MWt): 3411 Notes: *Nameplate
4. Nameplate Rating (Gross MWe): 1305
  • Rating (GrossMWe)
5. Design Electrical Rating (Net Mwe): 1180 calculated as 1450.000
6. Maximum Dependable Capacity (Gross MWe): 1144 MVA * .90 power
7. Maximum Dependable Capacity(Net MWe): 1100 factor per Page lii, NUREG-0020.
8. If Changes Occured in Capacity Ratings (Items Number 3-7) Since Last Report, Give Reasons:
9. Power Level To Which Restricted, If Any (Net MWe):
10. Reason for Restrictions, If any:

This Month YTD Cumulative

11. Hours in Reporting Period 744.0 2160.0 184824.0
12. Number of Hours Reactor was Critical 15.8 1431.8 154055.7
13. Reactor Reserve Shutdown Hours 0.0 0.0 0.0
14. Hours Generator On-Line 15.8 1431.8 152773.4
15. Unit Reserve Shutdown Hours 0.0 0.0 0.0
16. Gross Thermal Energy Generated (MWH) 51498 4878762 506010072
17. Gross Electrical Energy Generated (MWH) 17938 1710498 176000287
18. Net Electrical Energy Generated (MWH) 11154 1646155 169050782
19. Unit Service Factor 2.1 66.3 82.7
20. Unit Availability Factor 2.1 66.3 82.7
21. Unit Capacity Factor (Using MDC Net) 1.4 69.3 81.3
22. Unit Capacity Factor (Using DER Net) 1.3 64.6 77.5
23. Unit Forced Outage Rate 84.4 5.6 5.0
24. Shutdown Scheduled Over Next 6 Months (Type, Date and Duration of Each)
25. If ShutDown At End Of Report Period, Estimated Date of Startup
26. Units in Test Status (Prior to Commercial Operation)

Forcast Achieved Initial Criticality Initial Electricity Commercial Operation 3A - 4/12/2005

Page: 1 of 1 UNIT SHUTDOWNS DOCKET NO. 50-370 UNIT NAME: McGuire 2 DATE: April 12.2005 COMPLETED BY: Roger Williams TELEPHONE: 704-382-5346 REPORT MONTH: March. 2005 No. Date: Type Duration (1) Reason (2) Method of Licensed Cause and Corrective Action to Prevent Recurrence F - Forced Hours Shutdown R/X Event Report S - Scheduled No.

2C2 MOISTURE SEPARATOR REHEATER DRAIN LINE TO "A" 1 03/01/05 F 85.25 A 2 . FEEDWATER HEATER RUPTURE 2 03/05/05 S 643.00 C 4 END-OF-CYCLE 16 REFUELING OUTAGE Summary:

McGuire unit 2 began the month of March operating at approximately 100% power. On 03/01/05 at 1350 the unit began rapid down power due to 2C2 moisture separator reheater drain line to "A" feedwater heater rupture. The unit was manually tripped off-line at approximately 15% power on 03/01/05 at 1545 due to 2C2 moisture separator reheater drain line to "A" feedwater heater rupture. The unit began the end-of-cycle 16 refueling outage on 03/05/05 at 0500 and the unit remained in the end-of-cycle 16 refueling outage the remainder of the month.

(1) Reason (2) Method A - Equipment failure (Explain) E - Operator Training/License Examination 1 - Manual 2 - Manual Trip/Scram B - Maintenance or Test F - Administrative 3 - Automatic Trip/Scram 4 - Continuation C - Refueling G - Operator Error (Explain) 5 - Other (Explain)

D - Regulatory restriction H - Other (Explain) 3C- 4/12/2005

MONTHLY REFUELING INFORMATION REQUEST

1. Facility name: McGuire Unit 2
2. Scheduled next refueling shutdown: Currently Refueling
3. Scheduled restart following refueling: April 2005 THE PROJECT MANAGER HAS BEEN ADVISED BY SEPARATE COMMUNICATION OF ANY T.S. CHANGE OR LICENSE AMENDMENT. THEREFORE, QUESTIONS 4 THROUGH 6 WILL NO LONGER BE MAINTAINED IN THIS REPORT.
4. Will refueling or resumption of operation thereafter require a technical specification change or other license amendment?

If yes, what will these be?

If no, has reload design and core configuration been reviewed by Safety Review Committee regarding unreviewed safety questions?

5. Scheduled date(s) for submitting proposed licensing action and supporting information.
6. Important licensing considerations (new or different design or supplier, unreviewed design or performance analysis methods, significant changes in design or new operating procedures).
7. Number of Fuel assemblies (a) in the core: 193 (b) in the spent fuel pool: 1166 (c) in the ISFSI: 368
8. Present licensed fuel pool capacity: 1463 Size of requested or planned increase: =
9. Projected date of last refueling which can be accommodated by present license capacity:

June 2003 DUKE POWER COMPANY DATE: April 12. 2005 Name of

Contact:

R. A. Williams Phone: (704) - 382-5346

McGUIRE NUCLEAR STATION MONTHLY OPERATING STATUS REPORT FEBRUARY 2005

1. Personnel Exposure -

The total station liquid release for FEBRUARY has been compared with the Technical Specifications maximum annual dose commitment and was less than 10 percent of this limit.

The total station gaseous release for FEBRUARY has been compared with the Technical Specifications maximum annual dose commitment and was less than 10 percent of this limit.

Operating Data Report Docket No. 50-413 Date April 12.2005 Completed By Roger Williams Telephone 704-382-5346 Operating Status

1. Unit Name: Catawba 1
2. Reporting Period: March 1, 2005 -March 31, 2005
3. Licensed Thermal Power (MWt): 3411 Notes: *Nameplate
4. Nameplate Rating (Gross MWe): 1305 Rating (GrossMWe)
5. Design Electrical Rating (Net Mwe): 1145 calculated as 1450.000
6. Maximum Dependable Capacity (Gross MWe): 1192 MVA * .90 power 1129 factor per Page iii,
7. Maximum Dependable Capacity(Net MWe):

NUREG-0020.

8. If Changes Occured in Capacity Ratings (Items Number 3-7) Since Last Report, Give Reasons:
9. Power Level To Which Restricted, If Any (Net MWe):
10. Reason for Restrictions, If any:

This Month YTD Cumulative

11. Hours in Reporting Period 744.0 2160.0 173185.0
12. Number of Hours Reactor was Critical 744.0 2160.0 145394.1
13. Reactor Reserve Shutdown Hours 0.0 0.0 0.0
14. Hours Generator On-Line 744.0 2160.0 143529.5
15. Unit Reserve Shutdown Hours 0.0 0.0 0.0
16. Gross Thermal Energy Generated (MWH) 2534266 7156102 475072422
17. Gross Electrical Energy Generated (MWH) 912869 2572599 168721465
18. Net Electrical Energy Generated (MWH) 866947 2440162 159226841
19. Unit Service Factor 100.0 100.0 82.9
20. Unit Availability Factor 100.0 100.0 82.9
21. Unit Capacity Factor (Using MDC Net) 103.2 100.1 81.3
22. Unit Capacity Factor (Using DER Net) 101.8 98.7 80.3
23. Unit Forced Outage Rate 0.0 0.0 5.4
24. Shutdown Scheduled Over Next 6 Months (Type, Date and Duration of Each)
25. If ShutDown At End Of Report Period, Estimated Date of Startup
26. Units in Test Status (Prior to Commercial Operation)

Forcast Achieved Initial Criticality Initial Electricity Commercial Operation 3A - 4/12/2005

Page: 1 of 1 UNIT SHUTDOWNS DOCKET NO. 50-413 UNIT NAME: Catawba 1 DATE: April 12.2005 COMPLETED BY: Roger Williams TELEPHONE: 704-382-5346 REPORT MONTH: March. 2005 No. Date: Type Duration (1) Reason (2) Method of Licensed Cause and Corrective Action to Prevent Recurrence F - Forced Hours Shutdown R/X Event Report S - Scheduled No.

No Outages for the Month Summary:

(1) Reason (2) Method A - Equipment failure (Explain) E - Operator Training/License Examination I - Manual 2 - Manual Trip/Scram B - Maintenance or Test F - Administrative 3 - Automatic Trip/Scram 4 - Continuation C - Refueling G - Operator Error (Explain) 5 - Other (Explain)

D - Regulatory restriction H - Other (Explain) 3C. 4/12/2005

MONTHLY REFUELING INFORMATION REQUEST

1. Facility name: Catawba Unit 1
2. Scheduled next refueling shutdown: May 2005
3. Scheduled restart following refueling: June 2005 THE PROJECT MANAGER HAS BEEN ADVISED BY SEPARATE COMMUNICATION OF ANY T.S. CHANGE OR LICENSE AMENDMENT. THEREFORE, QUESTIONS 4 THROUGH 6 WILL NO LONGER BE MAINTAINED IN THIS REPORT.
4. Will refueling or resumption of operation thereafter require a technical specification change or other license amendment?

If yes, what will these be?

If no, has reload design and core configuration been reviewed by Safety Review Committee regarding unreviewed safety questions?

5. Scheduled date(s) for submitting proposed licensing action and supporting information.
6. Important licensing considerations (new or different design or supplier, unreviewed design or performance analysis methods, significant changes in design or new operating procedures).
7. Number of Fuel assemblies (a) in the core: 193 (b) in the spent fuel pool: 1021
8. Present licensed fuel pool capacity: 1418 Size of requested or planned increase: =
9. Projected date of last refueling which can be accommodated by present license capacity:

November 2009 DUKE POWER COMPANY DATE: April 12.2005 Name of

Contact:

R. A. Williams Phone: (704) - 382-5346

Operating Data Report Docket No. 50414 Date April 12.2005 Completed By RoLer Williams Telephone 704-382-5346 Operating Status

1. Unit Name: Catawba 2
2. Reporting Period: March 1, 2005 -March 31, 2005
3. Licensed Thermal Power (MWt): 3411 Notes: *Nameplate
4. Nameplate Rating (Gross MWe): 1305
  • Rating (GrossMWe)
5. Design Electrical Rating (Net Mwe): 1145 calculated as 1450.000
6. Maximum Dependable Capacity (Gross MWe): 1192 MVA * .90 power 1129 factor per Page iii,
7. Maximum Dependable Capacity(Net MWe):

NUREG-0020.

8. If Changes Occured in Capacity Ratings (Items Number 3-7) Since Last Report, Give Reasons:
9. Power Level To Which Restricted, If Any (Net MWe):
10. Reason for Restrictions, If any:

This Month YTD Cumulative

11. Hours in Reporting Period 744.0 2160.0 163201.0
12. Number of Hours Reactor was Critical 744.0 2160.0 137811.9
13. Reactor Reserve Shutdown Hours 0.0 0.0 0.0
14. Hours Generator On-Line 744.0 2160.0 136331.6
15. Unit Reserve Shutdown Hours 0.0 0.0 0.0
16. Gross Thermal Energy Generated (MWH) 2534345 7356631 449713100
17. Gross Electrical Energy Generated (MWH) 913808 2653357 160423993
18. Net Electrical Energy Generated (MWH) 869938 2525779 151664495
19. Unit Service Factor 100.0 100.0 83.5
20. Unit Availability Factor 100.0 100.0 83.5
21. Unit Capacity Factor (Using MDC Net) 103.6 103.6 82.2
22. Unit Capacity Factor (Using DER Net) 102.1 102.1 81.2
23. Unit Forced Outage Rate 0.0 0.0 6.1
24. Shutdown Scheduled Over Next 6 Months (Type, Date and Duration of Each)
25. If ShutDown At End Of Report Period, Estimated Date of Startup
26. Units in Test Status (Prior to Commercial Operation)

Forcast Achieved Initial Criticality Initial Electricity Commercial Operation 3A - 4112/2005

Page: 1 of 1 UNIT SHUTDOWNS DOCKET NO. 50-414 UNIT NAME: Catawba 2 DATE: April 12.2005 COMPLETED BY: Roger Williams TELEPHONE: 704-382-5346 REPORT MONTH: March. 2005 No. Date: Type Duration (1) Reason (2) Method of Licensed Cause and Corrective Action to Prevent Recurrence F - Forced Hours Shutdown R/X Event Report S - Scheduled No.

No Outages for the Month Summary:

(1) Reason (2) Method A - Equipment failure (Explain) E - Operator Training/License Examination 1 - Manual 2 - Manual Trip/Scram B - Maintenance or Test F - Administrative 3 - Automatic Trip/Scram 4 - Continuation C - Refueling G - Operator Error (Explain) 5 - Other (Explain)

D - Regulatory restriction H - Other (Explain) 3C- 4/12/2005

MONTHLY REFUELING INFORMATION REQUEST

1. Facility name: Catawba Unit 2
2. Scheduled next refueling shutdown: March 2006
3. Scheduled restart following refueling: April 2006 THE PROJECT MANAGER HAS BEEN ADVISED BY SEPARATE COMMUNICATION OF ANY T.S. CHANGE OR LICENSE AMENDMENT. THEREFORE, QUESTIONS 4 THROUGH 6 WILL NO LONGER BE MAINTAINED IN THIS REPORT.
4. Will refueling or resumption of operation thereafter require a technical specification change or other license amendment?

If yes, what will these be?

If no, has reload design and core configuration been reviewed by Safety Review Committee regarding unreviewed safety questions?

5. Scheduled date(s) for submitting proposed licensing action and supporting information.
6. Important licensing considerations (new or different design or supplier, unreviewed design or performance analysis methods, significant changes in design or new operating procedures).
7. Number of Fuel assemblies (a) in the core: 193 (b) in the spent fuel pool: 993
8. Present licensed fuel pool capacity: 1418 Size of requested or planned increase: --
9. Projected date of last refueling which can be accommodated by present license capacity:

May 2012 DUKE POWER COMPANY DATE: April 12.2005 Name of

Contact:

R. A. Williams Phone: (704) - 382-5346

CATAWBA NUCLEAR STATION MONTHLY OPERATING STATUS REPORT FEBRUARY 2005

1. Personnel Exposure -

The total station liquid release for FEBRUARY has been compared with the Technical Specifications maximum annual dose commitment and was less than 10 percent of this limit.

The total station gaseous release for FEBRUARY has been compared with the Technical Specifications maximum annual dose commitment and was less than 10 percent of this limit.