Re Confirmation of Initial Operator License Examination
ML051090367
Person / Time
Site: Dresden  Constellation icon.png
Issue date: 04/18/2005
From: Hironori Peterson
Division of Reactor Safety III
To: Crane C
Exelon Generation Co, Exelon Nuclear
References
Download: ML051090367 (3)


Text

April 18, 2005 Mr. Christopher M. Crane President and Chief Nuclear Officer Exelon Nuclear Exelon Generation Company, LLC 4300 Winfield Road Warrenville, IL 60555

SUBJECT:

DRESDEN NUCLEAR POWER STATION - CONFIRMATION OF INITIAL OPERATOR LICENSE EXAMINATION

Dear Mr. Crane:

In a letter (RS-04-150) dated October 1, 2004, which revised the letter (RS-04-093) dated July 14, 2004, your staff requested that the U. S. Nuclear Regulatory Commission reschedule an initial license operator examination from the week of September 19, 2005, to the week of February 6, 2006. Therefore, we have tentatively rescheduled the examination to occur during the week of February 6, 2006. On-site validation of the examination is tentatively scheduled to occur at the station during the week of January 9, 2006. In the unlikely event that we are unable to support the examination during the scheduled weeks, we will inform you immediately upon discovery of such conditions and make arrangements to administer the examination at a mutually acceptable date.

As stated in your letter of October 1, 2004, your staff will develop the examination. Your letter indicated that you are training approximately six candidates for the examination. Please inform us at your earliest opportunity if you discover you need to change the scheduled date for the examination.

A supplementary letter will be sent to the training department approximately 120 days prior to the initial examination informing them of the chief examiners name. The letter will also outline examination security expectations, list the materials required by the NRC to conduct the examination, reconfirm the examination dates, and reconfirm the number of candidates you have in the training program. If you have any questions concerning this information, please contact Mr. Charles Phillips of my staff at (630) 829-9739.

In accordance with 10 CFR 2.390 of the NRC's "Rules of Practice," a copy of this letter will be available electronically for public inspection in the NRC Public Document Room or from the Publicly Available Records (PARS) component of NRC's Agencywide Documents Access and

C. Crane Management System (ADAMS). ADAMS is accessible from the Electronic Reading Room page of the NRCs public Web site at http://www.nrc.gov/reading-rm/adams.html.

Sincerely,

/RA/

Hironori Peterson, Chief Operations Branch Division of Reactor Safety Docket Nos. 50-237; 50-249 License Nos. DPR-19; DPR-25 cc: Site Vice President - Dresden Nuclear Power Station Dresden Nuclear Power Station Plant Manager Regulatory Assurance Manager - Dresden Chief Operating Officer Senior Vice President - Nuclear Services Senior Vice President - Mid-West Regional Operating Group Vice President - Mid-West Operations Support Vice President - Licensing and Regulatory Affairs Director Licensing - Mid-West Regional Operating Group Manager Licensing - Dresden and Quad Cities Senior Counsel, Nuclear, Mid-West Regional Operating Group Document Control Desk - Licensing Assistant Attorney General Illinois Department of Nuclear Safety State Liaison Officer Chairman, Illinois Commerce Commission C. G. Symonds, Training Director

C. Crane Management System (ADAMS). ADAMS is accessible from the Electronic Reading Room page of the NRCs public Web site at http://www.nrc.gov/reading-rm/adams.html.

Sincerely,

/RA/

Hironori Peterson, Chief Operations Branch Division of Reactor Safety Docket Nos. 50-237; 50-249 License Nos. DPR-19; DPR-25 cc: Site Vice President - Dresden Nuclear Power Station Dresden Nuclear Power Station Plant Manager Regulatory Assurance Manager - Dresden Chief Operating Officer Senior Vice President - Nuclear Services Senior Vice President - Mid-West Regional Operating Group Vice President - Mid-West Operations Support Vice President - Licensing and Regulatory Affairs Director Licensing - Mid-West Regional Operating Group Manager Licensing - Dresden and Quad Cities Senior Counsel, Nuclear, Mid-West Regional Operating Group Document Control Desk - Licensing Assistant Attorney General Illinois Department of Nuclear Safety State Liaison Officer Chairman, Illinois Commerce Commission C. G. Symonds, Training Director ADAMS Distribution:

AJM MXB RidsNrrDipmIipb GEG KGO DRC1 DRPIII DRSIII PLB1 JRK1 DCT MAB1 DOCUMENT NAME: ML051090367.wpd To receive a copy of this document, indicate in the box "C" = Copy w/o attach/encl "E" = Copy with attach/encl "N" = No copy OFFICE RIII RIII RIII MABies:tr DMcNeil for HPeterson NAME CPhillips DATE 04/13/05 04/15/05 04/18/05 OFFICIAL RECORD COPY