RS-04-150, Revised Response to NRC Regulatory Issue Summary 2004-10 Preparation and Scheduling of Operator Licensing Examinations
| ML042750478 | |
| Person / Time | |
|---|---|
| Site: | Dresden |
| Issue date: | 10/01/2004 |
| From: | Gallagher M Exelon Generation Co, Exelon Nuclear |
| To: | Document Control Desk, Office of Nuclear Reactor Regulation |
| References | |
| RIS-04-010, RS-04-150 | |
| Download: ML042750478 (2) | |
Text
Cxplon Nuclear www exeloncorp roni 2 0 0 Exelon Way Kennett Square, PA 19348 RIS 2004-1 0 RS-04-150 October 1, 2004 U. S. Nuclear Regulatory Commission ATTN: Document Control Desk Washington, DC 20555-0001 Dresden Nuclear Power Station, Units 2 and 3 Facility Operating License Nos. DPR-19 and DPR-25 NRC Docket Nos. 50-237 and 50-249
Subject:
Revised Response to NRC Regulatory Issue Summary 2004-1 0 Preparation and Scheduling of Operator Licensing Examinations
Reference:
- 1. NRC Regulatory Issue Summary (RIS) 2004-1 0, Preparation and Scheduling of Operator Licensing Examinations, dated June 14, 2004.
- 2. Exelon/AmerGen Response to RIS 2004-1 0 dated July 14, 2004 In Reference 1, the NRC requested licensees to voluntarily submit a response concerning initial operator licensing examination needs, including an estimate of the number of applicants to be examined and intentions regarding the preparation of the examinations. In Reference 2, Exelon Generation Company, LLC (Exelon) and AmerGen Energy Company, LLC (AmerGen) provided the operator licensing examination information for each Exelon and AmerGen facility on a separate NRC Form 536.
The attachment to this letter provides a revised response to RIS 2004-10 for Dresden Nuclear Power Station. The revised response is requesting a change in the date for the Calendar Year 2005 and 2006 NRC Initial Operator Licensing Examination schedule. Dresden is requesting the Examination currently scheduled during the week of September 19, 2005, be moved to the week of February 6, 2006. The revised Initial Operator Licensing Examination information is provided on the attached NRC Form 536.
If you have any questions or require additional information, please do not hesitate to contact us.
Michael P. Gallagher, Director Licensing & Regulatory Affairs Exelon Generation Company, LLC Attachment - Completed NRC Form 536 for Dresden Nuclear Power Station
Revised Response to RIS 2004-1 0 PROPOSED NUMBER ESTIMATED NUMBER OF LICENSEE-PREPARED EXAMINATIONS ESTIMATED NUMBER OF NRC-PREPARED EXAMINATIONS Attachment APPROVED BY OMB NO 3150-0131 EXPIRES 07/31 12001 CY 2005 CY 2006 CY 2007 CY 2008 0
1 1
1 0
0 0
0 NRC FORM 536 (5-2003)
U.S NUCLEAR REGULATORY COMMISSION 0
NUMBER OF REACTOR OPERATORS OPERATOR LICENSING EXAMINATION DATA 0
2 0
FACl LlTY 0
NUMBER OF SENIOR REACTOR OPERATORS-LIMITED Estimated burden per response to comply with this voluntary information collectiot request: 1 hour1.157407e-5 days <br />2.777778e-4 hours <br />1.653439e-6 weeks <br />3.805e-7 months <br />. This information collection is used to plan budgets and resources fo o erator examinations. Send comments regarding burden estimate lo the Record:
- Jan, ement Branch (T-6 E6). U.S. Nuclear Regulator Commission. Washin ton DC 28555-0001 or by internet e-mail to infocollects&nrc ov and lo the 8esl Officer Office of information and Re ulatory Affairs, NEO8-10202. (3150-0131)
Office of Management and Budget dashin ton DC 20503. If a means used t(
impose an information collection dbes not &play a currently valid OMB contro number, the NRC may not conduct or sponsor. and a person is not required t(
respond to, the information collection.
NRC REGION 0
0 0
Dresden Nuclear Power Station, Units 2 and 3 Facility Operating License Nos. DPR-19 and DPR-25 NRC Docket Nos. 50-237 and 50-249 PRIMARY DATE ALTERNATE DATE TI1 N/A 2/6/06 - 211 0106 1/29/07 - 2/2/07 N/A 211 3/06 - 211 7/06 2/5/07 - 2/9/07 PROPOSED NUMBER EST1 MATED NUMBER OF EANDI DATES PROPOSED NUMBER CY 2005 CY 2006 MARCH JUNE SEPTEMBER DECEMBER MARCH JUNE SEPTEMBER DECEMBER -
0 0
0 10 0
0 0
0 NUMBER OF SENIOR REACTOR OPE RAT0 RS-I N STANT 6
6 NUMBER OF SENIOR REACTOR OPERATORS-UPGRADE O
I
2 0
PROPOSED DATES 711 4/08 - 711 8/08 7/21 108 - 7/25/08