Summary of 04/06/2005 Meeting with Constellation Energy Regarding Proposed Extended Power Uprate for Ginna
ML051010104
Person / Time
Site: Ginna Constellation icon.png
Issue date: 04/19/2005
From: Skay D
NRC/NRR/DLPM/LPD1
To:
Skay, Donna, DLPM/PD1, 415-1322
References
TAC MC4033
Download: ML051010104 (28)


Text

April 19, 2005 LICENSEE:

R. E. Ginna Nuclear Power Plant, LLC FACILITY:

R. E. Ginna Nuclear Power Plant

SUBJECT:

SUMMARY

OF APRIL 6, 2005, MEETING WITH R. E. GINNA NUCLEAR POWER PLANT, LLC REGARDING PROPOSED EXTENDED POWER UPRATE FOR GINNA (TAC NO. MC4033)

On April 6, 2005, a Category 1 public meeting was held between the U.S. Nuclear Regulatory Commission (NRC) and representatives of the licensee for the R. E. Ginna Nuclear Power Plant (Ginna) at NRC Headquarters, One White Flint North, 11555 Rockville Pike, Rockville, Maryland. The purpose of the meeting was to exchange information with the NRC regarding their proposed extended power uprate (EPU) for Ginna. A formal license amendment request is scheduled to be submitted to the NRC for approval in June of 2005. A list of attendees is provided as Enclosure 1.

The licensee presented information (see Enclosure 2) on three areas of the proposed EPU:

(1) Probablistic Safety Analysis approach; (2) A discussion of the license amendment requests that will be submitted prior to the EPU and will support the EPU application; and (3) A description of the new fuel assemblies to be loaded during the 2006 refueling outage in support of the EPU.

Members of the public were not in attendance. Public meeting feedback forms were not received.

Please direct any inquiries to Donna Skay at 301-415-1322 or dms6@nrc.gov.

/RA/

Donna Skay, Senior Project Manager, Section 1 Project Directorate I Division of Licensing Project Management Office of Nuclear Reactor Regulation Docket No. 50-244

Enclosures:

1. List of Attendees
2. Licensee Handouts cc w/encls: See next page

April 19, 2005 LICENSEE:

R. E. Ginna Nuclear Power Plant, LLC FACILITY:

R. E. Ginna Nuclear Power Plant

SUBJECT:

SUMMARY

OF APRIL 6, 2005, MEETING WITH R. E. GINNA NUCLEAR POWER PLANT, LLC REGARDING PROPOSED EXTENDED POWER UPRATE FOR GINNA (TAC NO. MC4033)

On April 6, 2005, a Category 1 public meeting was held between the U.S. Nuclear Regulatory Commission (NRC) and representatives of the licensee for the R. E. Ginna Nuclear Power Plant (Ginna) at NRC Headquarters, One White Flint North, 11555 Rockville Pike, Rockville, Maryland. The purpose of the meeting was to exchange information with the NRC regarding their proposed extended power uprate (EPU) for Ginna. A formal license amendment request is scheduled to be submitted to the NRC for approval in June of 2005. A list of attendees is provided as Enclosure 1.

The licensee presented information (see Enclosure 2) on three areas of the proposed EPU:

(1) Probablistic Safety Analysis approach; (2) A discussion of the license amendment requests that will be submitted prior to the EPU and will support the EPU application; and (3) A description of the new fuel assemblies to be loaded during the 2006 refueling outage in support of the EPU.

Members of the public were not in attendance. Public meeting feedback forms were not received.

Please direct any inquiries to Donna Skay at 301-415-1322 or dms6@nrc.gov.

/RA/

Donna Skay, Senior Project Manager, Section 1 Project Directorate I Division of Licensing Project Management Office of Nuclear Reactor Regulation Docket No. 50-244

Enclosures:

1. List of Attendees
2. Licensee Handouts cc w/encls: See next page DISTRIBUTION PUBLIC PDI-1 R/F ACRS/ACNW SLittle DSkay RLaufer JStang RLobel Cholden TMarsh/JLyons GMatakas, RI LWard OGC MStutzke CLiang SMiranda SLaur JLee KWood PClifford Forr Apatel DJohnson Accession No.: ML051010104 Package No.: ML051090389 OFFICE PDI-1/PM PDI-1/LA PDI-1/SC NAME DSkay SLittle RLaufer DATE 4/18/05 4/18/05 4/19/05 OFFICIAL RECORD COPY

R.E. Ginna Nuclear Power Plant cc:

Mr. Michael J. Wallace President R.E. Ginna Nuclear Power Plant, LLC c/o Constellation Energy 750 East Pratt Street Baltimore, MD 21202 Mr. John M. Heffley Senior Vice President and Chief Nuclear Officer Constellation Generation Group 1997 Annapolis Exchange Parkway Suite 500 Annapolis, MD 21401 Kenneth Kolaczyk, Sr. Resident Inspector R.E. Ginna Nuclear Power Plant U.S. Nuclear Regulatory Commission 1503 Lake Road Ontario, NY 14519 Regional Administrator, Region I U.S. Nuclear Regulatory Commission 475 Allendale Road King of Prussia, PA 19406 Peter R. Smith, President New York State Energy, Research, and Development Authority 17 Columbia Circle Albany, NY 12203-6399 Mr. Carey W. Fleming Sr. Counsel - Nuclear Generation Constellation Generation Group, LLC 750 E. Pratt Street, 17th Floor Baltimore, MD 21202 Charles Donaldson, Esquire Assistant Attorney General New York Department of Law 120 Broadway New York, NY 10271 Ms. Thelma Wideman, Director Wayne County Emergency Management Office Wayne County Emergency Operations Center 7336 Route 31 Lyons, NY 14489 Ms. Mary Louise Meisenzahl Administrator, Monroe County Office of Emergency Preparedness 1190 Scottsville Road, Suite 200 Rochester, NY 14624 Mr. Paul Eddy New York State Department of Public Service 3 Empire State Plaza, 10th Floor Albany, NY 12223 Mrs. Mary G. Korsnick Vice President R.E. Ginna Nuclear Power Plant R.E. Ginna Nuclear Power Plant, LLC 1503 Lake Road Ontario, NY 14519 MEETING BETWEEN NRC AND GINNA NUCLEAR POWER PLANT, LLC (GINNA)

ATTENDANCE LIST APRIL 6, 2005 NRC, Office of Nuclear Reactor Regulation (NRR)

D. Skay, NRR J. Stang, NRR R. Lobel, NRR S. Miranda, NRR C. Liang, NRR M. Stutzke, NRR J. Lee, NRR A. Patel, NRR D. Johnson, NRR F. Orr, NRR K. Wood, NRR P. Clifford, NRR INDUSTRY M. Finley, Ginna R. Cavedo, Ginna D. Sklarsky, Westinghouse W. Slagle, Westinghouse G. Wrobel, Ginna