March 31, 2005
Jeffrey S. Forbes
Vice President Operations
Arkansas Nuclear One
Entergy Operations, Inc.
1448 S.R. 333
Russellville, AR 72801-0967
SUBJECT:
ARKANSAS NUCLEAR ONE, UNIT 1 - NOTIFICATION OF NRC INITIAL
OPERATOR LICENSING EXAMINATION 05000313/2005301
Dear Mr. Forbes:
In a telephone conversation on March 1, 2005 between Mr. Randal Martin, Training Supervisor
and Mr. Mark Haire, Chief Examiner, arrangements were made for the administration of
licensing examinations at Arkansas Nuclear One during the week of September 12, 2005.
As agreed during the telephone conversation, your staff will prepare the examinations based on
the guidelines in Revision 9 of NUREG-1021, Operator Licensing Examination Standards for
Power Reactors. The NRCs regional office will discuss with your staff any changes that might
be necessary before the examinations are administered.
To meet the above schedule, it will be necessary for your staff to furnish the examination
outlines by May 16, 2005. The written examinations, operating tests, and supporting reference
materials identified in Attachment 2 to ES-201 will be due by July 14, 2005. Pursuant to
Title 10, Section 55.40(b)(3), of the Code of Federal Regulations (10 CFR 55.40(b)(3)), an
authorized representative of the facility licensee shall approve the outlines, examinations, and
tests before they are submitted to the NRC for review and approval. All materials shall be
complete and ready-to-use. Any delay in receiving the required examination and reference
materials, or the submittal of inadequate or incomplete materials, may cause the examinations
to be rescheduled.
In order to conduct the requested written examinations and operating tests, it will be necessary
for your staff to provide adequate space and accommodations in accordance with ES-402, and
to make the simulation facility available on the dates noted above. In accordance with ES-302,
your staff should retain the original simulator performance data (e.g., system pressures,
temperatures, and levels) generated during the dynamic operating tests until the examination
results are final.
Appendix E to NUREG-1021 contains a number of NRC policies and guidelines that will be in
effect while the written examinations and operating tests are being administered.
Entergy Operations, Inc.
-2-
To permit timely NRC review and evaluation, your staff should submit preliminary reactor
operator and senior reactor operator license applications (Office of Management and Budget
(OMB) approval number 3150-0090), medical certifications (OMB approval number 3150-0024),
and waiver requests (if any)(OMB approval number 3150-0090) at least 30 days before the first
examination date. If the applications are not received at least 30 days before the examination
date, a postponement may be necessary. Signed applications certifying that all training has
been completed should be submitted at least 14 days before the first examination date.
This letter contains information collections that are subject to the Paperwork Reduction Act of
1995 (44 U.S.C. 3501 et seq.). These information collections were approved by OMB, under
approval number 3150-0018, which expires on June 30, 2006. The public reporting burden for
this collection of information is estimated to average 500 hours0.00579 days <br />0.139 hours <br />8.267196e-4 weeks <br />1.9025e-4 months <br /> per response, including the time
for reviewing instructions, gathering and maintaining the data needed, writing the examinations,
and completing and reviewing the collection of information. Send comments on any aspect of
this collection of information, including suggestions for reducing the burden, to the Information
and Records Management Branch (T-6 F33), U.S. Nuclear Regulatory Commission,
Washington, DC 20555-0001, or by Internet electronic mail to BJS1@nrc.gov; and to the Desk
Officer, Office of Information and Regulatory Affairs, NEOB-10202, (3150- 0018), Office of
Management and Budget, Washington, DC 20503.
The NRC may neither conduct nor sponsor, and a person is not required to respond to, an
information collection, unless it displays a currently valid OMB control number.
In accordance with 10 CFR 2.390 of the NRCs Rules of Practice, a copy of this letter and
its enclosures will be available electronically for public inspection in the NRCs Public
Document Room or from the Publicly Available Records (PARS) component of the NRCs
Agencywide Documents Access and Management System (ADAMS). ADAMS is accessible
from the Electronic Reading Room page of the NRCs public Web site at
http://www.nrc.gov/reading-rm/adams.html.
Thank you for your cooperation in this matter. Randal Martin has been advised of the policies
and guidelines referenced in this letter. If you have any questions regarding the NRCs
examination procedures and guidelines, please contact Mark Haire at 817-860-8117, or myself
at 817-860-8159.
Sincerely,
/RA/
Anthony T. Gody, Chief
Operations Branch
Division of Reactor Safety
Dockets: 50-313
Licenses: DPR-51
Entergy Operations, Inc.
-3-
cc:
Senior Vice President
& Chief Operating Officer
Entergy Operations, Inc.
P.O. Box 31995
Jackson, MS 39286-1995
Vice President
Operations Support
Entergy Operations, Inc.
P.O. Box 31995
Jackson, MS 39286-1995
Manager, Washington Nuclear Operations
ABB Combustion Engineering Nuclear
Power
12300 Twinbrook Parkway, Suite 330
Rockville, MD 20852
County Judge of Pope County
Pope County Courthouse
100 West Main Street
Russellville, AR 72801
Winston & Strawn
1400 L Street, N.W.
Washington, DC 20005-3502
Bernard Bevill
Radiation Control Team Leader
Division of Radiation Control and
Emergency Management
4815 West Markham Street, Mail Slot 30
Little Rock, AR 72205-3867
James Mallay
Director, Regulatory Affairs
Framatome ANP
3815 Old Forest Road
Lynchburg, VA 24501
Entergy Operations, Inc.
-4-
Electronic distribution by RIV:
Regional Administrator (BSM1)
DRP Director (ATH)
DRS Director (DDC)
DRS Deputy Director (KSW)
Senior Resident Inspector (RWD)
Branch Chief, DRP/D (TWP)
Senior Project Engineer, DRP/D (GEW)
Team Leader, DRP/TSS (RLN1)
RITS Coordinator (KEG)
SISP Review Completed: ______
ADAMS: : Yes
G No Initials: ______
- Publicly Available G Non-Publicly Available G Sensitive
- Non-Sensitive
OE:OB
C:OB
MHaire/lmb
ATGody
/RA/
/RA/
3/30/05
3/31/05
OFFICIAL RECORD COPY
T=Telephone E=E-mail F=Fax