|
---|
Category:E-Mail
MONTHYEARML24296A0652024-10-22022 October 2024 NRR E-mail Capture - Arkansas Nuclear One, Unit 2 - Verbal Authorization of Relief Request for the Proposed Alternative ANO2-RR-24-001 ML24227A0072024-08-13013 August 2024 NRR E-mail Capture - LIC-109 Acceptance - ANO 2 - Proposed Alternative for Implementation of Extended Reactor Vessel In-Service Inspection Interval (ANO2-ISI-24-02) - EPID L-2024-LLR-0048 ML24218A0652024-08-0202 August 2024 NRR E-mail Capture - LIC-109 Acceptance Review - Arkansas Nuclear One, Unit 1 - License Amendment Request - Request for Review and Approval Changes to SAR and to a Confirmatory Order - Pzr Htr Emergency Power Supply - EPID L-2024-LLA-0092 ML24180A0022024-06-26026 June 2024 NRR E-mail Capture - LIC-109 Acceptance - ANO 1 and 2 - Proposed Alternatives for Examinations of SG Pressure Retaining Welds and Full Penetrations Nozzles - EPID L-2024-LLR-0038 ML24149A3672024-05-28028 May 2024 August 2024 Emergency Preparedness Exercise Inspection - Request for Information ML24117A0262024-04-26026 April 2024 NRR E-mail Capture - ANO Unit 2 - Acceptance of Requested Licensing Action License Amendment Request to Revise Typographical Errors in Technical Specifications ML24088A0082024-03-27027 March 2024 NRR E-mail Capture - ANO-2 -- TSTF-505 Post-Audit Final RAI (L-2023-LLA-0052) ML23269A0232023-09-22022 September 2023 NRR E-mail Capture - Arkansas Nuclear One, Unit 2 - TSTF-505 Audit Questions ML23240A3412023-08-28028 August 2023 NRR E-mail Capture - ANO-2, Grand Gulf, and River Bend - Acceptance Review of LAR Revising TSs to Adopt TSTF-205, Revision of Channel Calibration, Channel Functional Test, and Related Definitions ML23194A1752023-07-13013 July 2023 NRR E-mail Capture - ANO-1 - Acceptance Review of Alternative Request ANO1-ISI-037 ML23187A0432023-07-0303 July 2023 NRR E-mail Capture - Arkansas Nuclear One, Unit 1 - TSTF-505 Audit Agenda ML23166A0132023-06-14014 June 2023 NRR E-mail Capture - Arkansas Nuclear One, Unit 1 - TSTF-505 Audit Questions ML23130A2752023-05-10010 May 2023 NRR E-mail Capture - ANO Unit 2- Acceptance of Requested Licensing Action LAR to Adopt TSTF-505 Revision 2 ML23118A0692023-04-28028 April 2023 NRR E-mail Capture - ANO Unit 1 - Acceptance of Requested Licensing Action LAR to Modify ANO-1 TS 3.3.1, Reactor Protection System Instrumentation (L-2023-LLA-0048) ML23104A1052023-03-10010 March 2023 NRR E-mail Capture - ANO-2 Final RAI Alternative Request for Life-of-Repair of RVCH Pen. 46 ML23072A3672023-03-0909 March 2023 NRR E-mail Capture - Entergy Fleet - Acceptance Review of Quality Assurance Program Manual Reduction in Commitment ML23039A0872023-02-0808 February 2023 NRR E-mail Capture - Arkansas Nuclear One, Unit 2 - Acceptance Review of Relief Request ANO2-RR-23-001, Half-Nozzle Repair of RVCH Penetration 46 (L-2023-LLR-0000) ML23026A1322023-01-26026 January 2023 NRR E-mail Capture - ANO Unit 1 - Acceptance of Requested Licensing Action LAR to Adopt TSTF-505 Revision 2 ML22354A0122022-12-19019 December 2022 NRR E-mail Capture - ANO-1 and ANO-2 - Acceptance Review of Request for Alternative ANO-CISI-002 Alternative Frequency to Containment Unbonded Post-Tensioning System Inservice Inspection (L-2022-LLR-0080) ML22349A0112022-12-14014 December 2022 NRR E-mail Capture - Final RAI Relief Request ANO1-ISI-035 ML22341A1202022-12-0707 December 2022 NRR E-mail Capture - ANO Unit 1 - Acceptance of Requested Licensing Action LAR to to Remove Technical Specification Condition Allowing Two Reactor Coolant Pump Operation (L-2022-LLA-0161) ML22273A0982022-09-30030 September 2022 NRR E-mail Capture - ANO Units 1 and 2 - Acceptance of Requested Licensing Action Emergency Plan Staffing Requirements ML22265A2012022-09-22022 September 2022 NRR E-mail Capture - ANO-1 - Acceptance Review of Relief Request ANO1-ISI-036 ML22188A1782022-07-0707 July 2022 NRR E-mail Capture - ANO-1 - Acceptance Review of Relief Request ANO1-ISI-035 ML22174A1362022-06-23023 June 2022 NRR E-mail Capture - ANO-2 Final RAI Relief Requests ANO2-ISI-023 Through -028 (EPIDs L-2022-LLR-0022 Through -0027) ML22151A3262022-05-31031 May 2022 August 2022 Emergency Preparedness Exercise Inspection - Request for Information ML22124A2452022-05-0404 May 2022 NRR E-mail Capture - ANO-1 and ANO-2 - Final RAI 2 License Amendment Requests to Implement Provisions of 10 CFR 50.69 (L-2021-LLA-0105/-0106) ML22108A1642022-04-18018 April 2022 NRR E-mail Capture - ANO-1: Final RAI License Amendment Request Concerning TS Changes Due to Revised Dose Calculations (L-2021-LLA-0181) ML22081A3902022-03-22022 March 2022 NRR E-mail Capture - ANO-2 - Acceptance Review of Relief Requests ANO2-ISI-023, -024, -025, -026, -027, and -028 (Epids: L-2022-LLR-022, -023, -024, -025, -026, and -027) ML22034A5482022-02-0303 February 2022 NRR E-mail Capture - Final RAI License Amendment Requests to Implement Provisions of 10 CFR 50.69 (L-2021-LLA-0105/-0106) ML22020A0822022-01-19019 January 2022 NRR E-mail Capture - ANO-1 and 2 - Final RAI 2 License Amendment Requests to Allow the ECP to Remain Operable on a One-Time Basis for Up to 65 Days to Perform Piping Upgrade (L-2021-LLA-0015) ML22020A0742022-01-13013 January 2022 NRR E-mail Capture - ANO Unit 2 - Acceptance of Requested Licensing Action Alternative ANO2-PT-003 ML21314A1212021-11-0909 November 2021 Verbal Authorization of Relief Request ANO2-RR-21-002 ML21312A4792021-11-0505 November 2021 Email: NRC Staff Preliminary Questions Regarding X Energy LLC Xe-100 Topical Report: Risk-Informed Performance-Based Licensing Basis Development ML21312A0382021-11-0505 November 2021 NRR E-mail Capture - ANO-2 RAI Relief Request ANO2-RR-21-002 ML21308A5602021-11-0404 November 2021 NRR E-mail Capture - Arkansas Nuclear One, Units 1 and 2, Grand Gulf, River Bend, and Waterford, Unit 3 - Acceptance Review of LAR to Adopt TSTF-554, Revise Reactor Coolant Leakage Requirements ML21292A0112021-10-18018 October 2021 NRR E-mail Capture - ANO, 1 and 2, Grand Gulf, River Bend, Waterford, 3 - Acceptance Review of LAR to Adopt TSTF-541, Add Exceptions to Surveillance Requirements for Valves and Dampers Locked in the Actuated Position ML21287A1692021-10-13013 October 2021 Record of 10-13-21 Verbal Authorization of ANO2-R&R-012 (L-2021-LLR-0082) ML21298A1562021-10-11011 October 2021 NRR E-mail Capture - ANO-2 Final RAI Relief Request ANO2-R&R-012 Concerning Rv Closure Head Penetration 46 ML21273A0672021-09-29029 September 2021 NRR E-mail Capture - ANO-2 Final RAI 2 License Amendment Request to Adopt a Safety Function Determination Program ML21238A3742021-08-23023 August 2021 RFI Email - Cyber PI&R Inspection (ANO) ML21252A0052021-08-20020 August 2021 NRR E-mail Capture - ANO-1 and 2 Final RAI License Amendment Request to Allow the ECP to Remain Operable on a One-Time Basis for Up to 65 Days to Perform Piping Upgrade (L-2021-LLA-0015) ML21217A3302021-08-0505 August 2021 (ANO) Problem Identification and Resolution (PIR) Request for Information Combined ML21202A1662021-07-20020 July 2021 NRR E-mail Capture - ANO Unit 2 - Acceptance of Requested Licensing Action Alternative ANO2-PT-003 ML21201A0062021-07-19019 July 2021 NRR E-mail Capture - Arkansas Nuclear One, Units 1 and 2, and Waterford, Unit 3 - Acceptance Review of LAR to Adopt TSTF-577, Revised Frequencies for Steam Generator Tube Inspections ML21197A0372021-07-16016 July 2021 NRR E-mail Capture - ANO-1 and 2 - Final RAI Final Response to GL 2004-02 ML21179A0052021-06-25025 June 2021 NRR E-mail Capture - ANO Unit 2 - Acceptance of Requested Licensing Action License Amendment Request to Adopt 10 CFR 50.69 ML21179A0042021-06-25025 June 2021 NRR E-mail Capture - ANO Unit 1 - Acceptance of Requested Licensing Action License Amendment Request to Adopt 10 CFR 50.69 ML21174A0342021-06-22022 June 2021 NRR E-mail Capture - Entergy Fleet (ANO, Ggulf, Rbend, & Waterford) - Acceptance Review for Relief Request to Use a Provision of a Later Edition of the ASME Code, Section XI for Periodic System Pressure Tests Exemptions ML21116A1092021-04-26026 April 2021 NRR E-mail Capture - ANO-1 and ANO-2: Final Supplemental RAI Proposed Alternative to ASME Section XI Requirements for Repair/Replacement of ECP Supply Piping 2024-08-02
[Table view] |
Text
[Thomas Alexion - Sketch of ANO-1 Nozzle 61 Page 1 From: "BENNETT, STEVE A" <SBENNE2@entergy.com>
To: "Jeff Clark aac~nrc.gov)" .jac~nrc.gov>, "Tom Alexion"' <twa~nrc.gov>, "DEESE, RICHARD W" <rdees9O@entergy.com>
Date: 5/4/04 1:52PM
Subject:
bty NO Nzle 61 attached
[bAW1ND0WS\TEMP\GW)00001 .TMP Page 1 I Mail Envelope Properties (4097D83F.433: 21: 29747)
Subject:
Sketch of ANO-1 Nozzle 61 Creation Date: 5/4/04 1:45PM From: "BENNETT, STEVE A" <SBENNE2@entergy.com>
Created By: SBENNE2@entergy.com Recipients nrc.gov owf4_po.OWFNDO TWA (Thomas Alexion) nrc.gov ARLPO.ARL_DO JAC (Jeffrey Clark) entergy.com rdees90 (DEESE, RICHARD W)
Post Office Route owf4_po.0WFN_DO nrc.gov ARL_PO.ARL_DO nrc.gov entergy.com Files Size Date & Time MESSAGE 11 05/04/04 01:45PM Part.001 917 Sketch of Nozzle 61.pdf 11777 Mime.822 15534 Options Expiration Date: None Priority: Standard Reply Requested: No Return Notification: None Concealed
Subject:
No Security: Standard
XnS, cCIQ;) -Ind; "+,