ML050410097

From kanterella
Jump to navigation Jump to search
NRC Inspection Report 05000395/2005006; Preliminary White Finding
ML050410097
Person / Time
Site: Summer South Carolina Electric & Gas Company icon.png
Issue date: 01/14/2005
From: Casto C
Division of Reactor Safety II
To: Archie J
South Carolina Electric & Gas Co
References
EA-05-008 IR-04-009, IR-05-006
Download: ML050410097 (26)


See also: IR 05000395/2005006

Text

January 14, 2005

EA-05-008

South Carolina Electric & Gas Company

ATTN: Mr. Jeffery B. Archie

Senior Vice President, Nuclear Operations

Virgil C. Summer Nuclear Station

P. O. Box 88

Jenkinsville, SC 29065

SUBJECT:

VIRGIL C. SUMMER NUCLEAR STATION - NRC INSPECTION REPORT

05000395/2005006; PRELIMINARY WHITE FINDING

Dear Mr. Archie:

This letter and the enclosed supporting documentation discuss a finding that appears to have

low to moderate safety significance [White]. Section 4OA5.2.1.1 of NRC Inspection Report 05000395/2004009, issued on December 22, 2004, identified this finding [Unresolved Item

(URI) 05000395/2004009-01] which concerned inadequacies in your corrective actions

associated with a deficiency in the design of the emergency feedwater (EFW) system flow

control valves. This deficiency could have resulted in a common mode failure of the EFW

system as a result of plugging of the valves by tubercles and debris in the service water system.

This item was unresolved pending the NRCs determination of the safety significance.

This finding was assessed based on the best available information, including influential

assumptions, using the applicable Significance Determination Process (SDP) and was

preliminarily determined to be a White finding (i.e., a finding with some increased importance to

safety, which may require additional NRC inspection).

As indicated in the enclosed SDP Phase III Analysis, the issue appears to have a low to

moderate safety significance due to the importance of continued EFW system availability, when

supplied by the service water suction source, during events which deplete or render the

condensate storage tank inoperable. However, the risk associated with this deficiency was

somewhat mitigated by the fact that the finding only affected the alternate suction source for the

EFW system and did not impact normal EFW system operation. Additionally, other core cooling

mechanisms, such as use of the main feedwater system or primary system feed and bleed

were not affected.

This finding does not present an immediate safety concern because you instituted

compensatory measures including operator actions to install temporary hoses to bypass the

EFW flow control valves if they become plugged.

SCE&G

2

Two apparent violations (AV) of 10 CFR 50, Appendix B were identified regarding this finding.

The first, an apparent violation of Criterion III, Design Control, is identified as AV

05000395/2005006-01: EFW Flow Control Valves Are Susceptible to Plugging by

Tubercles and Other Debris from Service Water. The second, an apparent violation of Criterion

XVI, Corrective Actions, is identified as AV 05000395/2005006-02: Inadequate Corrective

Actions in Response to Potential EFW Control Valve Plugging. These apparent violations are

being considered for escalated enforcement action in accordance with the "General Statement

of Policy and Procedure for NRC Enforcement Actions (Enforcement Policy), NUREG-1600.

The current Enforcement Policy is included on the NRCs website at

http://www.nrc.gov/what-we-do/regulatory/enforcement/enforce-pol.html. Accordingly, for

administrative purposes, URI 05000395/2004009-01, is considered closed.

Before we make a final decision on this matter, we are providing you an opportunity (1) to

present to the NRC your perspectives on the facts and assumptions, used by the NRC to arrive

at the finding and its significance, at a Regulatory Conference or (2) submit your position on the

finding to the NRC in writing. If you request a Regulatory Conference, it should be held within

30 days of the receipt of this letter and we encourage you to submit supporting documentation

at least one week prior to the conference in an effort to make the conference more efficient and

effective. If a Regulatory Conference is held, it will be open for public observation and the NRC

will issue a press release to announce the conference. If you decide to submit only a written

response, such submittal should be sent to the NRC within 30 days of the receipt of this letter.

Please contact Mr. Charles R. Ogle at (404) 562-4605 within seven days of the date of this

letter to notify the NRC of your intentions regarding the regulatory conference for the

preliminary White finding. If we have not heard from you within 10 days, we will continue with

our significance determination and associated enforcement processes on this finding, and you

will be advised by separate correspondence of the results of our deliberations on this matter.

Since the NRC has not made a final determination in this matter, no Notice of Violation is being

issued for the inspection finding at this time. In addition, please be advised that the number

and characterization of the apparent violations may change as a result of further NRC review.

In accordance with 10 CFR 2.390 of the NRC's "Rules of Practice," a copy of this letter, its

enclosure and your response (if any) will be available electronically for public inspection in the

NRC Public Document Room or from the Publicly Available Records (PARS) component of

NRCs document system (ADAMS). ADAMS is accessible from the NRC web site at

http://www.nrc.gov/reading-rm/adams.html (the Public Electronic Reading Room).

SCE&G

3

If you have any questions regarding this letter, please contact me at (404) 562-4600.

Sincerely,

/RA By R. Haag For/

Charles A. Casto, Director

Division of Reactor Safety

Docket No.:

50-395

License No.:

NPF-12

Enclosure: SDP Phase III Analysis w/Attachments

cc w/encl.:

R. J. White

Nuclear Coordinator (Mail Code 802)

S.C. Public Service Authority

Virgil C. Summer Nuclear Station

Electronic Mail Distribution

Kathryn M. Sutton, Esq.

Winston and Strawn

Electronic Mail Distribution

Henry J. Porter, Director

Division of Radioactive Waste Mgmt.

Dept. of Health and Environmental

Control

Electronic Mail Distribution

R. Mike Gandy

Division of Radioactive Waste Mgmt.

S.C. Department of Health and

Environmental Control

Electronic Mail Distribution

Thomas D. Gatlin, General Manager

Nuclear Plant Operations (Mail Code 303)

South Carolina Electric & Gas Company

Virgil C. Summer Nuclear Station

Electronic Mail Distribution

Ronald B. Clary, Manager

Nuclear Licensing (Mail Code 830)

South Carolina Electric & Gas Company

Virgil C. Summer Nuclear Station

Electronic Mail Distribution

Distribution w/encl.:

SCE&G

4

K. Cotton, NRR

L. Slack, RII

RIDSNRRDIPMIIPB

PUBLIC

OEMail

S. Sparks, RII

  • For Previous Concurrence See Attached Copy

OFFICE

RII:DRS

RII:DRS

RII:DRS

RII:DRP

RII:EICS

SIGNATURE

CRO

JHM2

RPS

KDL

CFE

NAME

COgle

JMoorman

BSchin

KLandis

CEvans

DATE

1/13/2005

1/13/2005

1/13/2005

1/13/2005

1/13/2005

E-MAIL COPY?

YES

NO YES

NO YES

NO YES

NO YES

NO YES

NO YES

NO

PUBLIC DOCUMENT

YES

NO YES

NO YES

NO YES

NO YES

NO YES

NO YES

NO

OFFICIAL RECORD COPY DOCUMENT NAME: E:\\Filenet\\ML050410097.wpd

SRA Analysis Number: SUM0403

Analysis Type: SDP Phase III

Inspection Report # : 2005006

Plant Name: V. C. Summer

Unit Number: 1

Enforcement Action #: EA-05-008

I.

Background - At V.C. Summer the Condensate Storage Tank (CST) is the normal

suction supply for the Emergency Feedwater System (standard Westinghouse design -

two motor driven and one turbine driven prime movers). Since the CST is not design to

withstand tornados, an alternate supply from the Service Water System was provided.

The piping interconnecting the two systems contains stagnant service water.

Microbiological tubercles are growing and have been growing for many years on the

inside diameter of these stagnant pipe segments.

The most flow-restricting passages in the system are in the flow control valves (IFV-

3531-EF, IFV-3541-EF, IFV-3551-EF, IFV-3536-EF, IFV-3546-EF, and IFV-3556-EF).

The flow control valves contain a cylindrical trim with several hundred orifices through

which the EFW flow to each steam generator passes. Based upon observing a spare

flow control valve trim, the orifices are widened with a countersink to about 0.125 inches

in diameter on the flow entry side and narrow to 0.049 inches in diameter on the flow

exit side. The total flow area of the orifices in a single valve trim is about 0.91 square

inches. There are no strainers in the EFW system that would prevent particles larger

than the these flow-restricting passages from entering the system. The NRC team

physically agitated samples of tubercles by rapidly shaking them in a container, to

simulate turbulent flow through an EFW pump, and found that most of the tubercle

pieces did not pulverize but instead broke into small solid pieces approximately 0.125 to

0.25 inches in diameter. The tubercle pieces were larger than the orifices and therefore

could potentially plug the orifices. The team calculated that, with an operating

differential pressure across a flow control valve of about 100 pounds per square inch,

the differential pressure across each orifice would be about 0.2 pounds. The team

found that the sample tubercle pieces were resistant to compressive forces, so that if

they became wedged into the orifices, they would likely be able to withstand much more

than 0.2 pounds of compressive forces without breaking up.

The original purchase specification for the EFW flow control valves (SP-620-044461-

000, dated October 16, 1974) had identified the process fluid as "cold condensate."

Therefore, these EFW valves had been specified for use with clean condensate water

and not for use with comparatively unclean SW which could contain silt and other debris

from the SW pond plus clam shells, tubercles, and other debris from the SW piping.

This mis-application of the purchased EFW flow control valves, which were designed for

clean condensate, to handle unclean SW in the plant represented inadequate design

control.

The licensee became aware of this potential blockage issue in 1986 and has had other

opportunities to identify the significance of this design vulnerability since that time.

Licensee corrective actions have been inadequate to resolve this design vulnerability.

Enclosure

2

Performance Deficiency - The licensees corrective actions in response to a deficiency in

the design of the EFW flow control valves was inadequate.

Specifically, the licensees design control failed to specify that the EFW flow control

valves were required to be able to handle relatively unclean SW without plugging.

Instead, the EFW flow control valves were specified to handle a process fluid of clean

cold condensate. Tubercles as well as other debris in the service water system could

plug the valves thereby resulting in a common mode failure of the EFW system.

Despite multiple opportunities, the licensees corrective action program failed to correct

the condition in a timely manner.

Exposure Time - 1 year

Date of Occurrence - Condition has existed for numerous years

II.

Safety Impact: WHITE

III.

Risk Analysis/Considerations

Assumptions

1.

Upon transfer of the Emergency Feedwater System (EFW) suction to the Service

Water System (SWS) the tubercles will plug the FCVs stopping sufficient flow to

any Steam Generator.

2.

Failure of the CST as the suction source for the Emergency Feedwater System

will cause a reactor trip during the ensuing plant shutdown. The failure of the

CST is estimated at 1E-7 failure/hour * 8760 hour0.101 days <br />2.433 hours <br />0.0145 weeks <br />0.00333 months <br />s/yr = 8.76E-4/yr. {INEEL

telecon of database search for equipment failure}

3.

For every reactor trip recovery of Main Feedwater is assumed to occur 90% of

the time. This is the estimate from the Phase 2 Screening Sheets due to plant

modifications that allow this. These modifications are not reflected in the

licensees full scope model.

4.

In the absence of the tubercles the failure of the Service Water System as a

suction for the Emergency Feedwater System is estimated at 1E-3 (a multi-train

system). Therefore, the non-conforming condition will be assumed to be the

delta CDF since the conforming case CDF is <<. (Unless specifically quantified

by computer models)

Enclosure

3

5.

Recovery of the Emergency Feedwater System, once transferred to the SWS

suction source will not be considered. The FCV cages are assumed to be

plugged to the point of insufficient flow to the Steam Generators. Operators

would be able to recognize that insufficient flow was going to the Steam

Generators.

6.

However, there would be no procedure direction, training or experience that

allow the operators to unplug the FCVs or provide a bypass around the plugged

valves. Also, there would be no equipment available to accomplish such a task.

7.

The CST function will be assumed to be lost at the medium wind speed/intensity

of a F2 tornado (135 mph). The frequency of all tornadoes of this intensity or

higher striking the site is estimated to be 6E-5/yr as extrapolated from Figure 3-2

Tornado Hazard Curve - Exceedance (page 3-6) contained in the June 1995

IPEEE High Winds Evaluation in response to Generic Letter 88-20, Supplement

4. All tornadoes assumed to cause loss of the CST function will also cause Loss

of Offsite Power without recovery.

8.

The critical piping segment from CST to EFW is estimated at 30 yards in length

with 10 welds. Failure consideration will be by Design and Construction Defects

(D&C) and Corrosion Attack (COR) mechanisms. From Table A-33, Pipe failure

Rates for Westinghouse Feedwater and Condensate Systems, of EPRI TR-

111880, Piping System Failure Rates and Rupture Frequencies for Use In Risk

Informed In-service Inspection Applications, the per foot or per weld failure

probability is:

COR = 8.47E-8 failure/yr/ft * 90 ft = 7.6E-6 failure/yr

D&C = 6.89E-7 failure/yr/weld * 10 welds = 6.89E-6 failure/yr

Total = 6.89E-6 + 7.6E-6 = 1.45E-5 failure/yr

9.

Based upon a review of the licensees safe shutdown strategy procedures

following a fire, it is assumed that when operators remain in the Main Control

Room (MCR), the train used for safe shutdown is assumed to be fully protected

either by 3 hour3.472222e-5 days <br />8.333333e-4 hours <br />4.960317e-6 weeks <br />1.1415e-6 months <br /> barrier, 1 hour1.157407e-5 days <br />2.777778e-4 hours <br />1.653439e-6 weeks <br />3.805e-7 months <br /> barrier with suppression or a separation of 20 feet

between trains. Those procedures presently indicate that the CST would be the

suction source for the protected EFW train unless the CST was expended.

Consequently, fire effects causing actuation of the alternate EFW suction source

(SWS) could only happen to the unprotected train. For the unprotected train to

affect the protected EFW train it would require a significant number of spurious

actuations, including pump start and two suction valves to open before the

protected train would be impacted. This is screened as not credible.

Enclosure

4

Premature transfer of the protected train suction to SWS will be considered credible due

to random events and a fully developed fire in the 7.2KV Switchgear Room (Train A) will

be used as the surrogate for this situation.

Possible spurious actuation of the SWS valves to the EFW suction source caused by

the fire will be considered for those cases where alternate shutdown (shutdown from

outside the MCR) is used. The fire in the Main Control Room will be used as the

surrogate to screen this situation. Also, in all fire accident sequences it is assumed the

licensee will execute a plant shutdown to cold shutdown before the CST volume is

expended.

PRA Model used for basis of the risk analysis: Combination of hand calculation,

modified Phase 2 Screening Sheet and SPAR run in the GEM mode.

Significant Influence Factor(s) [if any]: The failure of the SWS to EFW function is always

lost when called upon and the tornado severity at which the CST function as a suction

source to EFW is lost.

IV.

Calculations

BASE CASE - N/A

NON-CONFORMING CASE

a.

Internal Events

In the non-conforming case two broad conditions will be analyzed. First the full demand

spectrum from all initiating events normally included in an internal events model will be

considered. In this case the normal EFW suction path fails upon demand. The SPAR

model is used to calculate the delta CDF by setting the basic event EFW-XHE-XA-SWS,

OPERATOR FAILS TO ALIGN SW TO EFW, to always fail (TRUE). The model

quantification details are provided in Attachment 2. Summarizing the delta CDF was

4.7E-8/yr. Due to its small contribution it will be excluded from the quantification.

Second there is a special case not explicitly covered by the internals event model that

must be included. This involves the special case where the normal EFW suction source

is known to be out of service and requires plant shutdown with an ensuing reactor trip.

The failure of the CST and the failure the piping segments from the CST to EFW pump

suctions will be quantified to estimate this initiating event. As indicated in the

assumptions section, tank failure is set at 8.76E-4 and the piping segment failure is set

at 1.45E-5. The collective loss of the CST function is estimated at 8.9E-4/yr. This

represents the Initiating Event frequency.

Enclosure

5

To acquire the CCDP portion of the CDF the SPAR model in the GEM mode was

solved for the transient initiating event with:

EFW-TNK-FC-CST1 set to TRUE - this sets the CST to always fail this will later

be substituted with the new initiating event frequency that correlates to tank loss.

EFW-XHE-XA-SWS set to TRUE - this sets the Service Water System supply to

the EFW pumps to always fail - the performance deficiency.

MFW-XHE-XL-TRANS & MFW-XHE-XL-TRIP set to 0.1 - this provides a

possible site- specific use of MFW as a viable secondary side heat removal

mechanism (consistent with assumption 3).

The details of the computer run is provided as Attachment 3. In summary the derived

CCDP was 6.2E-3. The non-conforming CDF is 8.9E-4/yr * 6.2E-3 = 5.5E-6

Correlation with the Phase 2 Screening Sheets - The Phase 2 Screening Sheet for

Transients is solved using the 8.9E-4 IEL converted to a 3 and the EFW function set to

zero. The accident sequences are shown in Attachment 4 and result in a 6,6 & 7 or

White. This is consistent with the computerized calculation.

b.

External Events

Earthquake - Based upon the licensees IPEEE (page 13-2) estimated that the High

Confidence of Low Probability of Failure (HCLPF) for the Service Water Pond Dam was

0.22g while the CST was estimated at > 0.3g. Therefore, Service Water is estimated to

fail before the CST due to earthquake and will be excluded from quantification.

Fire - Fully developed fire with operators shutting down from the MCR - Compartment

1DA is the surrogate and considered the dominant fire since there are almost 40 ignition

sources capable of causing a fully developed fire and the compartment does not contain

a fixed suppression system. A fire of 16 minutes duration will be postulated to cause

operators to enact the mitigation strategy which includes inducing a Station Blackout

and re-establishing power to the B train via the B Emergency Diesel Generator.

Therefore, MFW recovery will not be considered. From 0609, Appendix F page F8-6 the

non-suppression probability of an electrical fire is 0.15. Possible mechanisms that could

cause EFW suction transference to SWS are spurious valve operations, spurious failure

of 2 of the 4 level transmitters or tank failure. For purposes of scoping only a single

valve or level transmitter failure will be quantified at 5E-7/hr for the valve (NUREG 4550)

+ 5E-6/hr for an instrument + 1E-7/hr for tank failure over a 24 hr mission time yields

1E-4. A conservative scoping quantification would be:

The fully developed fire frequency would be 2.3E-3 (fire frequency) * 1.5E-1

(suppression failure Pr) * 1E-4 (EFW transfer to SWS) = 3E-8

Enclosure

6

Fully developed fire with operators shutting down from outside the MCR. Use the MCR

fire as the screen. From SDP Appendix F, MCR fire frequency is 8E-3. Assuming a fire

of approximately 16 minutes would be needed to cause spurious operation of the

applicable valves, the manual suppression failure probability is estimated to be 0.02

(Appendix F page F8-6).

Partitioning the MCR into the critical panel portion that could impact these valves to be

1/4 of the MCR panels would provide an addition 0.25 reduction factor. Two valves in

the train to be used for shutdown from outside the MCR would have to change state in

this critical portion of the MCR panel. Appendix F page F-48 estimates a spurious

operation of 0.6. Calculating 8E-3 * 2E-2 * 2.5E-1 * 6E-1 * 6E-1 = 1.4E-5. This would

be a fully developed fire requiring MCR evacuation with subsequent failure of the EFW

System due to transferring onto the SWS suction source. However, even though not

procedurialized there would be adequate time to establish feed & bleed as a mitigation

strategy. Using a 2E-2 failure probability as representative of this strategy failing (1E-2

for the F&B portion and 1E-2 for the HPR portion), the CDF would screen at 3E-7.

These two scoping quantifications provide the perspective that the fire initiating event

would not be a major risk contributor for this performance deficiency.

Tornado - The CST was not designed to withstand a tornado or the effects of a tornado.

Using the exceedence probability for wind speeds at an F2 median frequency as the

initiating event, yields 6E-5/yr. SPAR was run in the GEM mode with:

the LOSP initiating event for severe weather set at 6E-5

EFW-TNK-FC-CST1 set to TRUE - this sets the CST to always fail due to a

tornado

EFW-XHE-XA-SWS set to TRUE - this sets the Service Water System supply to

the EFW pumps to always fail - the performance deficiency

The non-conforming CDF result was 1.4E-6. See Attachment 5 for th details of the

computer run.

As a sensitivity analysis for tornado wind speeds in excess of 150 mph (the upper end of

the F2 scale) correlates to a 1E-6 CDF..

Correlation with the Phase 2 Screening Sheets - The surrogate for external events is

LOSP. By altering the LOOP Screening Sheet from the Phase 2 Notebook to 6E-5 for

the initiating event correlates to a 4 for the IEL, the EFW function is set to zero and the

REC functions are set to zero. The accident sequences are shown in Attachment 6 and

resulted in a 6, 6, 7 & 7 or White and consistent with the computerized calculation.

Enclosure

7

External Events Summary - The external events analysis was to ascertain whether the

White result of the internal events is altered by the external events. Evaluation of the

external events contribution indicates that the risk significance is not sufficient to

increase internal events results.

DELTA CDF FOR EXPOSURE TIME

Since the exposure time is for one year there is no alteration of the delta CDF from the

previous section.

LERF CONSIDERATION

The dominant accident sequences involving this performance deficiency do not include

SGTR or ISLOCA as the initiating event. Therefore, the LERF contribution is

considered not to exceed the CDF risk bands.

V.

Conclusions/Recommendations - Risk increase over the base case was >1E-6 but <1E-

5.

VI.

Attachments

1.

Phase I Screening Sheets

2.

Sws to efw.wpd

3.

CCDP for Loss of CST as Initiating Event

4.

Phase 2 Screening Sheet - Trans Initiating Event

5.

Tornado SWS to EFW.wpd

6.

Phase 2 Screening Sheet - LOOP Initiating Event

Analyst:

W. Rogers

Date:

12/22/04

Reviewed By:

R. Bernhard

Date: 12/22/04

M. Franovich Date: 12/29/04 per telecon

Enclosure

SWS TO EFW.WPD

C O N D I T I O N A S S E S S M E N T

Code Version: 7:22 Model Version  : 2004/12/10

Project  : SUMM_3 Duration (hrs) : 8.8E+003

User Name  : IDAHO NATIONAL LABORATORY (INL) Total CCDP  : 1.4E-005

Event ID  : SWS-TO-EFW-OOS Total CDP  : 1.4E-005

Importance  : 4.7E-008

Description : Condition Assessment sws to efw failed for one year

BASIC EVENT CHANGES

Event Name Description Base Prob Curr Prob Type


---------------------------- --------- --------- ------

EFW-XHE-XA-SWS OPERATOR FAILS TO ALIGN SW T 1.0E-003 1.0E+000 TRUE

________________________________________________________________________________

SEQUENCE PROBABILITIES

Truncation : Cummulative : 100.0% Individual : 1.0%

Event Tree Name Sequence Name CCDP CDP Importance


------------------------ --------- --------- ----------

TRANS 17 4.5E-007 4.1E-007 3.4E-008

LDCA 20 7.8E-007 7.7E-007 6.0E-009

TRANS 16 5.0E-008 4.6E-008 3.7E-009

LOOP 17 3.3E-008 3.1E-008 1.6E-009

NOTE: Percent contribution to total Importance.

SEQUENCE LOGIC

Event Tree Sequence Name Logic


------------- ---------------------------------------------------

TRANS 17 /RPS EFW

MFW FAB

LDCA 20 /RPS EFW

FAB

TRANS 16 /RPS EFW

MFW /FAB

HPR

LOOP 17 /RPS /EPS

EFW-L FAB-L

Fault Tree Name Description


------------------------------------------------------

EFW EMERGENCY FEEDWATER

EFW-L SUMMER PWR B EMERGENCY FEEDWATER SYSTEM DURING LOOP

2004/12/21 11:10:02 page 1

2

Attachment 2

EPS EMERGENCY POWER

FAB FEED AND BLEED

FAB-L FEED AND BLEED DURING LOOP

HPR HPR PRESSURE RECIRCULATION

MFW MAIN FEEDWATER SYSTEM

RPS REACTOR TRIP

________________________________________________________________________________

SEQUENCE CUT SETS

Truncation: Cummulative: 100.0% Individual: 1.0%

Event Tree: TRANS CCDF: 4.5E-007

Sequence: 17

CCDF  % Cut Set Cut Set Events


--------- ----------------------------------------------------

1.6E-007 36.04 EFW-MDP-CF-FRAB EFW-TDP-FR

MFW-SYS-FC-TRIP HPI-XHE-XM-FB

4.1E-008 9.22 EFW-MDP-CF-FRAB EFW-TDP-TM

MFW-SYS-FC-TRIP HPI-XHE-XM-FB

4.0E-008 9.01 EFW-MDP-CF-FRAB EFW-TDP-FR

MFW-SYS-FC-TRANS HPI-XHE-XM-FB

3.4E-008 7.68 EFW-MDP-CF-FRAB EFW-TDP-FS-1

MFW-SYS-FC-TRIP HPI-XHE-XM-FB

2.7E-008 6.04 EFW-TNK-FC-CST1 MFW-SYS-FC-TRIP

HPI-XHE-XM-FB

2.5E-008 5.62 EFW-MDP-CF-FSAB EFW-TDP-FR

MFW-SYS-FC-TRIP HPI-XHE-XM-FB

1.0E-008 2.30 EFW-MDP-CF-FRAB EFW-TDP-TM

MFW-SYS-FC-TRANS HPI-XHE-XM-FB

8.6E-009 1.92 EFW-MDP-CF-FRAB EFW-TDP-FS-1

MFW-SYS-FC-TRANS HPI-XHE-XM-FB

7.6E-009 1.70 EFW-CKV-CF-DIS MFW-SYS-FC-TRIP

HPI-XHE-XM-FB

7.6E-009 1.70 EFW-CKV-CF-SUCT MFW-SYS-FC-TRIP

HPI-XHE-XM-FB

7.6E-009 1.70 EFW-CKV-CF-SGS MFW-SYS-FC-TRIP

HPI-XHE-XM-FB

7.4E-009 1.66 EFW-PMP-CF-ALL MFW-SYS-FC-TRIP

HPI-XHE-XM-FB

6.7E-009 1.51 EFW-TNK-FC-CST1 MFW-SYS-FC-TRANS

HPI-XHE-XM-FB

6.4E-009 1.44 EFW-MDP-CF-FSAB EFW-TDP-TM

MFW-SYS-FC-TRIP HPI-XHE-XM-FB

6.3E-009 1.40 EFW-MDP-CF-FSAB EFW-TDP-FR

MFW-SYS-FC-TRANS HPI-XHE-XM-FB

5.7E-009 1.28 EFW-MDP-CF-FRAB EFW-XHE-XR-TDP1

MFW-SYS-FC-TRIP HPI-XHE-XM-FB

5.3E-009 1.20 EFW-MDP-CF-FSAB EFW-TDP-FS-1

MFW-SYS-FC-TRIP HPI-XHE-XM-FB

2004/12/21 11:10:02 page 2

Attachment 2

3

Event Tree: LDCA CCDF: 7.8E-007

Sequence: 20

CCDF  % Cut Set Cut Set Events


--------- ----------------------------------------------------

3.5E-007 45.34 EFW-MDP-TM-1B EFW-TDP-FR

7.5E-008 9.66 EFW-MDP-TM-1B EFW-TDP-FS-1

7.0E-008 9.07 EFW-TDP-FR EFW-XHE-XR-MDP1B

3.6E-008 4.62 EFW-MDP-CF-FRAB EFW-TDP-FR

2.8E-008 3.63 EFW-PMP-FR-1A EFW-TDP-FR

2.7E-008 3.50 EFW-MDP-FR-1B EFW-TDP-FR

EFW-XHE-XL-MDPFRB

1.8E-008 2.32 EFW-TDP-TM EFW-XHE-XR-MDP1B

1.8E-008 2.29 EFW-MDP-FS-1B EFW-TDP-FR

EFW-XHE-XL-MDPFSB

1.5E-008 1.93 EFW-TDP-FS-1 EFW-XHE-XR-MDP1B

1.3E-008 1.61 EFW-MDP-TM-1B EFW-XHE-XR-TDP1

1.2E-008 1.55 DCP-BDC-LP-1B

9.2E-009 1.18 EFW-MDP-CF-FRAB EFW-TDP-TM

Event Tree: TRANS CCDF: 5.0E-008

Sequence: 16

CCDF  % Cut Set Cut Set Events


--------- ----------------------------------------------------

1.6E-008 32.19 HPR-XHE-XM EFW-MDP-CF-FRAB

EFW-TDP-FR MFW-SYS-FC-TRIP

4.1E-009 8.23 HPR-XHE-XM EFW-MDP-CF-FRAB

EFW-TDP-TM MFW-SYS-FC-TRIP

4.0E-009 8.05 HPR-XHE-XM EFW-MDP-CF-FRAB

EFW-TDP-FR MFW-SYS-FC-TRANS

3.4E-009 6.86 HPR-XHE-XM EFW-MDP-CF-FRAB

EFW-TDP-FS-1 MFW-SYS-FC-TRIP

2.7E-009 5.39 HPR-XHE-XM EFW-TNK-FC-CST1

MFW-SYS-FC-TRIP

2.5E-009 5.02 HPR-XHE-XM EFW-MDP-CF-FSAB

EFW-TDP-FR MFW-SYS-FC-TRIP

1.0E-009 2.06 HPR-XHE-XM EFW-MDP-CF-FRAB

EFW-TDP-TM MFW-SYS-FC-TRANS

8.6E-010 1.72 HPR-XHE-XM EFW-MDP-CF-FRAB

EFW-TDP-FS-1 MFW-SYS-FC-TRANS

7.6E-010 1.52 HPR-XHE-XM EFW-CKV-CF-SGS

MFW-SYS-FC-TRIP

7.6E-010 1.52 HPR-XHE-XM EFW-CKV-CF-DIS

MFW-SYS-FC-TRIP

7.6E-010 1.52 HPR-XHE-XM EFW-CKV-CF-SUCT

MFW-SYS-FC-TRIP

7.4E-010 1.49 HPR-XHE-XM EFW-PMP-CF-ALL

MFW-SYS-FC-TRIP

6.7E-010 1.35 HPR-XHE-XM EFW-TNK-FC-CST1

MFW-SYS-FC-TRANS

2004/12/21 11:10:02 page 3

Attachment 2

4

6.4E-010 1.28 HPR-XHE-XM EFW-MDP-CF-FSAB

EFW-TDP-TM MFW-SYS-FC-TRIP

6.3E-010 1.25 HPR-XHE-XM EFW-MDP-CF-FSAB

EFW-TDP-FR MFW-SYS-FC-TRANS

5.7E-010 1.14 HPR-XHE-XM EFW-MDP-CF-FRAB

EFW-XHE-XR-TDP1 MFW-SYS-FC-TRIP

5.3E-010 1.07 HPR-XHE-XM EFW-MDP-CF-FSAB

EFW-TDP-FS-1 MFW-SYS-FC-TRIP

Event Tree: LOOP CCDF: 3.3E-008

Sequence: 17

CCDF  % Cut Set Cut Set Events


--------- ----------------------------------------------------

9.5E-009 29.09 EFW-MDP-CF-FRAB EFW-TDP-FR

HPI-XHE-XM-FB

2.4E-009 7.44 EFW-MDP-CF-FRAB EFW-TDP-TM

HPI-XHE-XM-FB

2.0E-009 6.20 EFW-MDP-CF-FRAB EFW-TDP-FS-1

HPI-XHE-XM-FB

2.0E-009 6.05 EFW-MDP-TM-1B EFW-TDP-FR

EPS-DGN-FR-1A HPI-XHE-XM-FB

2.0E-009 6.05 EFW-MDP-TM-1A EFW-TDP-FR

EPS-DGN-FR-1B HPI-XHE-XM-FB

1.6E-009 4.87 EFW-TNK-FC-CST1 HPI-XHE-XM-FB

1.5E-009 4.53 EFW-MDP-CF-FSAB EFW-TDP-FR

HPI-XHE-XM-FB

4.5E-010 1.37 EFW-CKV-CF-SUCT HPI-XHE-XM-FB

4.5E-010 1.37 EFW-CKV-CF-DIS HPI-XHE-XM-FB

4.5E-010 1.37 EFW-CKV-CF-SGS HPI-XHE-XM-FB

4.4E-010 1.34 EFW-PMP-CF-ALL HPI-XHE-XM-FB

4.2E-010 1.29 EFW-MDP-TM-1B EFW-TDP-FS-1

EPS-DGN-FR-1A HPI-XHE-XM-FB

4.2E-010 1.29 EFW-MDP-TM-1A EFW-TDP-FS-1

EPS-DGN-FR-1B HPI-XHE-XM-FB

4.0E-010 1.21 EFW-TDP-FR EFW-XHE-XR-MDP1B

EPS-DGN-FR-1A HPI-XHE-XM-FB

4.0E-010 1.21 EFW-TDP-FR EFW-XHE-XR-MDP1A

EPS-DGN-FR-1B HPI-XHE-XM-FB

3.8E-010 1.16 EFW-MDP-CF-FSAB EFW-TDP-TM

HPI-XHE-XM-FB

3.7E-010 1.14 EFW-MDP-TM-1B EFW-TDP-FR

EPS-DGN-FS-1A HPI-XHE-XM-FB

3.7E-010 1.14 EFW-MDP-TM-1A EFW-TDP-FR

EPS-DGN-FS-1B HPI-XHE-XM-FB

3.4E-010 1.03 EFW-MDP-CF-FRAB EFW-XHE-XR-TDP1

HPI-XHE-XM-FB

________________________________________________________________________________

2004/12/21 11:10:02 page 4

Attachment 2

5

BASIC EVENTS (Cut Sets Only)

Event Name Description Curr Prob


--------------------------------------------- ---------

DCP-BDC-LP-1B DIVISION 1B 125VDC BUS DP-1B ED FAILS 4.8E-006

EFW-CKV-CF-DIS COMMON CAUSE FAILURE OF EFW PUMPS DISCHARGE C 6.8E-007

EFW-CKV-CF-SGS COMMON CAUSE FAILURE OF SGS EFW CHECK VALVES 6.8E-007

EFW-CKV-CF-SUCT COMMON CAUSE FAILURE OF EFW PUMPS SUCTION CHE 6.8E-007

EFW-MDP-CF-FRAB CCF FAILURE OF EFW MDPS TO RUN 5.1E-004

EFW-MDP-CF-FSAB CCF EFW MDP FAIL TO START 7.9E-005

EFW-MDP-FR-1B EFW MDP 1B FAILS TO RUN 5.2E-004

EFW-MDP-FS-1B EFW MDP 1B FAILS TO START 1.2E-003

EFW-MDP-TM-1A EFW MDP 1A UNAVAILABLE DUE TO TEST AND MAINTE 5.0E-003

EFW-MDP-TM-1B EFW MDP 1B UNAVAILABLE DUE TO TEST AND MAINTE 5.0E-003

EFW-PMP-CF-ALL COMMON CAUSE FAILURE OF EFW PUMPS 6.6E-007

EFW-PMP-FR-1A FAILURE OF EFW PUMP 1A TO RUN (PUMP UNIT ONLY 4.0E-004

EFW-TDP-FR EFW TDP FAILS TO RUN 2.8E-002

EFW-TDP-FS-1 EFW TDP FAILS TO START 6.0E-003

EFW-TDP-TM EFW TDP UNAVAILABLE DUE TO TEST AND MAINTENAN 7.2E-003

EFW-TNK-FC-CST1 FAILURE OF CONDENSATE STORAGE TANK 2.4E-006

EFW-XHE-XL-MDPFRB OPERATOR FAILS TO RECOVER EFW MDP 1B (FAILS T 7.5E-001

EFW-XHE-XL-MDPFSB OPERATOR FAILS TO RECOVER EFW MDP 1B (FAILS T 2.1E-001

EFW-XHE-XR-MDP1A OP FAILS TO RESTORE EFW MDP 1A AFTER T&M 1.0E-003

EFW-XHE-XR-MDP1B OP FAILS TO RESTORE EFW MDP 1B 1.0E-003

EFW-XHE-XR-TDP1 OP FAILS TO RESTORE EFW TDP AFTER T&M 1.0E-003

EPS-DGN-FR-1A DIESEL GENERATOR A FAILS TO RUN 2.1E-002

EPS-DGN-FR-1B DIESEL GENERATOR B FAILS TO RUN 2.1E-002

EPS-DGN-FS-1A DIESEL GENERATOR A FAILS TO START 4.0E-003

EPS-DGN-FS-1B DIESEL GENERATOR B FAILS TO START 4.0E-003

HPI-XHE-XM-FB OPERATOR FAILS TO INITIATE FEED AND BLEED COO 2.0E-002

HPR-XHE-XM OPERTATOR FAILS TO INITIATE HPR 2.0E-003

MFW-SYS-FC-TRANS MFW IS UNAVAILABLE (TRANSIENT INTIATOR) 2.0E-001

MFW-SYS-FC-TRIP MFW IS UNAVAILABLE (TRANSIENT INTIATOR) 8.0E-001

2004/12/21 11:10:02 page 5

Attachment 2

CCDP FOR LOSS OF CST FUNCTION AS THE INITIATING EVENT

I N I T I A T I N G E V E N T A S S E S S M E N T

Code Ver : 7:22

Fam  : SUMM_3 Model Ver : 2004/12/10

User : IDAHO NATIONAL LABORATORY (INL) Init Event: IE-TRANS

Ev ID: TRANS-W-O-CST--SWAFW Total CCDP: 6.2E-003

Desc : Initiating Event Assessment

BASIC EVENT CHANGES

Event Name Description Base Prob Curr Prob Type


---------------------------- --------- --------- ------

EFW-TNK-FC-CST1 FAILURE OF CONDENSATE STORAG 2.4E-006 1.0E+000 TRUE

EFW-XHE-XA-SWS OPERATOR FAILS TO ALIGN SW T 1.0E-003 1.0E+000 TRUE

IE-LDCA LOSS OF DC POWER BUS 1A INIT 2.5E-003 +0.0E+000

IE-LLOCA LARGE LOSS OF COOLANT ACCIDE 5.0E-006 +0.0E+000

IE-LOCCW LOSS OF COMPONENT COOLING WA 2.0E-004 +0.0E+000

IE-LOOP LOSS OF OFFSITE POWER 3.3E-002 +0.0E+000

IE-LOSW LOSS OF SERVICE WATER INITIA 4.0E-004 +0.0E+000

IE-MLOCA MEDIUM LOSS OF COOLANT ACCID 4.0E-005 +0.0E+000

IE-RHR-CLDIS-V ISLOCA OCCURS WITH REACTOR A 1.0E+000 +0.0E+000

IE-RHR-HLDIS-V ISLOCA OCCURS WITH REACTOR A 1.0E+000 +0.0E+000

IE-RHR-SUC-V ISLOCA OCCURS WITH REACTOR A 1.0E+000 +0.0E+000

IE-SGTR STEAM GENERATOR TUBE RUPTURE 4.0E-003 +0.0E+000

IE-SI-CLDIS-V ISLOCA OCCURS WITH REACTOR A 1.0E+000 +0.0E+000

IE-SI-HLDIS-V ISLOCA OCCURS WITH REACTOR A 1.0E+000 +0.0E+000

IE-SLOCA SMALL LOSS OF COOLANT ACCIDE 4.0E-004 +0.0E+000

IE-TRANS TRANSIENT 7.0E-001 1.0E+000

MFW-XHE-XL-TRANS OPERATOR FAILS TO RECOVER MF 1.0E+000 1.0E-001

MFW-XHE-XL-TRIP OPERATOR FAILS TO RECOVER MF 1.0E+000 1.0E-001

________________________________________________________________________________

SEQUENCE PROBABILITIES

Truncation : Cummulative : 100.0% Individual : 1.0%

Event Tree Name Sequence Name CCDP %Cont


------------------------ --------- -----

TRANS 17 5.9E-003

TRANS 16 2.3E-004

SEQUENCE LOGIC

Event Tree Sequence Name Logic


------------- ---------------------------------------------------

TRANS 17 /RPS EFW

MFW FAB

TRANS 16 /RPS EFW

MFW /FAB

HPR

2004/12/21 10:06:37 page 1

Attachment 3

2

Fault Tree Name Description


------------------------------------------------------

EFW EMERGENCY FEEDWATER

FAB FEED AND BLEED

HPR HPR PRESSURE RECIRCULATION

MFW MAIN FEEDWATER SYSTEM

RPS REACTOR TRIP

________________________________________________________________________________

SEQUENCE CUT SETS

Truncation: Cummulative: 100.0% Individual: 1.0%

Event Tree: TRANS CCDP: 5.9E-003

Sequence: 17

CCDP  % Cut Set Cut Set Events


--------- ----------------------------------------------------

5.5E-003 92.92 MFW-SYS-FC-TRIP MFW-XHE-XL-TRIP

HPI-XHE-XM-FB1

4.0E-004 6.73 MFW-SYS-FC-TRANS MFW-XHE-XL-TRANS

HPI-XHE-XM-FB

Event Tree: TRANS CCDP: 2.3E-004

Sequence: 16

CCDP  % Cut Set Cut Set Events


--------- ----------------------------------------------------

1.6E-004 71.03 HPR-XHE-XM MFW-SYS-FC-TRIP

MFW-XHE-XL-TRIP

4.0E-005 17.76 HPR-XHE-XM MFW-SYS-FC-TRANS

MFW-XHE-XL-TRANS

4.3E-006 1.92 MFW-SYS-FC-TRIP MFW-XHE-XL-TRIP

RHR-MDP-CF-FSAB

________________________________________________________________________________

BASIC EVENTS (Cut Sets Only)

Event Name Description Curr Prob


--------------------------------------------- ---------

HPI-XHE-XM-FB OPERATOR FAILS TO INITIATE FEED AND BLEED COO 2.0E-002

HPI-XHE-XM-FB1 OPERATOR FAILS TO INITIATE FEED AND BLEED COO 6.9E-002

HPR-XHE-XM OPERTATOR FAILS TO INITIATE HPR 2.0E-003

MFW-SYS-FC-TRANS MFW IS UNAVAILABLE (TRANSIENT INTIATOR) 2.0E-001

MFW-SYS-FC-TRIP MFW IS UNAVAILABLE (TRANSIENT INTIATOR) 8.0E-001

MFW-XHE-XL-TRANS OPERATOR FAILS TO RECOVER MFW (TRANSIENT INIT 1.0E-001

MFW-XHE-XL-TRIP OPERATOR FAILS TO RECOVER MFW (TRANSIENT INIT 1.0E-001

RHR-MDP-CF-FSAB COMMON CAUSE FAILURE OF RHR MDPS TO START 5.4E-005

2004/12/21 10:06:37 page 2

Attachment 3

Attachment 5

TORNADO TO SWS TO EFW.WPD

I N I T I A T I N G E V E N T A S S E S S M E N T

Code Ver : 7:22

Fam  : SUMM_3 Model Ver : 2004/12/10

User : IDAHO NATIONAL LABORATORY (INL) Init Event: IE-LOOP

Ev ID: LOOP-SEVERE-TEST Total CCDP: 1.4E-006

Desc : Initiating Event Assessment

BASIC EVENT CHANGES

Event Name Description Base Prob Curr Prob Type


---------------------------- --------- --------- ------

EFW-TNK-FC-CST1 FAILURE OF CONDENSATE STORAG 2.4E-006 1.0E+000 TRUE

EFW-XHE-XA-SWS OPERATOR FAILS TO ALIGN SW T 1.0E-003 1.0E+000 TRUE

IE-LDCA LOSS OF DC POWER BUS 1A INIT 2.5E-003 +0.0E+000

IE-LLOCA LARGE LOSS OF COOLANT ACCIDE 5.0E-006 +0.0E+000

IE-LOCCW LOSS OF COMPONENT COOLING WA 2.0E-004 +0.0E+000

IE-LOOP LOSS OF OFFSITE POWER 3.3E-002 6.0E-005

IE-LOSW LOSS OF SERVICE WATER INITIA 4.0E-004 +0.0E+000

IE-MLOCA MEDIUM LOSS OF COOLANT ACCID 4.0E-005 +0.0E+000

IE-RHR-CLDIS-V ISLOCA OCCURS WITH REACTOR A 1.0E+000 +0.0E+000

IE-RHR-HLDIS-V ISLOCA OCCURS WITH REACTOR A 1.0E+000 +0.0E+000

IE-RHR-SUC-V ISLOCA OCCURS WITH REACTOR A 1.0E+000 +0.0E+000

IE-SGTR STEAM GENERATOR TUBE RUPTURE 4.0E-003 +0.0E+000

IE-SI-CLDIS-V ISLOCA OCCURS WITH REACTOR A 1.0E+000 +0.0E+000

IE-SI-HLDIS-V ISLOCA OCCURS WITH REACTOR A 1.0E+000 +0.0E+000

IE-SLOCA SMALL LOSS OF COOLANT ACCIDE 4.0E-004 +0.0E+000

IE-TRANS TRANSIENT 7.0E-001 +0.0E+000

OEP-XHE-XL-NR01H OPERATOR FAILS TO RECOVER OF 5.3E-001 4.6E-001

OEP-XHE-XL-NR02H OPERATOR FAILS TO RECOVER OF 3.7E-001 3.6E-001

OEP-XHE-XL-NR03H OPERATOR FAILS TO RECOVER OF 2.8E-001 3.0E-001

OEP-XHE-XL-NR04H OPERATOR FAILS TO RECOVER OF 2.2E-001 2.5E-001

OEP-XHE-XL-NR05H OPERATOR FAILS TO RECOVER OF 1.9E-001 2.2E-001

OEP-XHE-XL-NR06H OPERATOR FAILS TO RECOVER OF 1.6E-001 2.0E-001

OEP-XHE-XL-NR07H OPERATOR FAILS TO RECOVER OF 1.4E-001 1.8E-001

OEP-XHE-XL-NR08H OPERATOR FAILS TO RECOVER OF 1.2E-001 1.6E-001

OEP-XHE-XL-NR09H OPERATOR FAILS TO RECOVER OF 1.1E-001 1.4E-001

OEP-XHE-XL-NR10H OPERATOR FAILS TO RECOVER OF 1.0E-001 1.3E-001

OEP-XHE-XL-NR10H2 OPERATOR FAILS TO RECOVER OF 2.7E-001 3.7E-001

OEP-XHE-XL-NR10H4 OPERATOR FAILS TO RECOVER OF 4.5E-001 5.2E-001

OEP-XHE-XL-NR11H OPERATOR FAILS TO RECOVER OF 9.5E-002 1.2E-001

OEP-XHE-XL-NR12H OPERATOR FAILS TO RECOVER OF 8.9E-002 1.1E-001

OEP-XHE-XL-NR13H OPERATOR FAILS TO RECOVER OF 8.5E-002 1.0E-001

OEP-XHE-XL-NR14H OPERATOR FAILS TO RECOVER OF 8.2E-002 9.7E-002

OEP-XHE-XL-NR15H OPERATOR FAILS TO RECOVER OF 7.9E-002 9.0E-002

OEP-XHE-XL-NR16H OPERATOR FAILS TO RECOVER OF 7.6E-002 8.4E-002

OEP-XHE-XL-NR17H OPERATOR FAILS TO RECOVER OF 7.4E-002 7.9E-002

OEP-XHE-XL-NR18H OPERATOR FAILS TO RECOVER OF 7.2E-002 7.4E-002

OEP-XHE-XL-NR19H OPERATOR FAILS TO RECOVER OF 7.1E-002 7.0E-002

OEP-XHE-XL-NR20H OPERATOR FAILS TO RECOVER OF 6.9E-002 6.6E-002

OEP-XHE-XL-NR21H OPERATOR FAILS TO RECOVER OF 6.8E-002 6.2E-002

OEP-XHE-XL-NR22H OPERATOR FAILS TO RECOVER OF 6.7E-002 5.9E-002

2004/12/21 16:57:15 page 1

2

Attachment 5

OEP-XHE-XL-NR23H OPERATOR FAILS TO RECOVER OF 6.6E-002 5.6E-002

OEP-XHE-XL-NR24H OPERATOR FAILS TO RECOVER OF 6.5E-002 5.3E-002

OEP-XHE-XL-NR30M OPERATOR FAILS TO RECOVER OF 6.6E-001 5.6E-001

OEP-XHE-XL-NR90M OPERATOR FAILS TO RECOVER OF 4.4E-001 4.0E-001

ZV-LOOP-EW-LAMBDA EXTREME WEATHER RELATED LOSS 2.3E-003 +0.0E+000

ZV-LOOP-GR-LAMBDA GRID RELATED LOSS OF OFFSITE 1.7E-002 +0.0E+000

ZV-LOOP-PC-LAMBDA PLANT CENTERED LOSS OF OFFSI 2.4E-003 +0.0E+000

ZV-LOOP-SC-LAMBDA SWITCHYARD CENTERED LOSS OF 8.7E-003 +0.0E+000

ZV-LOOP-SW-LAMBDA SEVERE WEATHER RELATED LOSS 3.0E-003 1.0E+000

SEQUENCE PROBABILITIES

Truncation : Cummulative : 100.0% Individual : 1.0%

Event Tree Name Sequence Name CCDP %Cont


------------------------ --------- -----

LOOP 17 1.2E-006

LOOP 14 1.1E-007

LOOP 18-45 4.3E-008

LOOP 16 3.8E-008

SEQUENCE LOGIC

Event Tree Sequence Name Logic


------------- ---------------------------------------------------

LOOP 17 /RPS /EPS

EFW-L FAB-L

LOOP 14 /RPS /EPS

EFW-L /FAB-L

/OPR-06H HPR

LOOP 18-45 /RPS EPS

EFW-B OPR-01H

DGR-01H

LOOP 16 /RPS /EPS

EFW-L /FAB-L

OPR-06H HPR-L

Fault Tree Name Description


------------------------------------------------------

DGR-01H OPERATOR FAILS TO RECOVER EMERGENCY DIESEL IN 1 HOUR

EFW-B SUMMER PWR B EMERGENCY FEEDWATER SYSTEM DURING SBO

EFW-L SUMMER PWR B EMERGENCY FEEDWATER SYSTEM DURING LOOP

EPS EMERGENCY POWER

FAB-L FEED AND BLEED DURING LOOP

HPR HIGH PRESSURE RECIRC

HPR-L HIGH PRESSURE RECIRC

OPR-01H OPERATOR FAILS TO RECOVER OFFSITE POWER IN 1 HOUR

2004/12/21 16:57:15 page 2

3

Attachment 5

OPR-06H OFFSITE POWER RECOVERY IN 6 HRS

RPS REACTOR SHUTDOWN

________________________________________________________________________________

SEQUENCE CUT SETS

Truncation: Cummulative: 100.0% Individual: 1.0%

Event Tree: LOOP CCDP: 1.2E-006

Sequence: 17

CCDP  % Cut Set Cut Set Events


--------- ----------------------------------------------------

1.2E-006 98.00 HPI-XHE-XM-FB

Event Tree: LOOP CCDP: 1.1E-007

Sequence: 14

CCDP  % Cut Set Cut Set Events


--------- ----------------------------------------------------

9.7E-008 89.00 HPR-XHE-XM /OEP-XHE-XL-NR06H

2.6E-009 2.41 /OEP-XHE-XL-NR06H RHR-MDP-CF-FSAB

Event Tree: LOOP CCDP: 4.3E-008

Sequence: 18-45

CCDP  % Cut Set Cut Set Events


--------- ----------------------------------------------------

1.4E-008 32.02 EPS-XHE-XL-NR01H OEP-XHE-XL-NR01H

EPS-DGN-CF-FRAB

1.1E-008 24.48 EPS-XHE-XL-NR01H OEP-XHE-XL-NR01H

EPS-DGN-FR-1A EPS-DGN-FR-1B

4.5E-009 10.41 EPS-XHE-XL-NR01H OEP-XHE-XL-NR01H

EPS-DGN-TM-1A EPS-DGN-FR-1B

4.5E-009 10.41 EPS-XHE-XL-NR01H OEP-XHE-XL-NR01H

EPS-DGN-TM-1B EPS-DGN-FR-1A

2.0E-009 4.62 EPS-XHE-XL-NR01H OEP-XHE-XL-NR01H

EPS-DGN-FS-1A EPS-DGN-FR-1B

2.0E-009 4.62 EPS-XHE-XL-NR01H OEP-XHE-XL-NR01H

EPS-DGN-FS-1B EPS-DGN-FR-1A

2.0E-009 4.57 EPS-XHE-XL-NR01H OEP-XHE-XL-NR01H

EPS-DGN-CF-FSAB

8.4E-010 1.97 EPS-XHE-XL-NR01H OEP-XHE-XL-NR01H

EPS-DGN-TM-1B EPS-DGN-FS-1A

8.4E-010 1.97 EPS-XHE-XL-NR01H OEP-XHE-XL-NR01H

EPS-DGN-TM-1A EPS-DGN-FS-1B

5.0E-010 1.16 EPS-XHE-XL-NR01H OEP-XHE-XL-NR01H

EPS-XHE-XR-DGN1A EPS-DGN-FR-1B

5.0E-010 1.16 EPS-XHE-XL-NR01H OEP-XHE-XL-NR01H

EPS-XHE-XR-DGN1B EPS-DGN-FR-1A

2004/12/21 16:57:15 page 3

4

Attachment 5

Event Tree: LOOP CCDP: 3.8E-008

Sequence: 16

CCDP  % Cut Set Cut Set Events


--------- ----------------------------------------------------

2.3E-008 61.34 HPR-XHE-XM OEP-XHE-XL-NR06H

1.5E-009 3.90 OEP-XHE-XL-NR06H EPS-DGN-FR-1A

RHR-MDP-TM-1B

1.5E-009 3.90 OEP-XHE-XL-NR06H EPS-DGN-FR-1B

RHR-MDP-TM-1A

6.3E-010 1.66 OEP-XHE-XL-NR06H RHR-MDP-CF-FSAB

6.2E-010 1.62 OEP-XHE-XL-NR06H EPS-DGN-FR-1A

CCW-HTX-TM-1B

________________________________________________________________________________

BASIC EVENTS (Cut Sets Only)

Event Name Description Curr Prob


--------------------------------------------- ---------

CCW-HTX-TM-1B CCW HTX 1B UNAVAILABLE DUE TO T&M 2.5E-003

EPS-DGN-CF-FRAB DIESEL GENERATOR COMMON CAUSE FAILS TO RUN 5.9E-004

EPS-DGN-CF-FSAB DIESEL GENERATOR COMMON CAUSE FAILS TO START 8.4E-005

EPS-DGN-FR-1A DIESEL GENERATOR A FAILS TO RUN 2.1E-002

EPS-DGN-FR-1B DIESEL GENERATOR B FAILS TO RUN 2.1E-002

EPS-DGN-FS-1A DIESEL GENERATOR A FAILS TO START 4.0E-003

EPS-DGN-FS-1B DIESEL GENERATOR B FAILS TO START 4.0E-003

EPS-DGN-TM-1A DIESEL GENERATOR 1A UNAVAILABLE DUE TO T&M 9.0E-003

EPS-DGN-TM-1B DIESEL GENERATOR 1B UNAVAILABLE DUE TO T&M 9.0E-003

EPS-XHE-XL-NR01H OPERATOR FAILS TO RECOVER EMERGENCY DIESEL IN 8.4E-001

EPS-XHE-XR-DGN1A OPERATOR FAILS TO RESTORE DIESEL GENERATOR A 1.0E-003

EPS-XHE-XR-DGN1B OPERATOR FAILS TO RESTORE DIESEL GENERATOR B 1.0E-003

HPI-XHE-XM-FB OPERATOR FAILS TO INITIATE FEED AND BLEED COO 2.0E-002

HPR-XHE-XM OPERTATOR FAILS TO INITIATE HPR 2.0E-003

OEP-XHE-XL-NR01H OPERATOR FAILS TO RECOVER OFFSITE POWER IN 1 4.6E-001

OEP-XHE-XL-NR06H OPERATOR FAILS TO RECOVER OFFSITE POWER IN 6 2.0E-001

RHR-MDP-CF-FSAB COMMON CAUSE FAILURE OF RHR MDPS TO START 5.4E-005

RHR-MDP-TM-1A RHR MDP 1A UNAVAILABLE DUE TO TEST AND MAINTE 6.0E-003

RHR-MDP-TM-1B RHR MDP 1B UNAVAILABLE DUE TO TEST AND MAINTE 6.0E-003

2004/12/21 16:57:15 page 4