ML050380333

From kanterella
Jump to navigation Jump to search
IR 05000321-03-006, 05000366-03-006, Fire Protection Mc 0612 Appendix B, Minor Questions Worksheet in Reference to Triennial Fire Protection Inspection for Hatch Nuclear Plant
ML050380333
Person / Time
Site: Hatch  Southern Nuclear icon.png
Issue date: 02/04/2005
From:
NRC/RGN-II
To:
References
FOIA/PA-2004-0277 IR-03-006
Download: ML050380333 (3)


See also: IR 05000321/2003006

Text

1--1%-Z

FIRE PROTECTION MC 0612 APPENDIX B

Minor Questions Worksheet

Reference:

Triennial Fire protection Inspection

Plant:

Hatch Nuclear Plant

Report No.: I R 50-321, 366/2003-006

Performance Deficiency: The licensee's fire protection program for ensuring the ability to safely

shutdown the plant during a fire was inadequate, in that:

The plant modification installed by Design Change Request (DCR)91-134 did not

implement the specified design input requirements for actuating the eleven safety relief

valves (SRVs) using one out of two logic taken twice in support of nuclear boiler over

pressure protection. The installed plant modification actuates the SRVs using two out of

two coincidence logic taken twice and one out of two coincidence logic taken twice.

The installed plant modification has resulted in a common mode failure of all eleven

safety relief valves from fire induced damage to two instrumentation cables.

The safe shutdown analysis report (SSAR), identified several cables that were relied

upon for SSD during a fire, but the licensee failed to provide the required physical

protection from fire damage. A common mode failure of all eleven safety relief valves

could occur because of fire induced damage to two instrumentation cables. These

cables were not physically protected in accordance with the requirements of 10 CFR 50

Appendix R, section III.G.2. Instead, the SSAR designated that operator actions would

be taken to prevent or mitigate the effects of the fire damage. However, the licensee did

not obtain NRC exemptions for these manual actions.

Additionally, the manual actions were not performed early enough during the fire event

to provide reasonable assurance that all eleven SRVs would not have spuriously opened

as a result of fire damage. Performance of these manual actions were encumbered by

a lack of adequate lighting to facilitate completion of the action. Also the terminal block

points were not adequately labeled in order to ensure that the operators could correctly

identify the terminal links that were to be removed.

Description

A circuit analysis of SRV 2B21-FO13F (Path 1) and SRV 2B21-F013G (Path 2) revealed

that the design objective of implementing a "one-out-of-two taken twice" logic had not

been installed for the SRVs. The logic installed for the SRVs was a "two-out-of-two

taken twice" logic in addition to a "one-out-of-two taken twicem logic. The coincident

logic implemented using trip unit master relays K31 OD and K335D could result in

spurious actuation of Group A SRVs for a fire in Fire Area 2104. Additionally, the trip

unit slave relays associated with the master relays will also energize the pilot valves of

group B and group C SRVs and result in opening these SRVs. Whenever a SRV lifts, it

will remain open until nuclear boiler pressure is reduced to about 85% of its

overpressure lift setpoint. However, because the instrument loops have failed high, the

trip unit master relays and the trip unit slave relays will continue to energize the pilot

..

...

-1.1

valve of the individual SRV and keep the SRV open. As a result, this failure mode

prevents the operators from manually controlling the Group A SRVs as is required per

the SSAR.

Failure to manually control the SRVs will challenge the heat capacity temperature limit

of the suppression pool and result in the loss of net positive suction head to the Core

Spray pumps which are used for mitigating this event. This loss of containment heat

removal would increase the large early release frequency (LERF) and could potentially

lead to containment failure.

Fire Procedure, AOP 34AB-X43-001-2, Version 10.8, dated May 28, 2003, stated in step

9.3.2.1 that: 'To prevent all eleven SRVs from opening simultaneously, open links BB-

10 in Panel 2H1 1-P927 and BB-10 in Panel 2H11 -P928."

The team noted that spurious

opening of all eleven SRVs should be considered a large loss of coolant accident

(LOCA), and that a LOCA should be prevented from occurring during a fire event to

comply with 10 CFR 50, Appendix R, Section lll.L. Section lll.L requires that, during a

post-fire shutdown, the reactor coolant system process variables (e.g., reactor vessel

pressure and water level) shall be maintained within those predicted for a loss of normal

alternating current power. Having all eleven SRVs opened during a fire would challenge

this requirement. The team determined that step 9.3.2.1 was sufficiently far back in the

procedure that it may not be completed in time to prevent potential fire damage to the

instrumentation cables of concem, which would result in all eleven SRVs spuriously

opening.

Licensing Basis/Requirements:

Operating License Condition 2.C.(3)(a), Fire Protection; Title 10 of the Code of Federal

Regulations, Part 50 (10 CFR 50), Appendix R; 10 CFR 50.48; Appendix A of Branch

Technical Position (BTP) Auxiliary and Power Conversion Systems Branch (APCSB)

9.5-1; related NRC Safety Evaluation Reports (SERs); the Hatch Nuclear Plant Updated

Final Safety Analysis Report (UFSAR); and plant Technical Specification (TS).

Minor Questions:

Question (1) Could the finding be reasonably viewed as a precursor to a significant event?

NO

_

__

__

_

_

Question (2) If left uncorrected, would the finding become a more significant safety concern?

NO

Question (3)

Does the finding relate to performance indicators that would have caused the Pi

to exceed a threshold?

NO

Question (4)

Is the finding associated with one of the below cornerstone attributes and does

the finding affect the associated cornerstone objective?

%IC

YES - The team determined that this finding was associated with the 'design

control, equipment performance, and procedure quality" attributes. It affected

the objective of the initiating events cornerstone to limit the likelihood of events

that challenge critical safety functions as well as the mitigating systems

cornerstone to ensure the availability, reliability, and capability of systems that

respond to initiating events, and is therefore greater than minor.

CORNERSTONE OBJECTIVES AND ATTRIBUTES:

REACTOR SAFETY CORNERSTONE

Initiating Events Cornerstone: OBJECTIVE: to limit the likelihood of those events that upset

plant stability and challenge critical safety functions during shutdown as well as power

operations.

Attributes:

Design Control:

Protection Against External Factors:

Configuration Control:

Equipment Performance

Procedure Quality

Human Performance:

Initial Design and Plant Modifications

Flood Hazard, Fire, Loss of Heat Sink,

Toxic Hazard, Switchyard Activities, Grid

Stability

Shutdown Equipment Lineup, Operating

Equipment Lineup

Availability, Reliability, Maintenance, Barrier

Integrity (SGTR, ISLOCA, LOCA (S,M,L),

Refueling/fuel handling equipment

Procedure Adequacy

Human Error

Mitigating Systems: OBJECTIVE: to ensure the availability, reliability, and capability of systems

that respond to initiating events to prevent consequences (i.e., core damage).

Attributes:

Design Control:

Protection Against External Factors:

Configuration Control:

Equipment Performance

Procedure Quality:

Human Performance:

Initial Design and Plant Modifications

Flood Hazard, Fire, Loss of Heat Sink,

Toxic Hazard, Seismic

Shutdown Equipment Lineup, Operating

_Equipment Lineup,_

Availability, Reliability

Operating (Post Event) Procedure (AOPs,

SOPs, EOPs); Maintenance and Testing

(Pre-event) Procedures

Human Error (Post Event), Human Error

(Pre-event)

Because the answer to Questions (4) was "YES," the finding should be considered greater than

minor. Go to MC-0609, App. A.