MONTHYEARML24008A0592024-01-0808 January 2024 E-mail Dated 1-8-2024 from R. Guzman to R. Reynolds Correct TS Page 204 for License Amendment No. 250 Adoption of TSTF-505 ML24008A2622024-01-0808 January 2024 Acceptance Review Determination for Relief Request I5R-12, Concerning Installation of a FSWOL on RPV Recirculation Inlet Nozzle N2E Safe End-to-Nozzle Dissimilar Metal Weld ML23268A0022023-09-22022 September 2023 NRR E-mail Capture - Constellation Energy Generation, LLC - Fleet Request - Acceptance of License Amendment Request to Adopt TSTF-264-A, Revision 0 ML23264A7992023-09-21021 September 2023 NRR E-mail Capture - Final RAI - Constellation Energy Generation, LLC Fleet Request License Amendment Request to Adopt TSTF-580, Revision 1 ML23255A2872023-09-12012 September 2023 NRR E-mail Capture - Constellation Energy Generation, LLC - Fleet Request - Acceptance of Alternative to Use the Successive Inspection Requirements of BWRVIP-75-A ML23237B3972023-08-24024 August 2023 NRR E-mail Capture - Constellation Energy Generation, LLC - Fleet Request - Acceptance of Alternative Request to Use Updated BWRVIP Guidelines ML23205A2432023-07-19019 July 2023 NRC Staff Follow-up Question on Audit Question 18 TSTF-505 and 50.69 Regulatory Audit (E-mail Dated 7/19/2023) (EPIDs L-2022-LLA-0185 and L-2022-LLA-0186) ML23207A0762023-07-14014 July 2023 EN 56557 - Update to Part 21 Report Re Potential Defect with Trane External Auto/Stop Emergency Stop Relay Card Pn: XI2650728-06 ML23205A2412023-07-11011 July 2023 NRC Staff Follow-up Comments on Audit Questions 6a, 6b, and 6c TSTF-505 and 50.69 Regulatory Audit (E-mail Dated 7/11/2023) (EPIDs L-2022-LLA-0185 and L-2022-LLA-0186) ML23205A2422023-07-11011 July 2023 NRC Staff Follow-up Comments on Audit Questions 17 and 19 TSTF-505 and 50.69 Regulatory Audit (E-mail Dated 7/11/2023) (EPIDs L-2022-LLA-0185 and L-2022-LLA-0186) ML23209A7692023-06-14014 June 2023 Draft Audit Results File TSTF-505 and 50.69 (E-mail Dated 6/14/2023) (EPIDs L-2022-LLA-0185 and L-2022-LLA-0186) ML23209A7672023-06-13013 June 2023 Share File Observations on Response to Question 06 and 22 TSTF-505 and 50.69 (E-mail Dated 6/13/2023) (EPIDs L-2022-LLA-0185 and L-2022-LLA-0186) ML23163A2292023-06-12012 June 2023 NRR E-mail Capture - Constellation Energy Generation, LLC - Fleet Request - Acceptance of License Amendment Request to Adopt TSTF-580, Revision 1 ML23159A0052023-06-0505 June 2023 56557-EN 56557 - Paragon - Redlined ML23149A0012023-05-29029 May 2023 Audit Agenda TSTF-505 and 50.69 (E-mail Dated 5/29/2023) (EPIDs L-2022-LLA-0185 and L-2022-LLA-0186) ML23142A0222023-05-22022 May 2023 Regulatory Audit Questions (PRA) TSTF-505 and 50.69 (E-mail Dated 5/22/2023) (EPIDs L-2022-LLA-0185 and L-2022-LLA-0186) ML23118A3882023-04-28028 April 2023 Regulatory Audit Questions TSTF-505 and 50.69 (E-mail Dated 4/28/2023) (EPIDs L-2022-LLA-0185 and L-2022-LLA-0186) ML23104A3472023-04-14014 April 2023 Verbal Authorization for Relief Request I5R-14, Proposed Alternative Associated with N2E Dissimilar Metal Weld Overlay Repair with Laminar Indication ML23093A1782023-04-0303 April 2023 E-mail from T. Loomis to R. Guzman Proposed Alternative to Utilize Specific Provisions of Code Case N-716-3 ML23090A1302023-03-31031 March 2023 Verbal Authorization for Relief Request I5R-11, Proposed Alternative Repair of Recirculation Inlet Nozzle N2E Dissimilar Metal Weld ML23087A2912023-03-28028 March 2023 Request for Additional Information (3/28/2023 E-mail) - Proposed Emergent I5R-11 Alternative Associated with a Weld Overlay on RPV Recirculation Nozzle N2E DM Weld ML23061A0522023-03-0202 March 2023 Request for Additional Information (3/2/2023 E-mail) - Proposed Alternative Associated with a Weld Overlay Repair to the Torus ML23047A3832023-02-15015 February 2023 (2-15-2023 Email from J. Nelson to R. Guzman) Long Island Power Authority and Long Island Lighting Company Request for Threshold Determination ML23033A0142023-02-0202 February 2023 E-mail Dated 2-2-2023 from R.Guzman to R.Reynolds Correction to Error in NMP1 TSTF-505 and 50.69 Audit Plan ML23019A3092023-01-19019 January 2023 Acceptance Review Determination License Amendment Request to Adopt 10 CFR 50.69 Categorization Process ML23019A3032023-01-19019 January 2023 Acceptance Review Determination License Amendment Requets to Adopt TSTF-505 ML23013A3332023-01-13013 January 2023 Acceptance Review Determination Proposed Alternative for Weld Overlay Repair to the Torus ML22354A2622022-12-20020 December 2022 NRR E-mail Capture - Constellation Energy Generation, LLC - Fleet Request - Acceptance of Request to Use Certain Provisions of the 2019 Edition of the ASME BPV Code, Section XI ML22342B1462022-11-21021 November 2022 NRR E-mail Capture - Acceptance Review for TSTF 295A ML22314A2262022-11-10010 November 2022 E-mail Dated 11/10/2022 Relief Request Associated with Pump Periodic Verification Tests of Core Spray System Pumps ML22301A0902022-10-28028 October 2022 NRR E-mail Capture - Constellation Energy Generation, LLC - Fleet Request - Acceptance of License Amendment Request to Adopt TSTF-301, Revision 2 ML22252A1522022-09-0909 September 2022 Acceptance Review Determination Partial Adoption of TSTF-568 to Revise TS 3.3.1 for Primary Containment Oxygen Concentration ML22207A0192022-07-26026 July 2022 (E-mail Dated 7/26/2022) Setup of Online Reference Portal for Revision to Alternative Source Term Calculation for MSIV and Non-MSIV Leakage ML22207A0122022-07-26026 July 2022 Acceptance Review Determination Revision to Alternative Source Term Analysis for Containment Leakage ML22200A0782022-07-19019 July 2022 NRR E-mail Capture - Constellation Energy Generation, LLC - Fleet Request to Use Honeywell Mururoa V4F1 R Supplied Air Suits ML22194A9412022-07-13013 July 2022 Request for Additional Information Relief Request CS-PR-02 (7/13/2022 e-mail) ML22173A0802022-06-22022 June 2022 E-mail Dated 6/22/2022, Acceptance of Requested License Amendment Request to Revise Surveillance Requirements to Reduce Number of Fast Starts of EDGs ML22075A0362022-03-16016 March 2022 Acceptance Review Determination - Relief Request CS-PR-02 Associated with Pump Periodic Verification Test of Core Spray System Pumps, E-mail Dated 3/16/2022 ML22041B5362022-02-10010 February 2022 NRR E-mail Capture - Constellation Energy Generation, LLC - Request for Additional Information Regarding Fleet License Amendment Request to Adopt TSTF-541 ML22020A0642022-01-13013 January 2022 NRR E-mail Capture - Exelon Generation Company, LLC - Request for Additional Information Regarding Proposed Fleet Alternative for Repair of Water Level Instrumentation Partial Penetration Nozzles ML21320A3472021-11-16016 November 2021 Request for Additional Information LAR to Revise TSs to Adopt TSTF-582, Revision 0 ML21306A3312021-11-0202 November 2021 Request for Additional Information Alternative Request GV-RR-10 (11/2/2021 e-mail) ML21301A0672021-10-28028 October 2021 NRR E-mail Capture - Exelon Generation Company, LLC - Acceptance of License Amendment Request to Adopt TSTF-541 ML21298A0912021-10-25025 October 2021 E-mail Dated 10/25/2021, Acceptance of Requested License Amendment Request to Adopt Technical Specification Task Force Traveler 582 ML21292A2122021-10-19019 October 2021 NRR E-mail Capture - NRC Notification to the State of New York Regarding a Nine Mile Point Nuclear Station, Unit 2 Amendment - Adopt TSTF-501, Rev. 1 ML21278A6872021-10-0505 October 2021 Acceptance Review Determination - Relief Request GV-RR-10 ML21256A1902021-09-10010 September 2021 NRR E-mail Capture - Exelon Generation Company, LLC - Request for Additional Information Regarding License Transfer Application ML21252A0482021-09-0707 September 2021 NRR E-mail Capture - Exelon Generation Company, LLC - Fleet Alternative Request for Repair of Water Level Instrumentation Partial Penetration Nozzles ML21215A3502021-08-0303 August 2021 NRR E-mail Capture - Exelon Generation Company, LLC - Acceptance of License Amendment Request to Adopt TSTF-554 ML21168A3462021-06-17017 June 2021 Acceptance of Requested Licensing Action License Amendment Request - Adoption of TSTF-501, Relocate Stored Fuel Oil and Lube Oil Volume Values to Licensee Control (EPID L-2021-LLA-0096) (Email) 2024-01-08
[Table view] |
Text
From: Peter Tam To: Farouk Baxter Date: 12/29/04 2:08PM
Subject:
Your Concern - Nine Mile Point Offsite Power System (TAC MC5106, MC5107)
Dear Mr. Baxter:
Your e-mail (below) came to my attention. I am the NRC Project Manager for Nine Mile Point.
Tommy Le, our Project Manager for Nine Mile Point License Renewal, had told you that your concern is not under the purview of license renewal, but is under the current operating reactor project management program. Let me affirm the accuracy of this statement.
We have discussed your concern with the licensee, and the licensee submitted a letter on November 10, 2004, to address this issue. You may find this letter under Accession No. ML043280420 in NRC's public document system. The NRC staff has been reviewing that letter on a schedule based on the safety significance of the issue. Our tentative target date to issue a Safety Evaluation of this issue is April 2005.
Please note that I am your sole contact at NRC regarding this issue. Should the review schedule change, or we need more information from you, I shall contact you. Otherwise, rest assured that we are still on track and on schedule to complete this review.
You did not request that your e-mail (below) and one dated 9/19/04 (attached, Accession No. ML043230428) be withheld from public disclosure. Accordingly, unless you provide appropriate reason to withhold these two e-mails, I shall put them in the public domain by January 7, 2005.
Peter S. Tam Senior Project Manager Project Directorate I Division of Licensing Project Management Office of Nuclear Reactor Regulation
>>> Farouk Baxter <faroukbax@earthlink.net> 12/14/04 10:10AM >>>
On September 18, 2004, I submitted some safety concerns related to the Nine Mile Point License Renewal application, where I identified that Nine Mile Point did not meet applicable NRC regulations.
On October 18, 2004, I wrote to inquire the status and disposition of my comments.
On October 27, 2004, I received a phone call from Tommy Le indicating that the concerns I had raised were outside his area of expertise, and had been directed to another department for review and resolution.
It is now three months since submittal of my comments, and I have yet to hear how the safety concerns identified have been addressed and dispositioned.
Farouk D. Baxter, PE Expert/Specialist - Nuclear Power Plant Electrical Systems 23 PIlgrims Path Sudbury, MA 01776 (978)443-2914 On Sep 19, 2004, at 7:20 PM, NINEMILEPOINTEIS NINEMILEPOINTEIS wrote:
> Thank you for your comments on the Nine Mile Point License Renewal.
> Your comments will be forwarded to the appropriate NRC personnel and a
> follow up response will be sent back to you in the near future.
CC: Gordon Hunegs; James Trapp; Jennifer Davis; Narinder Trehan; Ngoc Le Mail Envelope Properties (41D300BA.8BA : 10 : 20510)
Subject:
Your Concern - Nine Mile Point Offsite Power System (TAC MC5106, MC5107)
Creation Date: 12/29/04 2:08PM From: Peter Tam Created By: PST@nrc.gov Recipients Action Date & Time kp1_po.KP_DO Delivered 12/29/04 02:08PM GKH CC (Gordon Hunegs) Opened 12/29/04 02:34PM JMT1 CC (James Trapp) Opened 12/29/04 02:09PM owf4_po.OWFN_DO Delivered 12/29/04 02:08PM NBL CC (Ngoc Le) Opened 12/29/04 03:27PM earthlink.net Transferred 12/29/04 02:08PM faroukbax (Farouk Baxter) nrc.gov owf2_po.OWFN_DO Delivered 12/29/04 02:08PM NKT CC (Narinder Trehan) Opened 12/30/04 09:47AM nrc.gov twf4_po.TWFN_DO Delivered 12/29/04 02:08PM BJD1 CC (Jennifer Davis)
Post Office Delivered Route kp1_po.KP_DO 12/29/04 02:08PM owf4_po.OWFN_DO 12/29/04 02:08PM earthlink.net owf2_po.OWFN_DO 12/29/04 02:08PM nrc.gov twf4_po.TWFN_DO 12/29/04 02:08PM nrc.gov Files Size Date & Time MESSAGE 4499 12/29/04 02:08PM ML0432304280.pdf 444590 12/29/04 02:03PM Options Auto Delete: No Expiration Date: None Notify Recipients: Yes Priority: Standard Reply Requested: No Return Notification: None Concealed
Subject:
No Security: Standard To Be Delivered: Immediate Status Tracking: Delivered & Opened