October 2004 Monthly Operating Report for Davis-Besse Nuclear Power Station Unit 1
ML043210161
Person / Time
Site: Davis Besse 
(NPF-003)
Issue date: 11/12/2004
From: Allen B
FirstEnergy Nuclear Operating Co
To:
Document Control Desk, Office of Nuclear Reactor Regulation
References
310700
Download: ML043210161 (6)


Text

FistEnergy Davis-Besse Nuclear Power Station 5501 North State Route 2 Oak Harbor, Ohio 43449.9760 Docket No. 50-346 License No. NPF-3 Serial No. 3107 November 12, 2004 United States Nuclear Regulatory Commission Document Control Desk Washington, D.C. 20555-0001 Monthly Operating Report, October 2004 Davis-Besse Nuclear Power Station Unit I Ladies and Gentlemen:

Enclosed is a copy of the Monthly Operating Report for the Davis-Besse Nuclear Power Station for the month of October 2004.

Please direct questions to Brian D. Boles, Manager - Plant Engineering, at (419) 321-7302.

Very truly yours, Barry S. Allen Director - Site Operations Davis-Besse Nuclear Power Station AWB/s Enclosures cc: DB-1 NRC/NRR Senior Project Manager DB-I Senior Resident Inspector NRC Region III Administrator

_j'-2>F

m Docket No. 50-346 License No. NPF-3 Serial No. 3107 Distribution bcc: B. S. Allen, DB-2101 A. W. Bless, DB 3065 B. D. Boles, DB-1056 D. R. Converse, DB-3310 J. J. Grabnar, DB-3210 L. J. Kovach, DB-1056 A. R. Miller, DB-1056 G. C. Wilson, DB-2103 D. R. Wuokko, DB-3065 CNRB Administrator M. E. O'Reilly, GO-18 R. Runo, GO-14 T. Schneider, A-GO-17 F. Heizer, PUCO B. Lewis, Utility Data Institute, Inc.

R. Schomaker, Framatome American Nuclear Insurers INPO Records Center Ohio EPA - DERR Compliance Utility Radiological Safety Board

Docket No. 50-346 License No. NPF-3 Serial No. 3107 Enclosure I Page 1 of 1 COMMITMENT LIST The following list identifies those actions committed to by the Davis-Besse Nuclear Power Station in this document. Any other actions discussed in the submittal represent intended or planned actions by Davis-Besse. They are described only as information and are not regulatory commitments. Please notify the Director - Performance Improvement (419-321-7181) at Davis-Besse of any questions regarding this document or associated regulatory commitments.

Commitments Due Date None N/A

Docket No. 50-346 License No. NPF-3 Serial No. 3107 Monthly Operating Report for October 2004 (two pages to follow)

OPERATING DATA REPORT DOCKET NO.

UNIT NAME DATE COMPLETED BY TELEPHONE 50-0346 Davis-Besse Unit 1 11/01104 A. R. Miller 419-321-7824 REPORTING PERIOD October, 2004 YEAR TO DATE MONTH CUMULATIVE 1 Design Electrical Rating (MWe-Net).

The nominal net electrical output of the unit specified by the utility and used for the purpose of plant design.

2 Maximum Dependable Capacity (MWe-Net).

The gross electrical output as measured at the output terminals of the turbine-generator during the most restrictive seasonal conditions minus the normal station service loads.

3 Number of Hours the Reactor Was Critical.

The total number of hours during the gross hours of the reporting period that the reactor was critical.

4 Number of Hours the Generator Was On Line.

(Also called Service Hours). The total number of hours during the gross hours of the reporting period that the unit operated with breakers closed to the station bus.

The sum of the hours the generator was on line plus the total outage hours should equal the gross hours In the reporting period.

5 Unit Reserve Shutdown Hours.

The total number of hours during the gross hours of the reporting period that the unit was removed from service for economic or similar reasons but was available for operation.

906 882 745.0 745.0 0.0 5,348.0 5,165.0 0.0 152,982.3 150,202.1 5,532.0 6 Net Electrical Energy (MWH).

The gross electrical output of the unit measured at the output terminals of the turbine-generator minus the normal station service loads during the gross hours of the reporting period, expressed In mega.

watt hours. Negative quantities should not be used.

662,232 4.470,192 123,601,990

UNIT SHUTDOWNS DOCKET NO.

50-346 UNIT NAME Davis-Besse #1 DATE 11101104 COMPLETED BY A.R. Miller REPORTING PERIOD:

October, 2004 TELEPHONE (419) 321-7824 NO.

DATE TYPE DURATION REASON (1)

METHOD OF CAUSE/CORRECTIVE ACTIONS F: FORCED (HOURS)

SHUTTING

&: SCHEDULED DOWN (2)

COMMENTS No Unit Shutdowns.

SUMMARY

The reactor was at 100% power for the majority of the month. On October 23, the unit downpowered to approximately 90% to conduct Main Turbine Control Valve, Combined Intermediate Valves Testing. However, on October 24, due to problems identified with the Electric Hydraulic Controls Pump (discharge filter differential pressure high alarm) it was decided to return the plant to 100% power and perform the valve testing at a later time. On October 31, the unit downpowered to approximately 90% for Main Turbine Control Valve, Combined Intermediate Valves Testing.

(1) Reason:

A-Equipment Failure (Explain)

B-Maintenance or Test C-Refueling D-Regulatory Restriction E-Operator Training & License Exam F-Administrative G-Operational Error (Explain)

H-Other (Explain)

(2)

Method:

1-Manual 2-Manual Trip/Scram 3-Automatic Trip/Scram 4-Continuation 5-Other (Explain)