Letter Sequence Other |
---|
|
|
MONTHYEARML0419702532004-06-28028 June 2004 RAI, Security Plan Sections 1-9 (TAC MC2913 and MC2914) Project stage: RAI DCL-04-085, Response to NRC Requests for Additional Information Regarding Physical Security Plan Sections 1 Through 19 Per NRC Secured Facsimile Dated June 22. 2004 and NRC Letter Dated June 28. 20042004-07-0808 July 2004 Response to NRC Requests for Additional Information Regarding Physical Security Plan Sections 1 Through 19 Per NRC Secured Facsimile Dated June 22. 2004 and NRC Letter Dated June 28. 2004 Project stage: Response to RAI ML0419801192004-07-0909 July 2004 Request for Additional Information Training and Qualification Plan Project stage: RAI ML0421904472004-07-23023 July 2004 RAI, Safeguards Contingency Plan and Section 9.4.1 of the Physical Security Plan, Project stage: RAI DCL-04-092, Response to Nrc'S Request for Additional Information Regarding the Plant Physical Security Plan. Training and Qualification Plan Per NRC Letter Dated July 9. 20042004-07-23023 July 2004 Response to Nrc'S Request for Additional Information Regarding the Plant Physical Security Plan. Training and Qualification Plan Per NRC Letter Dated July 9. 2004 Project stage: Request DCL-04-101, Response to Nrc'S Request for Additional Information Re Plant Safeguards Contingency Plan & Section 9.4.1 of the Physical Security Plan, Per NRC Letter Dated July 23, 20042004-08-0505 August 2004 Response to Nrc'S Request for Additional Information Re Plant Safeguards Contingency Plan & Section 9.4.1 of the Physical Security Plan, Per NRC Letter Dated July 23, 2004 Project stage: Request DCL-04-102, Response to Nrc'S Request for Additional Information Re Plant Physical Security Plan and Safeguards Contingency Plan - Closeout of Open Items2004-08-13013 August 2004 Response to Nrc'S Request for Additional Information Re Plant Physical Security Plan and Safeguards Contingency Plan - Closeout of Open Items Project stage: Request ML0425900182004-09-10010 September 2004 Implementation Status of Independent Spent Fuel Storage Installation Interim Compensatory Measures Project stage: Other DCL-04-120, ISFSI - 10-Day Response to NRC Letter, Dated September 10. 2004, Implementation Status of Independent Spent Fuel Storage Installation Interim Compensatory Measures.2004-09-23023 September 2004 ISFSI - 10-Day Response to NRC Letter, Dated September 10. 2004, Implementation Status of Independent Spent Fuel Storage Installation Interim Compensatory Measures. Project stage: Other ML0431800052004-10-28028 October 2004 Administrative Change to Facility Operating License in Conjunction with the Commission Order EA-03-086 Regarding Revised Design Basis Threat... Project stage: Other 2004-07-09
[Table View] |
|
---|
Category:Letter
MONTHYEARIR 05000275/20230042024-02-0909 February 2024 Integrated Inspection Report 05000275/2023004 and 05000323/2023004 ML24002B1802024-01-29029 January 2024 LRA Audit Plan DCL-24-010, Nuclear Material Transaction Report for New Fuel2024-01-29029 January 2024 Nuclear Material Transaction Report for New Fuel ML24018A0152024-01-29029 January 2024 License Renewal Application Review Schedule Letter ML24017A2492024-01-24024 January 2024 Letter to Neil Peyron, Chairman, Tule River Tribe, Re. Diablo Canyon ML24024A1752024-01-24024 January 2024 Letter to Tribal Council San Luis Obispo County Chumash Indians on Section 106 Consultation and Scoping Process for the Environmental Review of Diablo Canyon Nuclear Plant, Unit 1 and 2 License Renewal Application ML24003A8902024-01-24024 January 2024 Letter to P. Gerfen - Diablo Canyon Notice of Intent to Conduct Scoping and Prepare an Environmental Impact Statement ML24012A1582024-01-24024 January 2024 Letter to Hon. Violet Sage Walker, Chairwoman Northern Chumash Tribal Council on Section 106 Consultation and Scoping Process for the Environmental Review of Diablo Canyon Nuclear Plant, Unit 1 and 2 License Renewal Application ML24012A0062024-01-24024 January 2024 Achp Scoping Letter for Diablo Canyon License Renewal ML24012A0552024-01-24024 January 2024 Letter to J. Polanco, Shpo, on Request to Initiate Section 106 Consultation and Scooping Process for the Environmental Review of Diablo Canyon Nuclear Plant, Unit 1 and 2 License Renewal Application ML24024A1562024-01-24024 January 2024 Letter to Hon. Gabe Frausto, Coastal Band of Chumash Indians on Section 106 Consultation and Scoping Process for the Environmental Review of Diablo Canyon Nuclear Plant, Unit 1 and 2 License Renewal Application ML24024A1652024-01-24024 January 2024 Letter to Hon. Mona Olivas Tucker, Yak Tityu Tityu Yak Tilhini Northern Chumas Indians on Section 106 Consultation and Scoping Process for the Environmental Review of Diablo Canyon Nuclear Plant, Unit 1 and 2 License Renewal Application ML24024A1612024-01-24024 January 2024 Letter Hon. Gary Pierce, Salian Tribe of Monterey and San Luis Obispo Counties on Section 106 Consultation and Scoping Process for the Environmental Review of Diablo Canyon Nuclear Plant, Unit 1 and 2 License Renewal Application ML24012A0362024-01-24024 January 2024 Request to Initiate Section 106 Consultation and Scoping Process for the Environmental Review License Renewal Application DCL-24-009, Nuclear Material Transaction Report for New Fuel2024-01-17017 January 2024 Nuclear Material Transaction Report for New Fuel DCL-24-008, Schedule Considerations for Review of the DCPP License Renewal Application2024-01-17017 January 2024 Schedule Considerations for Review of the DCPP License Renewal Application DCL-24-004, Supplement to License Amendment Request 23-01 Revision to Technical Specifications to Adopt Risk-Informed Completion Times TSTF-505, Revision 2, Provide Risk-Informed Extended Completion Times - RITSTF Initiative 4b2024-01-15015 January 2024 Supplement to License Amendment Request 23-01 Revision to Technical Specifications to Adopt Risk-Informed Completion Times TSTF-505, Revision 2, Provide Risk-Informed Extended Completion Times - RITSTF Initiative 4b IR 05000275/20230112024-01-12012 January 2024 NRC License Renewal Phase 1 Inspection Report 05000275/2023011 DCL-23-129, Nuclear Material Transaction Report for New Fuel2023-12-27027 December 2023 Nuclear Material Transaction Report for New Fuel ML23326A0122023-12-21021 December 2023 12-21-23 Letter to the Honorable Byron Donalds from Chair Hanson Responds to Letter Regarding 2.206 Petition to Close Diablo Canyon Nuclear Power Plant, Unit 1 ML23341A0042023-12-19019 December 2023 LRA Acceptance Letter ML23352A2342023-12-18018 December 2023 Notification of Age-Related Degradation Inspection (05000275/2024014 and 05000323/2024014) and Request for Information DCL-23-122, Request for Exemption from Enhanced Weapons, Firearms Background Checks, and Security Event Notifications Implementation2023-12-14014 December 2023 Request for Exemption from Enhanced Weapons, Firearms Background Checks, and Security Event Notifications Implementation DCL-23-128, Emergency Plan Update2023-12-13013 December 2023 Emergency Plan Update ML23355A0952023-12-0808 December 2023 License Renewal Application Online Reference Portal DCL-23-125, Core Operating Limits Report for Unit 1 Cycle 252023-12-0606 December 2023 Core Operating Limits Report for Unit 1 Cycle 25 ML23291A2702023-11-28028 November 2023 Letter to Nakia Zavalla, Shpo, the Santa Ynez Band of Chumash Indians; Re., Diablo Canyon ISFSI Initiating Section 106 Consultation ML23320A2442023-11-28028 November 2023 Letter to Kerri Vera, Director of Department of Environmental Protection, Tule River Tribe; Re., Diablo Canyon ISFSI Initiating Section 106 Consultation ML23325A1382023-11-27027 November 2023 ISFSI Tribal Letter to San Luis Obispo County Chumash Indians ML23325A1322023-11-27027 November 2023 ISFSI Tribal Letter to Salian Tribe of Montgomery, San Luis Obispo ML23325A1332023-11-27027 November 2023 ISFSI Tribal Letter to Yak Tityu Tityu Northern Chumash Indians ML23307A0062023-11-27027 November 2023 ISFSI Tribal Letter to Northern Chumash Tribal Council ML24003A7242023-11-27027 November 2023 Independent Safety Committee; Diab Lo Canyon Nuclear Power Plant Operations, Thirty-Third Annual Report on the Safety ML23325A1292023-11-27027 November 2023 ISFSI Tribal Letter to Coastal Band of Chumash ML23320A1502023-11-17017 November 2023 Individual Notice of Consideration of Issuance of Amendment to Facility Operating License, Proposed No Significant Hazards Consideration Determination, & Opportunity for Hearing (Exigent Circumstances) (EPID L-2023-LLA-0155) - LTR DCL-23-121, Supplement to License Amendment Request 23-03, Revision to Technical Specification3.7.8, Auxiliary Saltwater System2023-11-16016 November 2023 Supplement to License Amendment Request 23-03, Revision to Technical Specification3.7.8, Auxiliary Saltwater System ML23296A0982023-11-15015 November 2023 Notification and Request for Consultation Regarding Pacific Gas and Electric Diablo Canyon Independent Spent Fuel Storage Installation Material License Renewal Request (Docket Number: 72-26) DCL-23-120, License Amendment Request 23-03 Revision to Technical Specification 3.7.8, Auxiliary Saltwater (Asw) System2023-11-14014 November 2023 License Amendment Request 23-03 Revision to Technical Specification 3.7.8, Auxiliary Saltwater (Asw) System ML23293A1052023-11-14014 November 2023 Receipt and Availability of License Renewal Application IR 05000275/20230032023-11-13013 November 2023 Integrated Inspection Report 05000275/2023003 and 05000323/2023003 ML23311A2082023-11-0909 November 2023 Reassignment of U.S. Nuclear Regulatory Commission Branch Chief in the Division of Operating Reactor Licensing for Plant Licensing Branch IV DCL-23-118, License Renewal Application2023-11-0707 November 2023 License Renewal Application ML23318A2102023-10-31031 October 2023 Independent Safety Committee; Thirty-Third Annual Report on the Safety of Diablo Canyon Nuclear Power Plant Operations DCL-2023-520, Discharge Self-Monitoring at Diablo Canyon Power Plant (DCPP)2023-10-19019 October 2023 Discharge Self-Monitoring at Diablo Canyon Power Plant (DCPP) DCL-23-103, Independent Spent Fuel Storage Installation - Withdrawal of License Amendment Request 22-01, Request for Approval of Alternative Security Measures for Early Warning System2023-10-13013 October 2023 Independent Spent Fuel Storage Installation - Withdrawal of License Amendment Request 22-01, Request for Approval of Alternative Security Measures for Early Warning System IR 05000275/20240152023-10-10010 October 2023 Information Request for the Cybersecurity Baseline Inspection, Notification to Perform Inspection (050002752024015 and 050003232024015) 2024-02-09
[Table view] Category:License-Operating (New/Renewal/Amendments) DKT 50
MONTHYEARML23012A2172023-02-0909 February 2023 Issuance of Amendment Nos. 244 and 245 Revision to Technical Specifications to Adopt TSTF-569, Revision 2, Revise Response Time Testing Definition ML21242A2162022-12-21021 December 2022 Issuance of Amendment Nos. 243 and 244 Technical Specifications and Revised License Conditions for the Permanently Defueled Condition (EPID: L-2020-LLA-0261 ML22326A1632022-11-21021 November 2022 Licensee Comment Email on Post-Shutdown Emergency Plan Amendment ML22187A0252022-11-16016 November 2022 Issuance of Amendment Nos. 242 and 243 Revision to Emergency Plan for Post-Shutdown and Permanently Defueled Condition ML22221A1682022-09-0606 September 2022 Issuance of Amendment Nos. 241 and 242 Revision to Technical Specifications to Adopt TSTF-577, Revised Frequencies for Steam Generator Tube Inspection ML21160A1742021-09-0202 September 2021 Issuance of Amendment Nos. 239 and 240 Revising Technical Specification 3.2.1, Heat Flux Hot Channel Factor (Fq(Z)), to Implement Methodology from WCAP-17661, Revision 1 ML21188A3452021-07-0808 July 2021 Issuance of Amendment No. 238 Revision to TS 3.7.8, Auxiliary Saltwater (Asw) System (Emergency Circumstances) ML20218A2762020-09-11011 September 2020 Issuance of Amendment Nos. 237 and 239 to Relocate Technical Specification 5.3, Unit Staff Qualifications, to Updated Final Safety Analysis Report ML20235R6352020-08-31031 August 2020 Issuance of Amendment Nos. 236 and 238 Revision to Technical Specification 3.7.5, Auxiliary Feedwater (AFW) System, Exigent Circumstances ML20232C6482020-08-17017 August 2020 Lochbaum Public Comment 1 on Exigent LAR to Modify TS 3.7.5, Auxiliary Feedwater System ML19196A3092019-08-21021 August 2019 Issuance of Amendment Nos. 233 and 235 Regarding Revision to Emergency Plan to Change Staffing and Extend Staff Augmentation Times for Emergency Response Organization Positions ML17212A3792017-09-25025 September 2017 Diablo Canyon Power Plant, Units 1 and 2 - Issuance of Amendment Nos. 231 and 233 Re: Emergency Action Level Scheme Change (CAC Nos. MF8528 and MF8529) ML17012A2462017-04-27027 April 2017 Issuance of Amendments Revise Licensing Bases to Adopt Alternative Source Term ML17018A3412017-02-23023 February 2017 Issuance of Amendments Revise Technical Specification 3.4.12, Low Temperature Overpressure Protection (LTOP) System, ML16330A6722017-01-0505 January 2017 Issuance of Amendment Nos. 228 and 230, Revise Technical Specifications to Adopt TSTF-523, Generic Letter 2008-01, Managing Gas Accumulation ML16139A0082016-12-21021 December 2016 Issuance of Amendment Nos. 227 and 229, Digital Replacement of the Process Protection System Portion of the Reactor Protection System and Engineered Safety Features Actuation System DCL-16-061, Supplement to License Amendment Request 15-03, Application of Alternative Source Term.2016-06-0909 June 2016 Supplement to License Amendment Request 15-03, Application of Alternative Source Term. DCL-16-061, Diablo Canyon, Units 1 and 2 - Supplement to License Amendment Request 15-03, Application of Alternative Source Term.2016-06-0909 June 2016 Diablo Canyon, Units 1 and 2 - Supplement to License Amendment Request 15-03, Application of Alternative Source Term. ML16117A2522016-05-19019 May 2016 Issuance of Amendment Nos. 226 and 228, Revise Minimum Flow Value Specified in Technical Specification 3.4.1, RCS Pressure, Temperature, and Flow Departure from Nucleate Boiling (DNB) Limits ML16035A4412016-04-14014 April 2016 Issuance of Amendment Nos. 225 and 227, Adopt National Fire Protection Association NFPA 805, Performance-Based Standard for Fire Protection for LWR Generating Plants (2001 Edition) ML16055A3592016-03-0909 March 2016 Issuance of Amendment Nos. 224 and 226, Revise Updated Final Safety Analysis Report for Beacon Power Distribution Monitoring System Methodology and TS 5.6.5 (COLR) Paragon and Nexus Methodologies ML16032A0062016-02-19019 February 2016 Redacted, Issuance of Amendment Nos. 223 and 225, Revise UFSAR Section 15.4.2.2 to Incorporate Pressurizer Filling Analysis for Major Rupture of a Main Feedwater Pipe Accident Into Licensing Basis ML15029A1732016-01-0505 January 2016 ISFSI - Issuance of Amendment Nos. 222, 224, and 4, Authorize Use of Preemption Authority Granted Under Provisions of Section 161A of the Atomic Energy Act of 1954, as Amended (CAC MF2809, MF2810, and L24991) ML15281A1642015-12-0303 December 2015 Issuance of Amendment Nos. 221 and 223, Revise Updated Final Safety Analysis Report and Approval to Perform Fuel Assembly Structural Analyses That Considers Application of Leak Before Break ML15245A5422015-09-30030 September 2015 Issuance of Amendment Nos. 220 and 222, Request to Revise Operating License Condition Related to Cyber Security Plan Milestone H Full Implementation Date ML15204A2222015-08-27027 August 2015 Issuance of Amendment Nos. 219 and 221, Adopt Technical Specifications Task Force Traveler TSTF-432, Revision 1, Change in Technical Specification End States (WCAP-16294) ML15162A8822015-07-0101 July 2015 Issuance of Amendment Nos. 218 and 220, Revise Surveillance Requirements in TS 3.8.1, AC Sources, Related to Diesel Generator Testing ML14042A1932014-02-27027 February 2014 Issuance of Amendment Nos. 217 and 219, Editorial and Clarifying Changes to Technical Specification (TS) 3.7.10, Control Room Ventilation System (CRVS) and TS 5.6.5, Core Operating Limits Report (COLR) (TAC MF1959-MF1960) ML13178A0052013-09-0505 September 2013 Issuance of Amendment Nos. 216 and 218, Adoption of TSTF-421-A, Revision to RCP Flywheel Inspection Program (WCAP-15666), Using Consolidated Line Item Improvement Process ML12352A0672013-01-31031 January 2013 Issuance of Amendment Nos. 215 and 217, Revise Technical Specifications Related to Auxilary Feedwater System to Adopt TSTF-245, Rev. 1, TSTF-340, Rev. 3, TSTF-412, Rev. 3, and TSTF-439, Rev. 2 ML12345A3792013-01-0909 January 2013 Issuance of Amendment Nos. 214 and 216, Revise Final Safety Analysis Report Update Section 4.3.2.2 to Allow Use of Beacon Power Distribution Monitoring System ML12338A0202012-12-0404 December 2012 Issuance of Amendment Nos. 213 and 215, Revise Technical Specification 3.7.10, Control Room Ventilation System (Crvs), Required Action A.1 Completion Time (Emergency Circumstances) ML1207903382012-03-29029 March 2012 Issuance of Amendment Nos. 211 and 213, Revise Technical Specifications to Adopt TSTF-163, Rev. 2, Minimum Vs. Steady State Voltage and Frequency, and Final Safety Analysis Report Update ML1116402742011-07-15015 July 2011 Issuance of Amendment Nos. 210 and 212, License Amendment Request to Revise License Condition and Approve Cyber Security Plan and Associated Implementation Schedule ML1020100842011-01-24024 January 2011 Issuance of Amendment Nos. 209 and 211, Revise Technical Specification 3.4.15, RCS Leakage Detection Instrumentation, Operability Requirements and Actions ML1025304432010-09-29029 September 2010 Issuance of Amendment Nos. 208 and 210, Revise FSAR Update to Include Damping Values for Seismic Design/Analysis - Integrated Head Assembly ML1018901172010-07-30030 July 2010 Issuance of Amendment Nos. 207 and 209, Revise FSAR Update to Include Critical Damping Value for Structural Dynamic Qualification of Control Rod Drive Mechanism Pressure Housings ML0925405442009-09-17017 September 2009 Issuance of Amendment No. 208, Revise Technical Specification 3.7.1, Main Steam Safety Valves (Mssvs) for Unit 2 Cycle 15 (Exigent Circumstances) ML0921203992009-08-19019 August 2009 Issuance of Amendment Nos. 206 and 207, Modify Technical Specifications to Adopt TSTF-511, Eliminate Working Hour Restrictions from TS 5.2.2 to Support Compliance with 10 CFR Part 26 ML0907701812009-04-29029 April 2009 License Amendment, Issuance of Amendment Nos. 205 and 206, Revise TS 3.3.1, Reactor Trip System (RTS) Instrumentation, to Delete High-Negative Rate Trip Function ML0906308082009-03-30030 March 2009 Issuance of Amendment Nos. 204 and 205, Revise TS 3.7.5, Auxiliary Feedwater (AFW) System, and TS 3.7.6, Condensate Storage Tank (CST) and Fire Water Storage Tank (Fwst) ML0900803872009-01-15015 January 2009 Issuance of Amendment Nos. 203 and 204, Changes to Technical Specification 5.5.16, Containment Leakage Rate Testing Program ML0834601732008-12-31031 December 2008 Issuance of Amendment No. 202 and 203 Increase the Completion Times for Required Actions Related to Technical Specifications 3.5.2, the ECCS, and 3.6.6, CS & CS (Tac MD7512 & MD7513) ML0832906092008-12-23023 December 2008 Issuance of Amendment Nos. 201 and 202, Adoption of Changes to Standard Technical Specifications Under Technical Specifications Task Force (TSTF)-448 ML0824102622008-10-30030 October 2008 Issuance of Amendment Nos. 200 and 201, Technical Specifications Change to Relocate Surveillance Test Intervals to a Licensee-Controlled Program (Risk-Informed Initiative 5b) ML0732400062008-01-0808 January 2008 Units, 1 and 2, Issuance of Amendment Nos. 198 and 199, Revise Technical Specification (TS) 3.3.2, TS 5.5.9, and TS 5.6.10 to Support Replacement of Steam Generators ML0719102142007-07-11011 July 2007 License Amendments, Incorporated the Mitigation Strategies Required by Section B.5.b. of Commission Order EA-02-026 ML0713707312007-06-26026 June 2007 Issuance of License Amendment Nos. 197 and 198 TS 5.5.16, Containment Leakage Rate Testing Program, for Consistency with 10 CFR 50.55a(g)(4) ML0703500512007-04-17017 April 2007 Issuance of Amendment Nos. 195 and 196 TS 3.4.1 Reactor Coolant System Pressure, Temperature, & Flow Departure from Nucleate Boiling Limits & TS 5.6.5 Core Operating Limits Report. ML0704405032007-03-19019 March 2007 License Amendment, Deletion of License Condition Section 2.G in Facility Operating License (CLIIP Item) 2023-02-09
[Table view] |
Text
SAFEGUARDS INFORMATION October 28, 2004 Mr. Gregory M. Rueger Senior Vice President Generation and Chief Nuclear Officer Pacific Gas and Electric Company Diablo Canyon Nuclear Power Plant, Units 1 and 2 P. O. Box 3 Avila Beach, CA 93424
SUBJECT:
DIABLO CANYON NUCLEAR POWER PLANT, UNITS 1 AND 2 -
ADMINISTRATIVE CHANGE TO FACILITY OPERATING LICENSES IN CONJUNCTION WITH THE COMMISSION ORDER EA-03-086 REGARDING REVISED DESIGN BASIS THREAT (DBT); AND REVISIONS TO PHYSICAL SECURITY PLAN, TRAINING AND QUALIFICATION PLAN, AND SAFEGUARDS CONTINGENCY PLAN (TAC NOS. MC2913 AND MC2914)
Dear Mr. Rueger:
By letter dated April 29, 2004, Pacific Gas and Electric Company submitted a supplemental response in accordance with Order EA-03-086, the Order requiring compliance with the revised design basis threat, dated April 29, 2003, (DBT Order) for the Diablo Canyon Nuclear Power Plant, Units 1 and 2.Section III.A of the DBT Order required licensees to revise physical security plans (PSPs), training and qualification plans (T&Q Plans), and safeguards contingency plans (SCPs) to provide protection against the revised DBT set forth in to the DBT Order. These revised plans, along with an implementation schedule, were required to be submitted to the Nuclear Regulatory Commission (NRC or the Commission) for review and approval no later than April 29, 2004.
In the revised security plans for Diablo Canyon Nuclear Power Plant, Units 1 and 2, you included information related to the independent spent fuel storage installation (ISFSI) co-located at the site. The DBT Order did not require this information to be included in the revised security plans for Diablo Canyon Nuclear Power Plant, Units 1 and 2. However, Order EA 104, dated October 16, 2002, required licensees to comply with the requirements, set forth in an attachment to the Order, that described the compensatory measures necessary to protect the ISFSI as a result of the heightened threat environment following the September 11, 2001, terrorist attacks. On September 10, 2004, the NRC staff requested that you clarify whether the information provided in the revised security plans for Diablo Canyon Nuclear Power Plant, Units 1 and 2 related to the ISFSI, modified the response you provided to Order EA-02-104.
NOTICE: Enclosure 2 contains Safeguards Information. Upon separation from Enclosure 2, this letter and Enclosure 1 are DECONTROLLED.
SAFEGUARDS INFORMATION
G. M. Rueger By letter dated September 23, 2004, you indicated that the actions you have taken in response to Order EA-02-104 remain essentially unchanged and therefore, there is no decrease in effectiveness of the protective measures in place for the ISFSI. The effectiveness of these security provisions will continue to be the subject of NRC review and inspection.
The NRC staffs review of the Diablo Canyon Nuclear Power Plant, Units 1 and 2 PSP, SCP, and T&Q Plan submitted in your letter dated April 28, 2004, as supplemented on July 8, 2004, July 23, 2004, August 4, 2004, August 5, 2004, August 11, 2004, August 13, 2004, September 8, 2004, October 1, 2004, October 8, 2004, October 14, 2004, and October 19, 2004, has focused on ensuring the necessary programmatic elements are contained in these plans in order to provide high assurance that activities involving special nuclear material are not inimical to the common defense and security and do not constitute an unreasonable risk to the public health and safety.
The NRC staff has determined that subject to subsequent inspection and evaluation, these plans contain the necessary programmatic elements that, when effectively implemented, will provide the required high assurance that Diablo Canyon Nuclear Power Plant, Units 1 and 2 will be protected against the revised DBT. The NRC staff, therefore, approves the for Diablo Canyon Nuclear Power Plant, Units 1 and 2. However, ultimately the effectiveness of these plans will be judged on your ability to meet regulatory requirements through facility implementing procedures and site practices. As such your facility implementing procedures and practices will continue to be subject to future NRC review and inspection, including NRC-conducted, force-on-force exercises.
In addition, the NRC staff noted that your PSP included alternatives to certain requirements of Title 10 of the Code of Federal Regulations (10 CFR) Section 73.55. In each case, the NRC staff found that the alternative measures provide an equivalent level of protection to that of the associated requirement and meet the high assurance objective of 10 CFR 73.55(a). The NRC staff, therefore, approves the alternatives shown in the table below. The NRC staffs evaluation is discussed further in the enclosed Safety Evaluation (SE).
Approved Alternatives to the Requirements of 10 CFR Part 73 SE Section PSP Alternative to Description Section 10 CFR 3.6.2 6.2 73.55(c)(3) Isolation Zones 3.9.4.3 9.4.3 73.55(d)(4) Protected Area (PA) vehicle search requirements 3.9.4.4 9.4.4 73.55(d)(1) PA personnel search requirements 3.9.5.2 9.5 73.55(d)(1) PA access control requirements 73.55(d)(4) 3.10.1 10.1 73.55(c)(5) PA illumination requirements 3.13.1 14.1 73.55(c)(1) Temporary reclassification of Vital 73.55(d)(7)(i)(B) Areas to PA status (devitalization)
G. M. Rueger Finally, consistent with the DBT Order, conforming administrative changes to Facility Operating Licenses (FOLs) are required to ensure implementation of DBT Order requirements.
Therefore, administrative license changes to FOL Nos. DPR-80 and DPR-82 are being made to incorporate the reference to the revised PSP, SCP, and T&Q Plan required by the DBT Order.
These changes comply with the standards and requirements of the Atomic Energy Act of 1954, as amended, and the Commission's rules and regulations set forth in 10 CFR Chapter I.
Please replace the enclosed pages to your FOLs as indicated in Enclosure 1.
A copy of our SE with regard to your security plans (designated as Safeguards Information) is provided in Enclosure 2.
Sincerely,
/RA/
John A. Nakoski, Chief Security Plan Review Team Project Directorate II Division of Licensing Project Management Office of Nuclear Reactor Regulation Docket Nos. 50-275 and 50-323
Enclosures:
- 1. Administrative Change to FOL Nos. DPR-80 and DPR-82
- 2. SE Regarding the Security Plans (SAFEGUARDS INFORMATION) cc w/encl 1 only: See mailing list 1 cc w/encls 1 and 2: Mr. Ron Todaro
G. M. Rueger Finally, consistent with the DBT Order, conforming administrative changes to Facility Operating Licenses (FOLs) are required to ensure implementation of DBT Order requirements.
Therefore, an administrative license change to FOL Nos. DPR-80 and DPR-82 is being made to incorporate the reference to the revised PSP, SCP, and T&Q Plan required by the DBT Order.
These changes comply with the standards and requirements of the Atomic Energy Act of 1954, as amended, and the Commission's rules and regulations set forth in 10 CFR Chapter I.
Please replace the enclosed pages to your FOLs as indicated in Enclosure 1.
A copy of our SE with regard to your security plans (designated as Safeguards Information) is provided in Enclosure 2.
Sincerely,
/RA/
John A. Nakoski, Chief Security Plan Review Team Project Directorate II Division of Licensing Project Management Office of Nuclear Reactor Regulation Docket Nos. 50-275 and 50-323
Enclosures:
- 1. Administrative Change to FOL Nos. DPR-80 and DPR-82
- 2. Safety Evaluation Regarding the Security Plans (SAFEGUARDS INFORMATION) cc w/encl 1 only: See mailing list 1 cc w/encls 1 and 2: Mr. Ron Todaro Distribution w/o Enclosure 2 PUBLIC SPRT R/F OGC ACRS EPeyton GShukla SDembek HBerkow GHill (4) DLPM DPR TBoyce AHowell, RIV Accession No.:
OFFICE SPRT/TL SPRT/PM SPRT/LA SPRT/PL OGC NSIR/ SC NRR/SC NAME JPeralta SMorris JNakoski DATE 10/24/04 10/24/04 10/24/04 10/24/04 10/24/0 10/28/04 10/28/04 4
OFFICIAL RECORD COPY
Diablo Canyon Power Plant, Units 1 and 2 cc w/o encl.:
NRC Resident Inspector Mr. David H. Oatley, Vice President Diablo Canyon Power Plant and General Manager c/o U.S. Nuclear Regulatory Commission Diablo Canyon Power Plant P.O. Box 369 P.O. Box 56 Avila Beach, CA 93424 Avila Beach, CA 93424 Sierra Club San Lucia Chapter City Editor c/o Henriette Groot The Tribune 1000 Montecito Road 3825 South Higuera Street Cayucos, CA 93430 P.O. Box 112 San Luis Obispo, CA 93406-0112 Ms. Nancy Culver San Luis Obispo Mr. Ed Bailey, Chief Mothers for Peace Radiologic Health Branch P.O. Box 164 State Department of Health Services Pismo Beach, CA 93448 P.O. Box 997414 (MS 7610)
Sacramento, CA 95899-7414 Chairman San Luis Obispo County Board of Mr. James D. Boyd, Commissioner Supervisors California Energy Commission Room 370 1516 Ninth Street (MS 31)
County Government Center Sacramento, CA 95814 San Luis Obispo, CA 93408 Mr. James R. Becker, Vice President Mr. Truman Burns Diablo Canyon Operations Mr. Robert Kinosian and Station Director California Public Utilities Commission Diablo Canyon Power Plant 505 Van Ness, Room 4102 P.O. Box 3 San Francisco, CA 94102 Avila Beach, CA 93424 Diablo Canyon Independent Safety Mr. Gregory M. Rueger Committee Senior Vice President, Generation and ATTN: Robert R. Wellington, Esq. Chief Nuclear Officer Legal Counsel Pacific Gas & Electric Company 857 Cass Street, Suite D Diablo Canyon Power Plant Monterey, CA 93940 P.O. Box 3 Avila Beach, CA 93424 Regional Administrator, Region IV U.S. Nuclear Regulatory Commission Harris Tower & Pavillion 611 Ryan Plaza Drive, Suite 400 Arlington, TX 76011-8064 Richard F. Locke, Esq.
Pacific Gas & Electric Company P.O. Box 7442 San Francisco, CA 94120
PACIFIC GAS AND ELECTRIC COMPANY DOCKET NO. 50-275 DIABLO CANYON NUCLEAR POWER PLANT, UNIT 1 ADMINISTRATIVE LICENSE CHANGE TO FACILITY OPERATING LICENSE License No. DPR-80
- 1. The Nuclear Regulatory Commission (the Commission) has found that:
A. Consistent with Order EA-03-086, the Order requiring compliance with the revised design basis threat, (DBT Order) issued on April 29, 2003, conforming administrative changes to Facility Operating Licenses (FOLs) are required to ensure implementation of DBT Order requirements. Therefore, an administrative license change to FOL No. DPR-80 is being made to incorporate the reference to the revised Physical Security Plan, Safeguards Contingency Plan, and Training and Qualification Plan required by the DBT Order. These changes comply with the standards and requirements of the Atomic Energy Act (the Act) of 1954, as amended and the Commission's rules and regulations set forth in 10 CFR Chapter I; B. The facility will operate in conformity with the application, the provisions of the Act, and the rules and regulations of the Commission; C. There is reasonable assurance (i) that the activities authorized by this administrative license change can be conducted without endangering the health and safety of the public, and (ii) that such activities will be conducted in compliance with the Commission's regulations; D. The issuance of this administrative license change will not be inimical to the common defense and security or to the health and safety of the public; and E. The issuance of this administrative license change is in accordance with 10 CFR Part 51 of the Commission's regulations and all applicable requirements have been satisfied.
Enclosure 1
- 2. Accordingly, the FOL is changed as indicated in the Attachment.
- 3. This administrative license change is effective as of its date of issuance and shall be implemented on or before October 29, 2004.
FOR THE NUCLEAR REGULATORY COMMISSION
/RA/
John A. Nakoski, Chief Security Plan Review Team Project Directorate II Division of Licensing Project Management Office of Nuclear Reactor Regulation
Attachment:
Changes to the FOL Date of Issuance: October 28, 2004
CHANGES TO FACILITY OPERATING LICENSE NO. DPR-80 DOCKET NO. 50-275 Replace the following page of the Facility Operating License No. DPR-80 with the attached revised page as indicated. The revised page is identified by a revision date and contains marginal lines indicating the area of change.
Remove Page Insert Page 9 9
E. Physical Protection The licensee shall fully implement and maintain in effect all provisions of the l Commission-approved physical security, training and qualification, and safeguards l contingency plans including amendments made pursuant to provisions of the l Miscellaneous Amendments and Search Requirements revisions to 10 CFR 73.55 l (51 FR 27817 and 27822) and to the authority of 10 CFR 50.90 and 10 CFR 50.54(p). l The combined set of plans, which contains Safeguards Information protected under l 10 CFR 73.21, is entitled: "Diablo Canyon Power Plant, Units 1 and 2 Physical Security l Plan, by Training and Qualification Plan, and Safeguards Contingency Plan," submitted l by letter dated October 8, 2004, as supplemented by letters dated October 14, 2004 and l October 19, 2004. l F. Antitrust Pacific Gas and Electric Company shall comply with the antitrust conditions in Appendix C to this license.
G. Reporting PG&E shall report any violations of the requirements contained in Sections 2.C(3) and 2.C(4), 2.C(6) through 2.C(10), 2.E and 2.F, of this License within 24 hours2.777778e-4 days <br />0.00667 hours <br />3.968254e-5 weeks <br />9.132e-6 months <br />. Initial notification shall be made in accordance with the provisions of 10 CFR 50.72, with written follow-up in accordance with the procedures described in I0 CFR 50.73(b), (c),
(d) and (e).
H. Financial Protection PG&E shall have and maintain financial protection of such type and in such amonts as the Commission shall require in accordance with Section 170 of the Atomic Energy Act of 1954, as amended, to cover public liability claims.
I. Term of License This License is effective as of the date of issuance and shall expire at midnight on September 22, 2021.
FOR THE NUCLEAR REGULATORY COMMISSION Original Signed by:
Edson G. Case for Harold R. Denton, Director Office of Nuclear Reactor Regulation Attachments:
- 1. Appendix A - Technical Specifications
- 2. Appendix B - Environmental Protection Plan
- 3. Appendix C - Antitrust Conditions
- 4. Appendix D - Additional Conditions Date of Issuance: November 2, 1984 Amendment No. 32,75,97,120 Revised by letter dated October 28, 2004
PACIFIC GAS AND ELECTRIC COMPANY DOCKET NO. 50-323 DIABLO CANYON NUCLEAR POWER PLANT, UNIT 2 ADMINISTRATIVE LICENSE CHANGE TO FACILITY OPERATING LICENSE License No. DPR-82
- 1. The Nuclear Regulatory Commission (the Commission) has found that:
A. Consistent with Order EA-03-086, the Order requiring compliance with the revised design basis threat, (DBT Order) issued on April 29, 2003, conforming administrative changes to Facility Operating Licenses (FOLs) are required to ensure implementation of DBT Order requirements. Therefore, an administrative license change to FOL No. DPR-82 is being made to incorporate the reference to the revised Physical Security Plan, Safeguards Contingency Plan, and Training and Qualification Plan required by the DBT Order. These changes comply with the standards and requirements of the Atomic Energy Act (the Act) of 1954, as amended and the Commission's rules and regulations set forth in 10 CFR Chapter I; B. The facility will operate in conformity with the application, the provisions of the Act, and the rules and regulations of the Commission; C. There is reasonable assurance (i) that the activities authorized by this administrative license change can be conducted without endangering the health and safety of the public, and (ii) that such activities will be conducted in compliance with the Commission's regulations; D. The issuance of this administrative license change will not be inimical to the common defense and security or to the health and safety of the public; and E. The issuance of this administrative license change is in accordance with 10 CFR Part 51 of the Commission's regulations and all applicable requirements have been satisfied.
- 2. Accordingly, the FOL is changed as indicated in the Attachment.
- 3. This administrative license change is effective as of its date of issuance and shall be implemented on or before October 29, 2004.
FOR THE NUCLEAR REGULATORY COMMISSION
/RA/
John A. Nakoski, Chief Security Plan Review Team Project Directorate II Division of Licensing Project Management Office of Nuclear Reactor Regulation
Attachment:
Changes to the FOL Date of Issuance: October 28, 2004
CHANGES TO FACILITY OPERATING LICENSE NO. DPR-82 DOCKET NO. 50-323 Replace the following page of the Facility Operating License No. DPR-82 with the attached revised page as indicated. The revised page is identified by a revision date and contains marginal lines indicating the area of change.
Remove Page Insert Page 6 6
(10) Pipeway Structure DE and DDE Analysis (SBER 32. Section 4)
Prior to start-up following the first refueling outage PG&E shall complete a confirmatory analysis for the pipeway structure to further demonstrate the adequacy of the pipeway structure for load combinations that include the design earthquake (DE) and double design earthquake (DDE).
(11) Spent Fuel Pool Modification The licensee is authorized to modify the spent fuel pool as described in the application dated October 30, 1985 (LAR 85-13) as supplemented. Amendment No. 6 issued on May 30, 1986 and stayed by the U.S. Court of Appeals for the Ninth Circuit pending completion of NRC hearings is reinstated.
Prior to final conversion to the modified rack design, fuel may be stored, as needed, in either the modified storage racks described in Technical Specification 5.6.1.1 or in the unmodified storage racks (or both) which are designed and shall be maintained with a nominal 21-inch center-to-center distance between fuel assemblies placed in the storage racks.
(12) Additional Conditions The Additional Conditions contained in Appendix D, as revised through Amendment No. 118, are hereby incorporated into this license. Pacific Gas and Electric Company shall operate the facility in accordance with the Additional Conditions.
D. Exemption (SSER 31, Section 6.2.6)
An exemption from certain requirements of Appendix J to 10 CFR Part 50 is described in the Office of Nuclear Reactor Regulation's Safety Evaluation Report, Supplement No.
- 9. This exemption is authorized by law and will not endanger life or property or the common defense and security and is otherwise in the public interest. Therefore, this exemption previously granted in Facility Operating License No. DPR-81 pursuant to 10 CFR 50.12 is hereby reaffirmed. The facility will operate, with the exemption authorized, in conformity with the application, as amended, the provisions of the Act, and the regulations of the Commission.
E. Physical Protection The licensee shall fully implement and maintain in effect all provisions of the l Commission-approved physical security, training and qualification, and safeguards l contingency plans including amendments made pursuant to provision of the l Miscellaneous Amendments and Search Requirements revisions to 10 CFR 73.55 l (51 FR 27817 and 27822) and to the authority of 10 CFR 50.90 and 10 CFR 50.54(p). l The combined set of plans, which contains Safeguards Information protected under l 10 CFR 73.21, is entitled: "Diablo Canyon Power Plant, Units 1 and 2 Physical Security l Plan, Training and Qualification Plan and Safeguards Contingency Plan," submitted by l letter dated October 8, 2004, as supplemented by letters dated October 14, 2004, and l October 19, 2004. l Amendment No. 21, 31, 118 Revised by letter dated October 28, 2004