MONTHYEARLR-N04-0021, Units I and 2 - Implementation of Alternative Source Term (AST) Request for Changes to Technical Specifications and Updated Final Safety Analysis Report2004-04-26026 April 2004 Units I and 2 - Implementation of Alternative Source Term (AST) Request for Changes to Technical Specifications and Updated Final Safety Analysis Report Project stage: Request ML0416103102004-07-0606 July 2004 PSEG Nuclear, LLC, Withholding from Public Disclosure, NEDC-33066P, Hope Creek Generating Station Aprm/Rbm/Technical Specifications/Maximum Extended Load Line Limit Analysis (Arts/Mellla), Revision 1 Project stage: Other ML0423701062004-08-24024 August 2004 Request for Additional Information Implementation of Alternate Source Term Project stage: RAI LR-N04-0417, LCR S03-05, Implementation of Alternate Source Term Request for Additional Information (TAC Nos. MC3094 & MC3095)2004-09-23023 September 2004 LCR S03-05, Implementation of Alternate Source Term Request for Additional Information (TAC Nos. MC3094 & MC3095) Project stage: Request LR-N04-0431, Request for License Amendment Arts/Mella Implementation - Schedule Update2004-09-30030 September 2004 Request for License Amendment Arts/Mella Implementation - Schedule Update Project stage: Request ML0429406752004-10-29029 October 2004 Delay in Submission of Fuel Dependent Analyses (Tac No. Mc 3390) Project stage: Other ML0431303612004-11-16016 November 2004 Request for Additional Information Amendment to Implement Alternative Source Term Project stage: RAI ML0504901532005-03-0808 March 2005 Facsimile Transmission, Draft Request for Additional Information to Be Discussed in an Upcoming Conference Call Project stage: Draft RAI ML0510803412005-05-0505 May 2005 RAI, Amendment to Implement Alternative Source Term Project stage: RAI LR-N05-0314, May 2005 Monthly Operating Report for Salem Generating Station, Unit 12005-06-14014 June 2005 May 2005 Monthly Operating Report for Salem Generating Station, Unit 1 Project stage: Request ML0522105012005-07-25025 July 2005 E-Mail Miller, NRR, to Duke, PSEG, Hope Creek Arts/Mellla Draft RAIs Project stage: Draft Other ML0525102402005-08-10010 August 2005 Implementation of Alternate Source Term (AST) Request for Changes to Technical Specifications and Updated Final Safety Analysis Report Project stage: Request ML0523004982005-08-18018 August 2005 RAI - Request for Change to Technical Specifications, Implementation of Arts/Mellla Operating Domain Project stage: RAI 05000354/LER-2005-007, Re B Control Room Emergency Filtration (CREF) Train Inoperable Greater than Allowed by Technical Specifications2005-08-18018 August 2005 Re B Control Room Emergency Filtration (CREF) Train Inoperable Greater than Allowed by Technical Specifications Project stage: Request LR-N05-0448, Response to Request for Additional Information Re Request for Change to Technical Specifications Arts/Mellla Implementation2005-09-23023 September 2005 Response to Request for Additional Information Re Request for Change to Technical Specifications Arts/Mellla Implementation Project stage: Response to RAI ML0530000292005-10-31031 October 2005 PSEG Nuclear LLC, Request for Withholding Information from Public Disclosure Project stage: Withholding Request Acceptance LR-N05-0520, Response to Request for Additional Information Request for Change to Technical Specifications Arts/Mellla Implementation2005-11-16016 November 2005 Response to Request for Additional Information Request for Change to Technical Specifications Arts/Mellla Implementation Project stage: Response to RAI JAFP-06-0015, Application for Technical Specification Amendment to Support Implementation of Arts/Meod2006-01-26026 January 2006 Application for Technical Specification Amendment to Support Implementation of Arts/Meod Project stage: Request ML0605301292006-02-17017 February 2006 Issuance of Amendments Alternate Source Term - Technical Specification Pages Project stage: Approval ML0600403222006-02-17017 February 2006 Issuance of License Amendments 271 and 252 Alternate Source Term Project stage: Approval ML0606204702006-03-0303 March 2006 Re-Issuance of Safety Evaluation for Amendment 163 Implementation of Arts/Mellla Project stage: Approval ML0606205002006-03-0303 March 2006 SE Related to Amendment No. 163 - Non-Proprietary Project stage: Other ML0610700392006-05-0202 May 2006 Corrections to Safety Evaluation for Amendment No. 271 and No. 252, Respectively, Alternate Source Term Project stage: Approval 2005-03-08
[Table View] |
Text
October 29, 2004 Mr. A. Christopher Bakken, III President & Chief Nuclear Officer PSEG Nuclear LLC-X15 Post Office Box 236 Hancocks Bridge, NJ 08038
SUBJECT:
HOPE CREEK GENERATING STATION - DELAY IN SUBMISSION OF FUEL DEPENDENT ANALYSES (TAC NO. MC3390)
Dear Mr. Bakken:
By letter dated June 7, 2004, PSEG Nuclear, LLC (PSEG) requested U.S. Nuclear Regulatory Commission (NRC) approval of an amendment to Facility Operating License No. NPF-57 for the Hope Creek Generating Station (Hope Creek). The amendment would allow the implementation of Average Power Range Monitor/Rod Block Monitor/Technical Specifications (TSs)/Maximum Extended Load Line Limit Analysis. In this submittal, PSEG indicated that it would submit the Hope Creek fuel dependent analyses results and, if required, any additional TS changes associated with the fuel dependent evaluations on or before September 30, 2004.
Per schedule discussions between PSEG and the NRC staff, approval of the amendment was requested within 6 months after submittal of the fuel dependent evaluations.
By letter dated September 30, 2004, PSEG informed the NRC that the fuel dependent analyses would not be submitted until November 30, 2004. The NRC initially scheduled its review based upon the anticipated submission of the fuel dependent analyses on September 30, 2004. As such, any delay in your submission of the fuel analysis will result in a delay in the NRC review of the application. It should be noted that your anticipated submittal date is during a time period when the NRC staff workload will be increased due to items such as preparation for spring refueling outages. Accordingly, your delay in submission of the fuel dependent evaluations may result in a change in our review schedule in light of other priority actions currently under NRC staff review. We will inform you of the new review schedule once the fuel dependent evaluations have been submitted.
Sincerely,
/RA/
Daniel S. Collins, Sr. Project Manager, Section 2 Project Directorate I Division of Licensing Project Management Office of Nuclear Reactor Regulation Docket No. 50-354 cc: See next page
Hope Creek Generating Station cc:
Mr. John T. Carlin Vice President - Nuclear Assessment PSEG Nuclear - N10 P.O. Box 236 Hancocks Bridge, NJ 08038 Mr. Patrick S. Walsh Vice President - Eng/Tech Support PSEG Nuclear - N28 P.O. Box 236 Hancocks Bridge, NJ 08038 Mr. Michael Brothers Vice President - Site Operations PSEG Nuclear - N10 P.O. Box 236 Hancocks Bridge, NJ 08038 Mr. James A. Hutton Plant Manager PSEG Nuclear - X15 P.O. Box 236 Hancocks Bridge, NJ 08038 Ms. Christina L. Perino Director - Licensing & Nuclear Safety PSEG Nuclear - N21 P.O. Box 236 Hancocks Bridge, NJ 08038 Jeffrie J. Keenan, Esquire PSEG Nuclear - N21 P.O. Box 236 Hancocks Bridge, NJ 08038 Ms. R. A. Kankus Joint Owner Affairs Exelon Generation Company, LLC Nuclear Group Headquarters KSA1-E 200 Exelon Way Kennett Square, PA 19348 Lower Alloways Creek Township c/o Mary O. Henderson, Clerk Municipal Building, P.O. Box 157 Hancocks Bridge, NJ 08038 Dr. Jill Lipoti, Asst. Director Radiation Protection Programs NJ Department of Environmental Protection and Energy CN 415 Trenton, NJ 08625-0415 Brian Beam Board of Public Utilities 2 Gateway Center, Tenth Floor Newark, NJ 07102 Regional Administrator, Region I U.S. Nuclear Regulatory Commission 475 Allendale Road King of Prussia, PA 19406 Senior Resident Inspector Hope Creek Generating Station U.S. Nuclear Regulatory Commission Drawer 0509 Hancocks Bridge, NJ 08038
ML042940675 OFFICE PDI-2/PE PDI-2/PM PDI-2/LA SRXB-A/SC PDI-2/SC PDI/PD NAME GMiller DCollins SLittle for CRaynor FAkstulewicz DCollins for JClifford CHolden DATE 10/27/04 10/27/04 10/25/04 10/15/2004 10/27/04 10/29/04