MONTHYEARIR 05000400/20230042024-01-30030 January 2024 Integrated Inspection Report 05000400/2023004 ML23317A3462023-11-14014 November 2023 Duke Fleet - Correction Letter to License Amendment Nos. 312 & 340 Issuance of Amendments Regarding the Adoption of Technical Specifications Task Force Traveler TSTF-554, Revision 1 IR 05000400/20230032023-11-0909 November 2023 Integrated Inspection Report 05000400/2023003 ML23346A1322023-10-0606 October 2023 Communication from C-10 Research & Education Foundation Regarding NextEra Common Emergency Fleet Plan License Amendment Request and Related Documents Subsequently Published ML23234A1702023-10-0303 October 2023 Issuance of Amendment No. 199 Regarding Administrative Changes to the Renewed Facility Operating License and Technical Specifications ML23256A0882023-09-25025 September 2023 Issuance of Alternative to Steam Generator Welds ML23195A0782023-08-29029 August 2023 Issuance of Amendments Regarding the Adoption of Technical Specifications Task Force Traveler TSTF-554, Revision 1 IR 05000400/20230052023-08-23023 August 2023 Updated Inspection Plan for Shearon Harris Nuclear Power Plant, Unit 1 (Report 05000400/2023005) ML23234A2542023-08-22022 August 2023 RQ Inspection Notification Letter IR 05000400/20234022023-07-26026 July 2023 Security Baseline Inspection Report 05000400/2023402 IR 05000400/20230022023-07-24024 July 2023 Integrated Inspection Report 05000400/2023002 IR 05000400/20234402023-07-17017 July 2023 Special Inspection Report 05000400/2023440 and Preliminary Greater than Green Finding and Apparent Violation Cover Letter IR 05000400/20243012023-05-15015 May 2023 Notification of Licensed Operator Initial Examination 05000400/2024301 IR 05000400/20230012023-05-10010 May 2023 Integrated Inspection Report 05000400 2023001 IR 05000400/20234042023-05-0404 May 2023 Cyber Security Inspection Report 05000400/2023404 ML23118A0762023-05-0101 May 2023 Approval for Use of Specific Provision of a Later Edition of the American Society of Mechanical Engineers Boiler and Pressure Vessel Code, Section XI ML23118A1392023-04-28028 April 2023 Submittal of Updated Final Safety Analysis Report (Amendment 65), Technical Specification Bases Revision, Report of Changes Pursuant to 10 CFR 50.59 and Summary of Commitment Changes IR 05000400/20234032023-04-0505 April 2023 Security Baseline Inspection Report 05000400/2023403 IR 05000400/20230102023-03-15015 March 2023 Comprehensive Engineering Team Inspection (CETI) Inspection Report 05000400/2023010 ML22332A4932023-03-10010 March 2023 William States Lee III 1 and 2 - Issuance of Amendments Regarding the Relocation of the Emergency Operations Facility IR 05000400/20220062023-03-0101 March 2023 Annual Assessment Letter for Shearon Harris Nuclear Power Plant - NRC Inspection Report 05000400/2022006 ML23033A5272023-02-0808 February 2023 Correction of Typographical Errors Incurred During Issuance of License Amendment No. 196 IR 05000400/20220042023-02-0707 February 2023 Integrated Inspection Report 05000400/2022004 ML23020A1252023-01-23023 January 2023 Notification of Target Set Inspection and Request for Information (NRC Inspection Report 05000400/2023403) ML22096A0032022-11-18018 November 2022 McGuire Nuclear Station and Shearon Harris Nuclear Power Plant Authorization of RA-19-0352 Regarding Use of Alternative for RPV Head Closure Stud Examinations ML22256A2532022-11-14014 November 2022 Issuance of Amendments Regarding the Adoption of Technical Specifications Task Force Traveler TSTF-541, Rev. 2 IR 05000400/20220032022-11-10010 November 2022 Integrated Inspection Report 05000400/2022003 IR 05000400/20223012022-11-0202 November 2022 NRC Operator License Examination Report 05000400/2022301 ML22271A6202022-09-29029 September 2022 Notification of Shearon Harris Nuclear Power Plant Comprehensive Engineering Team Inspection - U.S. Nuclear Regulatory Commission Inspection Report 05000400/2023010 ML22258A1262022-09-14014 September 2022 NRC Operator Licensing Examination Approval 05000400/2022301 ML22242A0022022-09-12012 September 2022 Issuance of Amendments to Adopt TSTF 569, Revision 2, Revise Response Time Testing Definition ML22227A0682022-09-0202 September 2022 Alternative to Certain Inservice Testing Requirements in the American Society of Mechanical Engineers Code for Operation and Maintenance for Certain Target Rock Solenoid Valves IR 05000400/20220052022-08-24024 August 2022 Updated Inspection Plan for Shearon Harris Nuclear Power Plant (Report 05000400/2022005) IR 05000400/20224032022-08-23023 August 2022 Security Baseline Inspection Report 05000400/2022403 ML22126A0082022-08-0909 August 2022 Issuance of Amendment No. 194 Revise Technical Specifications Related to Reactor Protection System Instrumentation P7 IR 05000400/20220022022-08-0505 August 2022 Integrated Inspection Report 05000400/2022002 ML22161B0332022-07-28028 July 2022 Issuance of Amendment No. 193 Regarding Revision of Surveillance Requirements to Remove Shutdown Limitation IR 05000400/20220112022-07-20020 July 2022 Biennial Problem Identification and Resolution Inspection Report 05000400 2022011 IR 05000400/20224022022-06-30030 June 2022 Material Control and Accounting Program Inspection Report 05000400/2022402 (OUO Removed) IR 05000400/20220102022-06-13013 June 2022 Design Basis Assurance Inspection (Programs) Inspection Report 05000400/2022010 ML22138A4012022-05-26026 May 2022 Project Manager Reassignment ML22101A2822022-05-0606 May 2022 Regulatory Audit Summary Related to the Review of License Amendment Regarding Revising the Flood Hazard Protection Scheme IR 05000400/20220012022-05-0404 May 2022 Integrated Inspection Report 05000400/2022001 IR 05000400/20224012022-03-24024 March 2022 Security Baseline Inspection Report 05000400/2022401 ML22020A0072022-03-10010 March 2022 Issuance of Amendment No. 192 Regarding Removal of Extraneous Content and Requirements from the Renewed Facility Operating License and Technical Specifications ML22010A2812022-03-0404 March 2022 Issuance of Amendments to Adopt TSTF-577, Rev. 1 Revised Frequencies for Steam Generator Tube Inspections (EPID L-2021-LLA-0161 IR 05000400/20210062022-03-0202 March 2022 Annual Assessment Letter for Shearon Harris Nuclear Power Plant (Report No. 05000400/2021006) ML21351A4722022-02-10010 February 2022 Issuance of Amendment No. 190 Regarding Revision to Containment Spray Nozzle Test Frequency IR 05000400/20210042022-02-0404 February 2022 Integrated Inspection Report 05000400/2021004 ML22034A5352022-02-0202 February 2022 Notification of Licensed Operator Initial Examination 05000400/2022301 2024-01-30
[Table view] Category:Request for Additional Information (RAI)
MONTHYEARML24025A1592024-01-25025 January 2024 NRR E-mail Capture - Shearon Harris Nuclear Power Plant, Unit 1 - Request for Additional Information - Rvi AMP and Inspection Plan (L-2023-LLL-0016) ML23151A3482023-05-30030 May 2023 Duke Fleet - Request for Additional Information Proposed Alternative for Pressurizer Welds in Accordance with 10 CFR 50.55a(z)(1) ML23142A2732023-05-22022 May 2023 Duke Fleet - Request for Additional Information Proposed Alternative for Steam Generator Welds in Accordance with 10 CFR 50.55a(z)(1) ML23082A0432023-03-23023 March 2023 002 Radiation Safety Baseline Inspection Information Request Final ML23020A1252023-01-23023 January 2023 Notification of Target Set Inspection and Request for Information (NRC Inspection Report 05000400/2023403) ML22115A1412022-04-25025 April 2022 NRR E-mail Capture - Duke Common EOF Relocation - Request for Addition Information ML21354A8612021-12-15015 December 2021 NRR E-mail Capture - Request for Additional Information - Duke Fleet Request RA-19-0352 - Alternative for RPV Closure Stud Exams (L-2020-LLR-0156) ML21258A3652021-09-15015 September 2021 Notification of an NRC Fire Protection Team Inspection (FPTI) (NRC Inspection Report 05000400/2021011) and Request for Information (RFI) ML21172A2432021-06-21021 June 2021 NRR E-mail Capture - Request for Additional Information - Harris RA-20-0252 - LAR to Remove Extraneous Requirements from OL and TS (L-2021-LLA-0027) ML21036A1142021-02-0505 February 2021 NRR E-mail Capture - Request for Additional Information - Harris - Relief Request RA-20-0312 - SW Pinhole Leak (L-2020-LLR-0143) ML21049A2632021-02-0404 February 2021 NRR E-mail Capture - Request for Additional Information - Duke Energy Fleet License Amendment Request to Revise Emergency Plan ML21032A0492021-02-0101 February 2021 NRR E-mail Capture - Request for Additional Information - Duke Fleet RA-20-0263 - Use of Later ASME B&Pv, XI for Repair - Replacement (L-2020-LLR-0124) ML20323A4072020-11-18018 November 2020 NRR E-mail Capture - Request for Additional Information - Brunswick License Exemption Request from 10CFR73 Annual Force on Force Exercise Requirements (EPIC L-2020-LLE-0180) ML20297A3072020-10-13013 October 2020 NRR E-mail Capture - Request for Additional Information - Shearon Harris Nuclear Power Plant, Unit 1 - RCS Flowrate Reduction/Lbloca LAR ML20274A0462020-09-29029 September 2020 Request for Additional Information Regarding License Amendment Request to Adopt TSTF-505, Revision 2 ML20247J3822020-09-0303 September 2020 Request for Additional Information - Shearon Harris Nuclear Power Plant, Unit 1 - Revise TS Related to Accident Monitoring and RFO Instrumentation ML19331A4002019-11-27027 November 2019 Request for Additional Information Regarding Licensing Action to Modify the Departure from Nucleate Boiling Ratio Safety Limit to Address Transition to New Fuel Type ML19204A2682019-07-23023 July 2019 NRR E-mail Capture - Shearon Harris Nuclear Power Plant, Unit 1 Request for Additional Information for the Escw System TS AOT Extension and Removal of an Expired Note in TS Risk Informed LAR (L-2019-LLA-0025) ML19136A2712019-05-28028 May 2019 Supplemental Information Needed for Acceptance of Requested Licensing Action Regarding License Amendment Request to Modify the Departure from Nucleate Boiling Ratio Safety Limit to Address Transition to New Fuel Type ML19060A0912019-03-18018 March 2019 Request for Additional Information Regarding License Amendment Request to Adopt 10 CFR 50.69, Risk Informed Categorization and Treatment of Structures, Systems and Components for Nuclear Power Reactors ML19011A1372019-01-10010 January 2019 NRR E-mail Capture - Duke Energy Fleet RAIs - Relief Request 18-GO-001 - Proposed Alternative for Depth Sizing Qualification Examination of Welds (L-2018-LLR-0117) ML19007A3422018-12-21021 December 2018 NRR E-mail Capture - Duke Energy Fleet Draft RAIs - Relief Request 18-GO-001 - Proposed Alternative for Depth Sizing Qualification Examination of Welds (L-2018-LLR-0117) ML18332A4392018-11-28028 November 2018 NRR E-mail Capture - Shearon Harris Nuclear Power Plant, Unit 1 Request for Additional Information for EAL Scheme Changes ML18337A1272018-11-28028 November 2018 NRR E-mail Capture - Shearon Harris Nuclear Power Plant, Unit 1 Request for Additional Information Regarding the Rts/Esfas Trip Setpoints Modification LAR ML18264A0282018-10-0909 October 2018 RAI Regarding License Amendment Request to Adopt 10 CFR 50.69, Risk Informed Categorization Aad Treatment of Structures, Systems and Components for Nuclear Power Reactors ML18145A1812018-06-18018 June 2018 Request for Additional Information, License Amendment Request to Revise Updated Final Safety Analysis Report to Incorporate Tornado Missile Risk Evaluator Methodology Into Licensing Basis RA-18-0011, Response to Request for Supplemental Information Regarding Duke Energy'S Response to GL 2016-01 Monitoring of Neutron-Absorbing Materials in Spent Fuel Pools2018-05-30030 May 2018 Response to Request for Supplemental Information Regarding Duke Energy'S Response to GL 2016-01 Monitoring of Neutron-Absorbing Materials in Spent Fuel Pools ML18116A1052018-04-25025 April 2018 NRR E-mail Capture - Harris/Robinson RAIs - Change Technical Specifications to Support Performance of Core Reload Design and Safety Analyses (L-2017-LLA-0356) ML18108A7602018-04-18018 April 2018 NRR E-mail Capture - Harris/Robinson Draft RAIs - Change Technical Specifications to Support Performance of Core Reload Design and Safety Analyses (L-2017-LLA-0356) ML18058B2242018-02-26026 February 2018 Emailed Radiation Safety RFI ML18005A5482018-01-0808 January 2018 Request for Additional Information Regarding License Amendment Request for Spent Fuel Storage Pool Criticality Analyses (CAC No. MF9996; EPID L-2017-LLA-0303) ML17345A8772017-12-11011 December 2017 NRR E-mail Capture - Harris and Robinson Supplemental RAI - LAR to Adopt DPC-NE-3009-P, Revision 0, Thermal-Hydraulic Models for Transient Analysis, (L-2016-LLA-0012) ML17339A0722017-12-0404 December 2017 NRR E-mail Capture - Subject: Harris and Robinson Draft Supplemental RAIs - LAR to Adopt DPC-NE-3009-P, Revision 0, Thermal-Hydraulic Models for Transient Analysis, (L-2016-LLA-0012) ML17289A3062017-10-23023 October 2017 Shearon Harris Nuclear Plant, Unit 1 - Request for Additional Information Regarding License Amendment Request Proposing Changes to Emergency Diesel Generator Technical Specifications Surveillance Requirements (CAC No. MF9828; EPID L-2017-LLA-0244) ML17250B0172017-09-18018 September 2017 Shearon Harris, Unit 1 - Request for Additional Information Re: License Amendment Request Proposing New Set of Fission Gas Gap Release Fractions for High Burnup Fuel Rods that Exceed the LHGR Limit Detailed in RG 1.183, Table 3 (CAC No. MF9740) ML17241A0182017-08-30030 August 2017 Supplemental Information Needed for Acceptance of Requested Licensing Action Regarding Spent Fuel Storage Pool Criticality Analyses ML17192A4842017-07-11011 July 2017 NRR E-mail Capture - Duke Energy Fleet RAIs Alternative for Reactor Pressure Vessel Flange Threads Examination (MF9513 to MF9521) ML17123A1332017-05-0909 May 2017 Shearon Harris Nuclear Plant, Unit 1 - Request for Additional Information Re: License Amendment Request to Relocate Specific TS Parameters to the COLR, Remove Reference to a Plant Procedure as it Pertains to the COLR in TSs, etc. (CAC No. MF8894) ML17109A2912017-04-19019 April 2017 NRR E-mail Capture - Shearon Harris Nuclear Power Plant, Unit 1 Final Request for Additional Information Concerning LAR to Adopt TSTF-339, TSTF-5 and Other Administrative Changes ML16363A0112016-12-27027 December 2016 Notification of Shearon Harris Nuclear Power Plant Design Basis Assurance Inspection - U.S. Nuclear Regulatory Commission Inspection Report 05000400/2017007 ML16335A0462016-12-0606 December 2016 Shearon Harris Nuclear Power Plant, Unit 1 - Request for Additional Information Regarding License Amendment Request to Modify Diesel Fuel Oil Testing Surveillance Requirements (CAC No. MF7775) ML16288A0782016-10-26026 October 2016 Shearon Harris Nuclear Power Plant, Unit 1, and H.B. Robinson Steam Electric Plant, Unit No. 2 - Redacted, Request for Additional Information Re: Request to Adopt DPC-NF-2010 and DPC-NF-2011 Nuclear Design Methodology (CAC Nos. MF7693 and MF7694) ML16288A0042016-10-26026 October 2016 Shearon Harris Nuclear Plant, Unit 1 - Request For Additional Information Regarding License Amendment Request To Relocate The Explosive Gas Mixture And Liquid Holdup Tanks Technical Specifications Requirements (CAC No. MF8067) ML16223A4172016-08-0808 August 2016 Notification of Inspection and Request for Information ML16209A2642016-08-0202 August 2016 Shearon Harris Nuclear Plant, Unit 1 - Second Request For Additional Information Regarding License Amendment Request For A Temporary Change To Technical Specifications For The 'A' Emergency Service Water Pump Replacement (CAC No. MF7017) ML16028A1972016-02-0808 February 2016 Request for Additional Information Regarding License Amendment Request for a Temporary Change to Technical Specifications for the 'A' Emergency Service Water Pump Replacement ML15344A0302015-12-17017 December 2015 Request for Additional Information Application to Revise Technical Specifications for Methodology Report DPC-NE-2005-P, Revision 5, Thermal Hydraulic Statistical Core Design Methodology (MF5872/MF5873) ML15320A3862015-11-19019 November 2015 RAI LAR to Adopt TSTF-523 ML15314A3592015-11-10010 November 2015 Duke Energy Draft RAIs Request to Adopt TSTF-523 (CAC Nos. MF6413-MF6422) ML15314A3562015-11-10010 November 2015 E-mail from J. Whited to A. Zaremba Duke Energy Draft RAIs License Amendment Request to Adopt TSTF-523 (CAC Nos. MF6413-MF6422) 2024-01-25
[Table view] |
Text
October 1, 2004 Mr. James Scarola, Vice President Shearon Harris Nuclear Power Plant Carolina Power & Light Company Post Office Box 165, Mail Code: Zone 1 New Hill, North Carolina 27562-0165
SUBJECT:
SHEARON HARRIS NUCLEAR POWER PLANT, UNIT 1 - REQUEST FOR ADDITIONAL INFORMATION REGARDING NRC BULLETIN 2004-01, INSPECTION OF ALLOY 82/182/600 MATERIALS USED IN THE FABRICATION OF PRESSURIZER PENETRATIONS AND STEAM SPACE PIPING CONNECTIONS AT PRESSURIZED-WATER REACTORS
Dear Mr. Scarola:
The Nuclear Regulatory Commission (NRC) staff has reviewed and evaluated your response dated July 27, 2004, to NRC Bulletin 2004-01, 60-day Response to NRC Bulletin 2004-01 for the Inspection of Alloy 82/182/600 Materials Used in the Fabrication of Pressurizer Penetrations and Steam Space Piping Connections at Pressurized-Water Reactors, for the Shearon Harris Nuclear Power Plant, Unit 1 (HNP). We have determined that more information is needed to complete our review. Our Request for Additional Information (RAI) for HNP is enclosed. We request that you to respond to the RAI within 30 days of receipt of this letter. If you have any questions, please contact me at 301-415-3025.
Sincerely,
/RA/
Chandu P. Patel, Project Manager, Section 2 Project Directorate II Division of Licensing Project Management Office of Nuclear Reactor Regulation Docket No. 50-400
Enclosure:
RAI cc w/enclosure:
See next page
ML042740719 Nrr-088 OFFICE PM:PDII/S2 LA:PDII/S2 SC:PDII/S2 SC:EMCB NAME CPatel EDunnington MMarshall SCoffin DATE 9/27/04 9/24/04 10/01/04 9/27/04 COPY Yes/No Yes/No Yes/No Yes/No REQUEST FOR ADDITIONAL INFORMATION FOR NRC BULLETIN 2004-01 RESPONSE Shearon Harris Nuclear Power Plant, Unit 1 Carolina Power & Light Company Docket No. 50-400 The NRC staff has completed its review of your response dated July 27, 2004, to NRC Bulletin 2004-01, 60-day Response to NRC Bulletin 2004-01 for the Inspection of Alloy 82/182/600 Materials Used in the Fabrication of Pressurizer Penetrations and Steam Space Piping Connections at Pressurized-Water Reactors. Based on the NRC staffs review, please provide a supplemental response that addresses the following question.
Your response to Bulletin 2004-01 Question (1)(c) did not clearly communicate your intentions with respect to ensuring that an appropriate dialogue would be established with NRC technical staff in the event that circumferential primary water stress corrosion cracking (PWSCC) is identified at any locations covered under the scope of Bulletin 2004-01. The NRC staff addressed this issue, in part, on page 5 of Bulletin 2004-01 stating, . . . the NRC staff believes that the topic of NDE scope expansion should be discussed with the NRC if circumferential PWSCC is observed in either the pressure boundary or non-pressure boundary portions of any locations covered under the scope of this bulletin to ensure that the licensee has performed an adequate extent-of-condition evaluation.
Because of the potential plant-specific and generic significance of circumferential PWSCC at locations covered under the scope of Bulletin 2004-01, it is the NRC staffs position that cognizant members of the Office of Nuclear Reactor Regulations Materials and Chemical Engineering Branch (EMCB) should be promptly made aware of any emerging issue regarding this degradation phenomena at your facility.
This is important not only for the reason cited in the passage above from Bulletin 2004-01, but also so that the NRC staff can evaluate any such information and fulfill its obligation to inform other U.S. nuclear power plant licensees of new operational experience that may be relevant to the continued safe operation of their facilities.
It is the NRC staffs expectation that if you obtain inspection results in the future that indicate that circumferential PWSCC may be occurring at any location covered under the scope of Bulletin 2004-01, you should contact your NRC Headquarters Project Manager (PM) and request a teleconference or meeting with EMCB technical staff. Notification of your NRC PM should allow ample time for you to incorporate any insights from the aforementioned teleconference or meeting into your plans for evaluating the extent of condition at your facility prior to the end of the outage during which the degradation was discovered.
In order to document your intent to follow the guidance provided above, please provide a supplement to your Bulletin 2004-01 item (1)(c) response that states:
If circumferential cracking is observed in either the pressure boundary or non-pressure boundary portions of any locations covered under the scope of this bulletin, [we] will develop plans to perform an adequate extent-of-condition evaluation and [we] will discuss those plans with cognizant NRC technical staff prior to restarting the affected unit.
Enclosure
Mr. James Scarola Shearon Harris Nuclear Power Plant Carolina Power & Light Company Unit 1 cc:
Steven R. Carr Mr. John H. ONeill, Jr.
Associate General Counsel - Legal Shaw, Pittman, Potts & Trowbridge Department 2300 N Street, NW.
Progress Energy Service Company, LLC Washington, DC 20037-1128 Post Office Box 1551 Raleigh, North Carolina 27602-1551 Mr. Robert J. Duncan II Director of Site Operations Resident Inspector/ Harris NPS Shearon Harris Nuclear Power Plant c/o U. S. Nuclear Regulatory Commission Carolina Power & Light Company 5421 Shearon Harris Road Post Office Box 165, Mail Zone 1 New Hill, North Carolina 27562-9998 New Hill, North Carolina 27562-0165 Ms. Margaret A. Force Mr. Robert P. Gruber Assistant Attorney General Executive Director State of North Carolina Public Staff NCUC Post Office Box 629 4326 Mail Service Center Raleigh, North Carolina 27602 Raleigh, North Carolina 27699-4326 Public Service Commission Chairman of the North Carolina State of South Carolina Utilities Commission Post Office Drawer 11649 Post Office Box 29510 Columbia, South Carolina 29211 Raleigh, North Carolina 27626-0510 Ms. Beverly Hall, Section Chief Mr. Herb Council, Chair Division of Radiation Protection Board of County Commissioners N.C. Department of Environment of Wake County and Natural Resources P. O. Box 550 3825 Barrett Drive Raleigh, North Carolina 27602 Raleigh, North Carolina 27609-7721 Mr. Tommy Emerson, Chair Mr. Chris L. Burton Board of County Commissioners Manager of Chatham County Performance Evaluation and P. O. Box 87 Regulatory Affairs PEB 7 Pittsboro, North Carolina 27312 Progress Energy Post Office Box 1551 Mr. Terry C. Morton, Manager Raleigh, North Carolina 27602-1551 Support Services Shearon Harris Nuclear Power Plant Mr. Benjamin C. Waldrep Carolina Power & Light Company Plant General Manager P. O. Box 165, Mail Zone 1 Shearon Harris Nuclear Power Plant New Hill, North Carolina 27562-0165 Carolina Power & Light Company P. O. Box 165, Mail Zone 3 Mr. John R. Caves, Supervisor New Hill, North Carolina 27562-0165 Licensing/Regulatory Programs Shearon Harris Nuclear Power Plant Carolina Power & Light Company P. O. Box 165, Mail Zone 1 New Hill, NC 27562-0165