SAFEGUARDS INFORMATION SAFEGUARDS INFORMATION September 21, 2004 Mr. Mark A. Peifer Site Vice President Nuclear Management Company, LLC Duane Arnold Energy Center 3277 DAEC Road Palo, Iowa 52324-9785
SUBJECT:
SECURITY PLAN PROVISIONS FOR ENHANCED OWNER CONTROLLED AREA SURVEILLANCE AND RESPONSE (TAC NO. MC2917)
Dear Mr. Peifer:
On May 14, 2004, the U. S. Nuclear Regulatory Commissions (NRC) staff completed an evaluation of lessons learned from the pilot expanded force-on-force exercises. As a result of this evaluation, surveillance and response in the owner controlled area (OCA) was identified as one aspect of security at nuclear power plant facilities that required further improvement. On August 13, 2004, the Commission directed the staff to work with industry toward voluntary implementation of enhanced OCA surveillance and response measures.
The NRC staff worked with the industrys Security Working Group and the Nuclear Energy Institute to develop appropriate provisions to be included in physical security plans. These provisions have been discussed with your staff for incorporation into your facilitys physical security plan. Specific revised security plan language developed to achieve this objective is included as an enclosure to this letter.
Thank you for your cooperation in resolving this issue. Should you have further questions on this matter, please call Juan Peralta at (301) 415-6689 or me at (301) 415-7083.
Sincerely,
/RA/
Scott A. Morris, Chief Reactor Security Section Division of Nuclear Security Office of Nuclear Security and Incident Response
Enclosure:
As stated cc: See next page Docket No.: 50-331 WARNING: Violation of Section 147 of the Atomic Energy Act, Safeguards Information is subject to Civil and Criminal Penalties NOTICE: Enclosure transmitted herewith contains Safeguards Information. When separated from Enclosure(s) this Cover Document is DECONTROLLED
SAFEGUARDS INFORMATION SAFEGUARDS INFORMATION September 21, 2004 Mr. Mark A. Peifer Site Vice President Nuclear Management Company, LLC Duane Arnold Energy Center 3277 DAEC Road Palo, Iowa 52324-9785
SUBJECT:
SECURITY PLAN PROVISIONS FOR ENHANCED OWNER CONTROLLED AREA SURVEILLANCE AND RESPONSE (TAC NO. MC2917)
Dear Mr. Peifer:
On May 14, 2004, the U. S. Nuclear Regulatory Commissions (NRC) staff completed an evaluation of lessons learned from the pilot expanded force-on-force exercises. As a result of this evaluation, surveillance and response in the owner controlled area (OCA) was identified as one aspect of security at nuclear power plant facilities that required further improvement. On August 13, 2004, the Commission directed the staff to work with industry toward voluntary implementation of enhanced OCA surveillance and response measures.
The NRC staff worked with the industrys Security Working Group and the Nuclear Energy Institute to develop appropriate provisions to be included in physical security plans. These provisions have been discussed with your staff for incorporation into your facilitys physical security plan. Specific revised security plan language developed to achieve this objective is included as an enclosure to this letter.
Thank you for your cooperation in resolving this issue. Should you have further questions on this matter, please call Juan Peralta at (301) 415-6689 or me at (301) 415-7083.
Sincerely,
/RA/
Scott A. Morris, Chief Reactor Security Section Division of Nuclear Security Office of Nuclear Security and Incident Response
Enclosure:
As stated cc: See next page Docket No.: 50-331 DISTRIBUTION:
SPRT R/F RFretz DHuyck JCreed BBenney BVaidya ACRS OGC MBurrell DSpaulding RManili PPeduzzi MChernoff DBeaulieu LRaghavan WRuland SReynolds, RIII ADAMS Accession Number: ML042720073 OFFICE SPRT/LA SPRT SPRT SPRT NAME CHawes JPeralta JNakoski SMorris DATE 9/20/04 9/20/04 9/20/04 9/20/04 OFFICIAL RECORD COPY
Duane Arnold Energy Center cc:
Mr. John Paul Cowan Executive Vice President &
Chief Nuclear Officer Nuclear Management Company, LLC 700 First Street Hudson, MI 54016 John Bjorseth Plant Manager Duane Arnold Energy Center 3277 DAEC Road Palo, IA 52324 Steven R. Catron Manager, Regulatory Affairs Duane Arnold Energy Center 3277 DAEC Road Palo, IA 52324 U. S. Nuclear Regulatory Commission Resident Inspectors Office Rural Route #1 Palo, IA 52324 Regional Administrator, Region III U. S. Nuclear Regulatory Commission 2443 Warrenville Road, Suite 210 Lisle, IL 60532-4352 Jonathan Rogoff Vice President, Counsel & Secretary Nuclear Management Company, LLC 700 First Street Hudson, WI 54016 Bruce Lacy Nuclear Asset Manager Alliant Energy/Interstate Power and Light Company 3277 DAEC Road Palo, IA 52324 Daniel McGhee Utilities Division Iowa Department of Commerce Lucas Office Buildings, 5th floor Des Moines, IA 50319 Chairman, Linn County Board of Supervisors 930 1st Street SW Cedar Rapids, IA 52404 Craig G. Anderson Senior Vice President, Group Operations 700 First Street Hudson, WI 54016 Mark A. Peifer Site Vice President Duane Arnold Energy Center Nuclear Management Company, LLC 3277 DAEC Road Palo, IA 52324-0351