RAI, Training and Qualification Plan
ML042100067
Person / Time
Site: Duane Arnold NextEra Energy icon.png
Issue date: 07/09/2004
From: Bhalchandra Vaidya
NRC/NRR/DLPM
To: Peifer M
Nuclear Management Co
vaidya B, NRR/DLPM, 415-3308
References
TAC MC2917
Download: ML042100067 (3)


Text

SAFEGUARDS INFORMATION SAFEGUARDS INFORMATION WARNING: Violation of Section 147 of the Atomic Energy Act, Safeguards Information is subject to Civil and Criminal Penalties July 9, 2004 Mr. Mark A. Peifer Site Vice President Nuclear Management Company, LLC 3277 DAEC Road Palo, Iowa 52324-9785 c/o Mr. Ben Kindred

SUBJECT:

DUANE ARNOLD ENERGY CENTER - REQUEST FOR ADDITIONAL INFORMATION RE: TRAINING AND QUALIFICATION PLAN (TAC NO.

MC2917)

Dear Mr. Peifer:

In response to the April 29, 2003, Orders revising the design basis threat, you submitted a revised physical security plan, safeguards contingency plan, and training and qualification plan, including an implementation schedule, for Duane Arnold Energy Center.

The Nuclear Regulatory Commission staff is reviewing your submission and has determined based on its review of your Training and Qualification Plan that a request for additional information (RAI) is necessary in order to complete its evaluation. Please respond to the enclosed RAI within 10 working days from the date of receipt. If circumstances result in the need to revise the target response date, please contact me at (301)415-3498.

Sincerely,

/RA/

Bhalchandra Vaidya, Project Manager Security Plan Review Team Division of Licensing Project Management Office of Nuclear Reactor Regulation Docket No. 50-331

Enclosure:

As stated cc w/o encl: See next page NOTICE: The Enclosure contains Safeguards Information. Upon separation from the Enclosure, this letter is DECONTROLLED.

July 9, 2004 Mr. Mark A. Peifer Site Vice President Nuclear Management Company, LLC 3277 DAEC Road Palo, Iowa 52324-9785 c/o Mr. Ben Kindred

SUBJECT:

DUANE ARNOLD ENERGY CENTER - REQUEST FOR ADDITIONAL INFORMATION RE: TRAINING AND QUALIFICATION PLAN (TAC NO.

MC2917)

Dear Mr. Peifer:

In response to the April 29, 2003, Orders revising the design basis threat, you submitted a revised physical security plan, safeguards contingency plan, and training and qualification plan, including an implementation schedule, for Duane Arnold Energy Center.

The Nuclear Regulatory Commission staff is reviewing your submission and has determined based on its review of your Training and Qualification Plan that a request for additional information (RAI) is necessary in order to complete its evaluation. Please respond to the enclosed RAI within 10 working days from the date of receipt. If circumstances result in the need to revise the target response date, please contact me at (301)415-3498.

Sincerely,

/RA/

Bhalchandra Vaidya, Project Manager Security Plan Review Team Division of Licensing Project Management Office of Nuclear Reactor Regulation Docket No. 50-331

Enclosure:

As stated cc w/o encl: See next page DISTRIBUTION:

SPRT R/F RidsNsirDns RidsNrrDlpm OGC ACRS D. Beaulieu L. Raghavan B. Ruland S. Reynolds, RIII ADAMS Accession Number: ML042100067 OFFICE SPRT/NRR/PM SPRT/NRR/LA SPRT/NSIR SPRT/NRR/SC NAME BVaidya CHawes JPeralta JNakoski DATE 07/09/04 07/09/04 07/09/04 07/09/04 OFFICIAL RECORD COPY

Duane Arnold Energy Center cc:

Mr. John Paul Cowan Executive Vice President &

Chief Nuclear Officer Nuclear Management Company, LLC 700 First Street Hudson, MI 54016 John Bjorseth Plant Manager Duane Arnold Energy Center 3277 DAEC Road Palo, IA 52324 Steven R. Catron Manager, Regulatory Affairs Duane Arnold Energy Center 3277 DAEC Road Palo, IA 52324 U. S. Nuclear Regulatory Commission Resident Inspectors Office Rural Route #1 Palo, IA 52324 Regional Administrator, Region III U. S. Nuclear Regulatory Commission 2443 Warrenville Road, Suite 210 Lisle, IL 60532-4352 Jonathan Rogoff Vice President, Counsel & Secretary Nuclear Management Company, LLC 700 First Street Hudson, WI 54016 Bruce Lacy Nuclear Asset Manager Alliant Energy/Interstate Power and Light Company 3277 DAEC Road Palo, IA 52324 Daniel McGhee Utilities Division Iowa Department of Commerce Lucas Office Buildings, 5th floor Des Moines, IA 50319 Chairman, Linn County Board of Supervisors 930 1st Street SW Cedar Rapids, IA 52404 Craig G. Anderson Senior Vice President, Group Operations 700 First Street Hudson, WI 54016 Mark A. Peifer Site Vice President Duane Arnold Energy Center Nuclear Management Company, LLC 3277 DAEC Road Palo, IA 52324-0351