Text

SAFEGUARDS INFORMATION SAFEGUARDS INFORMATION September 21, 2004 Mr. Dwight E. Nunn Vice President Southern California Edison Company San Onofre Nuclear Station, Units 2 and 3 P. O. Box 128 San Clemente, CA 92674-0128

SUBJECT:

SECURITY PLAN PROVISIONS FOR ENHANCED OWNER CONTROLLED AREA SURVEILLANCE AND RESPONSE (TAC NOS. MC2969 AND MC2970)

Dear Mr. Nunn:

On May 14, 2004, the U. S. Nuclear Regulatory Commissions (NRC) staff completed an evaluation of lessons learned from the pilot expanded force-on-force exercises. As a result of this evaluation, surveillance and response in the owner controlled area (OCA) was identified as one aspect of security at nuclear power plant facilities that required further improvement. On August 13, 2004, the Commission directed the staff to work with industry toward voluntary implementation of enhanced OCA surveillance and response measures.

The NRC staff worked with the industrys Security Working Group and the Nuclear Energy Institute to develop appropriate provisions to be included in physical security plans. These provisions have been discussed with your staff for incorporation into your facilities physical security plans. Specific revised security plan language developed to achieve this objective is included as an enclosure to this letter.

Thank you for your cooperation in resolving this issue. Should you have further questions on this matter, please call Juan Peralta at (301) 415-6689 or me at (301) 415-7083.

Sincerely,

/RA/

Scott A. Morris, Chief Reactor Security Section Division of Nuclear Security Office of Nuclear Security and Incident Response

Enclosure:

As stated cc: See next page Docket No.:

50-361 and 50-362 WARNING: Violation of Section 147 of the Atomic Energy Act, Safeguards Information is subject to Civil and Criminal Penalties NOTICE: Enclosure transmitted herewith contains Safeguards Information. When separated from Enclosure(s) this Cover Document is DECONTROLLED

SAFEGUARDS INFORMATION SAFEGUARDS INFORMATION September 21, 2004 Mr. Dwight E. Nunn Vice President Southern California Edison Company San Onofre Nuclear Station, Units 2 and 3 P. O. Box 128 San Clemente, CA 92674-0128

SUBJECT:

SECURITY PLAN PROVISIONS FOR ENHANCED OWNER CONTROLLED AREA SURVEILLANCE AND RESPONSE (TAC NOS. MC2969 AND MC2970)

Dear Mr. Nunn:

On May 14, 2004, the U. S. Nuclear Regulatory Commissions (NRC) staff completed an evaluation of lessons learned from the pilot expanded force-on-force exercises. As a result of this evaluation, surveillance and response in the owner controlled area (OCA) was identified as one aspect of security at nuclear power plant facilities that required further improvement. On August 13, 2004, the Commission directed the staff to work with industry toward voluntary implementation of enhanced OCA surveillance and response measures.

The NRC staff worked with the industrys Security Working Group and the Nuclear Energy Institute to develop appropriate provisions to be included in physical security plans. These provisions have been discussed with your staff for incorporation into your facilities physical security plans. Specific revised security plan language developed to achieve this objective is included as an enclosure to this letter.

Thank you for your cooperation in resolving this issue. Should you have further questions on this matter, please call Juan Peralta at (301) 415-6689 or me at (301) 415-7083.

Sincerely,

/RA/

Scott A. Morris, Chief Reactor Security Section Division of Nuclear Security Office of Nuclear Security and Incident Response

Enclosure:

As stated cc: See next page Docket No.:

50-361 and 50-362 DISTRIBUTION:

SPRT R/F RFretz DHuyck JCreed BBenney BVaidya ACRS OGC MBurrell DSpaulding RManili PPeduzzi MChernoff BPham SDembek HBerkow AHowell, RIV Accession Number: ML042670243 OFFICE SPRT/LA SPRT SPRT SPRT NAME CHawes JPeralta JNakoski SMorris DATE 9/20/04 9/20/04 9/20/04 9/20/04 OFFICIAL RECORD COPY

San Onofre Nuclear Generating Station, Units 2 and 3 cc:

Mr. Raymond Waldo, Plant Manager Nuclear Generation Southern California Edison Company San Onofre Nuclear Generating Station P. O. Box 128 San Clemente, CA 92674-0128 Mr. Douglas K. Porter Southern California Edison Company 2244 Walnut Grove Avenue Rosemead, CA 91770 Mr. David Spath, Chief Division of Drinking Water and Environmental Management P. O. Box 942732 Sacramento, CA 94234-7320 Chairman, Board of Supervisors County of San Diego 1600 Pacific Highway, Room 335 San Diego, CA 92101 Eileen M. Teichert, Esq.

Supervising Deputy City Attorney City of Riverside 3900 Main Street Riverside, CA 92522 Mr. Gary L. Nolff Power Projects/Contracts Manager Riverside Public Utilities 2911 Adams Street Riverside, CA 92504 Regional Administrator, Region IV U.S. Nuclear Regulatory Commission 611 Ryan Plaza Drive, Suite 400 Arlington, TX 76011-8064 Mr. Michael Olson San Diego Gas & Electric Company P.O. Box 1831 San Diego, CA 92112-4150 Mr. Ed Bailey, Chief Radiologic Health Branch State Department of Health Services Post Office Box 997414 (MS7610)

Sacramento, CA 95899-7414 Resident Inspector/San Onofre NPS c/o U.S. Nuclear Regulatory Commission Post Office Box 4329 San Clemente, CA 92674 Mayor City of San Clemente 100 Avenida Presidio San Clemente, CA 92672 Mr. Dwight E. Nunn, Vice President Southern California Edison Company San Onofre Nuclear Generating Station P.O. Box 128 San Clemente, CA 92674-0128 Mr. James D. Boyd, Commissioner California Energy Commission 1516 Ninth Street (MS 31)

Sacramento, CA 95814 Mr. Joseph J. Wambold, Vice President Southern California Edison Company San Onofre Nuclear Generating Station P.O. Box 128 San Clemente, CA 92764-0128 Mr. Steve Hsu Department of Health Services Radiologic Health Branch MS 7610, P.O. Box 997414 Sacramento, CA 95899 Mr. Harold B. Ray Executive Vice President Southern California Edison Company San Onofre Nuclear Generating Station P.O. Box 128, Mail Stop: D-3-F San Clemente, CA 92674-0128