February 8, 2005 LICENSEE:
Nuclear Management Company, LLC FACILITY:
Point Beach Nuclear Plant, Units 1 and 2
SUBJECT:
SUMMARY
OF SEPTEMBER 2, 2004, MEETING WITH NUCLEAR MANAGEMENT COMPANY, LLC (NMC), REGARDING THE JUNE 25, 2004, POINT BEACH NUCLEAR PLANT EMERGENCY ACTION LEVEL (EAL)
CONVERSION SUBMITTAL (TAC NOS. MC3773 AND MC3774)
On September 2, 2004, a Category 1 public meeting was held between the U.S. Nuclear Regulatory Commission (NRC) and representatives of NMC at NRC Headquarters, One White Flint North, 11555 Rockville Pike, Rockville, Maryland. The purpose of the meeting was to facilitate discussion between NRC staff and NMC so the NRC staff could gather more information concerning NMCs June 25, 2004, Point Beach Emergency Action Level (EAL) conversion submittal. A list of attendees is provided as Enclosure 1.
During its acceptance review of the submittal, the NRC staff had identified instances where the proposed Point Beach EALs deviated/differed from the Nuclear Energy Institute (NEI) 99-01 EALs. The NRC staff sought clarification of the nature of these deviations/differences and whether the submittal contained deviations/differences in addition to those identified by the staff. During the meeting, NMC presented information that compared the proposed Point Beach EALs with the NEI 99-01 EALs (see Enclosure 2). Selected deviations/differences were identified and discussed, including examples of deviations from NEI 99-01 that had not been identified in the NMC submittal.
The NRC staff discussed its understanding of and comments regarding the submittal and the information presented by NMC. During the discussions, the NRC staff stated that deviations/differences from the NEI 99-01 EALs should have been clearly identified and justified/discussed in the submittal. The NRC staff discussions, however, do not constitute an NRC staff position. Furthermore, no regulatory decisions were made during the meeting.
The NRC staff also requested that NMC inform the NRC of a schedule for providing the NRC with a supplement to the original submittal. NMC did so on September 7, 2004, stating that October 8, 2004, was the planned submission date.
Please direct any inquiries to Harold Chernoff at 301-425-4018, or hkc@nrc.gov.
/RA/
Harold K. Chernoff, Project Manager, Section 1 Project Directorate III Division of Licensing Project Management Office of Nuclear Reactor Regulation Docket Nos. 50-266 and 50-301
Enclosures:
- 1. List of Attendees
- 2. Licensee Handouts cc w/encls: See next page
ML042610007 (Memo)
ADAMS Accession No.: ML042610011 (Attendees)
ADAMS Accession No.: ML042610035 (Matrix)
ADAMS Accession No.: ML042610044 (Presentation)
ADAMS Accession No.: ML042610058 (Package)
OFFICE PDIII-1/PM PDIII-1/PM PDIII-1/LA PDIII-1/LA PDIII-1/SC NAME HChernoff MCall THarris DClarke for THarris LRaghavan DATE 9/24/04 2/4/05 09/24/04 9/24/04 2/7/05 2/4/05
Point Beach Nuclear Plant, Units 1 and 2 cc:
Jonathan Rogoff, Esquire Vice President, Counsel & Secretary Nuclear Management Company, LLC 700 First Street Hudson, WI 54016 Mr. F. D. Kuester President & Chief Executive Officer WE Generation 231 West Michigan Street Milwaukee, WI 53201 Regulatory Affairs Manager Point Beach Nuclear Plant Nuclear Management Company, LLC 6610 Nuclear Road Two Rivers, WI 54241 Mr. Ken Duveneck Town Chairman Town of Two Creeks 13017 State Highway 42 Mishicot, WI 54228 Chairman Public Service Commission of Wisconsin P.O. Box 7854 Madison, WI 53707-7854 Regional Administrator, Region III U.S. Nuclear Regulatory Commission 801 Warrenville Road Lisle, IL 60532-4351 Resident Inspector's Office U.S. Nuclear Regulatory Commission 6612 Nuclear Road Two Rivers, WI 54241 Mr. Jeffery Kitsembel Electric Division Public Service Commission of Wisconsin P.O. Box 7854 Madison, WI 53707-7854 Nuclear Asset Manager Wisconsin Electric Power Company 231 West Michigan Street Milwaukee, WI 53201 John Paul Cowan Executive Vice President & Chief Nuclear Officer Nuclear Management Company, LLC 700 First Street Hudson, WI 54016 Douglas E. Cooper Senior Vice President - Group Operations Palisades Nuclear Plant Nuclear Management Company, LLC 27780 Blue Star Memorial Highway Covert, MI 49043 Site Director of Operations Nuclear Management Company, LLC 6610 Nuclear Road Two Rivers, WI 54241 Dennis L. Koehl Site Vice-President Nuclear Management Company, LLC 6590 Nuclear Road Two Rivers, WI 54241 July 2004