Letter Sequence RAI |
---|
|
|
MONTHYEARML0413504792004-05-17017 May 2004 Company - Supplemental Response to the April 29, 2003, Orders Modifying Licenses for Revised Design Basis Threat (TAC MC2974 and MC2975) Project stage: Other ML0417400602004-06-21021 June 2004 Co, Units 1 and 2, RAI, Security Plan Sections 10-19 Project stage: RAI ML0421101072004-07-23023 July 2004 Co, Units 1 and 2, RAI, Safeguards Contingency Plan and Section 9.4.1 of the Physical Security Plan (TAC Nos. MC2974 and MC2975) Project stage: RAI ML0431800102004-10-28028 October 2004 Company, Units 1 and 2, Administrative Change to Facility Operating License in Conjunction with the Commission Order EA-03-086 Regarding Revised Design Basis Threat... Project stage: Other 2004-05-17
[Table View] |
|
---|
Category:Letter
MONTHYEARML24029A2752024-01-29029 January 2024 Request to Reschedule Evaluated Force-on-Force Drill IR 05000498/20230042024-01-29029 January 2024 Integrated Inspection Report 05000498/2023004 and 05000499/2023004 ML24024A1162024-01-24024 January 2024 STP Unit 2 Request for Information IR 05000498/20244042024-01-18018 January 2024 Information Request for the Cyber-Security Baseline Inspection, Notification to Perform Inspection 05000498/2024404; 05000499/2024404 IR 05000498/20230032023-12-28028 December 2023 Acknowledgment of Reply to a Notice of Violation (NRC Inspection Report 05000498/2023003 and 05000499/2023003) ML23360A1692023-12-26026 December 2023 FEMA, Submittal of Radiological Emergency Preparedness Final Report for the South Texas Project Medical Services Drill Evaluated on August 31, 2023 NOC-AE-230040, Supplement to Proposed Alternate Frequency to Containment Unbonded Post-Tensioning System Inservice Inspection (Relief Request RR-ENG-4-06)2023-12-14014 December 2023 Supplement to Proposed Alternate Frequency to Containment Unbonded Post-Tensioning System Inservice Inspection (Relief Request RR-ENG-4-06) NOC-AE-230039, Docket Nos. Stn 50-498, Stn 50-499 - Reply to a Notice of Violation, NRC Inspection Report 05000498/2023003 and 05000499/20230032023-12-12012 December 2023 Docket Nos. Stn 50-498, Stn 50-499 - Reply to a Notice of Violation, NRC Inspection Report 05000498/2023003 and 05000499/2023003 ML23326A2592023-12-0505 December 2023 Review of the Fall 2022 Steam Generator Tube Inspection Report ML23339A1902023-12-0505 December 2023 Update Foreign Ownership, Control, or Influence (FOCI) IR 05000498/20234012023-12-0404 December 2023 Security Baseline Inspection Report 05000498/2023401 and 05000499/2023401 ML23324A0102023-11-16016 November 2023 Request for Exemption from Enhanced Weapons, Firearms Background Checks, and Security Event Notifications Implementation ML23310A2282023-11-13013 November 2023 Integrated Inspection Report 05000498/2023003 and 05000499/2023003, and Notice of Violation ML23311A2082023-11-0909 November 2023 Reassignment of U.S. Nuclear Regulatory Commission Branch Chief in the Division of Operating Reactor Licensing for Plant Licensing Branch IV ML23298A0002023-11-0101 November 2023 the Associated Independent Spent Fuel Storage Installation - Issuance of Amendment Nos. 226 and 211 Related to Order Approving Indirect Transfer of Licenses and Conforming License Amendments ML23303A0782023-10-30030 October 2023 Submittal of Supplemental Information in Response to Order Consenting to License Transfers and Approval of Draft Conforming License Amendments ML23279A0342023-10-30030 October 2023 Associated Independent Spent Fuel Storage Installation - Order Approving Indirect Transfer of Licenses and Draft Conforming License Amendments (EPID L-2023-LLM-0004) (Letter) IR 05000498/20234032023-10-26026 October 2023 Material Control and Accounting Program Inspection Report 05000498/2023403 and 05000499/2023403 (Cover Letter) ML23317A1262023-10-12012 October 2023 South. Texas Project Physical Security Plan, Training and Qualification Plan, Safeguards Contingency Plan, and Independent Spent Fuel Storage Installation Security Program Revision 26 ML23279A1382023-10-0505 October 2023 Responses to Requests for Additional Information Related to Application for Order Approving Indirect Transfer of Control of Licenses ML23271A1942023-10-0303 October 2023 Notification of Commercial Grade Dedication Inspection (05000498/2024013 and 05000499/2024013) and Request for Information ML23270B2592023-09-27027 September 2023 Update Foreign Ownership, Control, or Influence ML23263B1132023-09-20020 September 2023 Operator Licensing Examination Schedule Revision 1 IR 05000498/20243012023-09-0707 September 2023 Notification of NRC Initial Operator Licensing Examination 05000498/2024301; 05000499/2024301 IR 05000498/20233012023-09-0101 September 2023 NRC Examination Report 05000498/2023301 and 05000499/2023301 ML23243B0562023-08-31031 August 2023 Supplemental Information to Application for Order Approving Indirect Transfer of Control of Licenses ML23236A6042023-08-24024 August 2023 Annual Dose Report for 2022 IR 05000498/20230052023-08-22022 August 2023 Updated Inspection Plan for South Texas Project Electric Generating Station, Units 1 and 2 (Report 05000498/2023005 and 05000499/2023005) - Mid Cycle Letter ML23229A5262023-08-17017 August 2023 Inservice Inspection Summary Report - 1 RE24, ML23229A5892023-08-17017 August 2023 Voluntary Response to Regulatory Issue Summary (RIS) 2023-02, Scheduling Information for the Licensing of Accident Tolerant, Increased Enrichment, and Higher Burnup Fuels ML23229A4992023-08-17017 August 2023 Supplement to Proposed Alternate Frequency to Containment Unbonded Post-Tensioning System Inservice Inspection (Relief Request RR-ENG-4-06) ML23228A2102023-08-15015 August 2023 Closure of Investigation (OI 4-22-19) ML23222A0322023-08-10010 August 2023 Report of Changes Made to Quality Assurance Program for Radioactive Material Packages ML23221A3002023-08-0909 August 2023 RE22 Inspection Summary Report for Steam Generator Tubinq, Rev. 1 (Epld L-2023-LRO-0029) ML23222A2792023-08-0909 August 2023 Submittal of Update Foreign Ownership, Control, or Influence (FOCI) IR 05000498/20230022023-07-28028 July 2023 Integrated Inspection Report 05000498/2023002 and 05000499/2023002 ML23198A0532023-07-24024 July 2023 Request for Withholding Information from Public Disclosure ML23188A1612023-07-14014 July 2023 the Associated ISFSI - Notice of Consideration of Approval of Indirect Transfer of Licenses and Conforming Amendments and Opportunity to Request a Hearing (EPID L-2023-LLM-0004) - Letter ML23193A9932023-07-11011 July 2023 Submittal of Update Foreign Ownership, Control or Influence (FOCI) ML23192A0482023-07-11011 July 2023 NRC Initial Operator Licensing Examination Approval 05000498/2023301; 05000499/2023301 NOC-AE-230039, Submittal of Update Foreign Ownership, Control or Influence (FOCI)2023-07-11011 July 2023 Submittal of Update Foreign Ownership, Control or Influence (FOCI) ML23180A2822023-06-29029 June 2023 Operator Licensing Examination Schedule ML23177A2522023-06-26026 June 2023 Units 1, 2 & Independent Spent Fuel Storage Installation - Biennial Submittal of Technical Specification Bases Changes, Commitment Changes, 10 CFR 50.59 Evaluation Summary, and 10 CFR 72.48 Evaluation Summary ML23166B0802023-06-14014 June 2023 Update Foreign Ownership, Control, or Influence (FOCI) ML23163A1762023-06-12012 June 2023 Application for Order Approving Indirect Transfer of Control of Licenses 2024-01-29
[Table view] Category:Request for Additional Information (RAI)
MONTHYEARML24024A1162024-01-24024 January 2024 STP Unit 2 Request for Information ML23334A0062023-11-29029 November 2023 NRR E-mail Capture - South Texas Project - Request for Additional Information - Proposed Alternative to ASME BPV Code Requirements ML23319A4442023-11-15015 November 2023 NRR E-mail Capture - South Texas Project - Draft Request for Additional Information - Proposed Alternative to ASME BPV Code Requirements ML23278A1532023-10-0505 October 2023 NRR E-mail Capture - South Texas Project Request for Additional Information - Request for Indirect Transfer of Licenses and Conforming Amendments (L-2023-LLM-0004) ML23264A0972023-09-21021 September 2023 NRR E-mail Capture - South Texas Project - Request for Additional Information - License Amendment Request to Revise the Alternate Source Term Dose Calculation (L-2023-LLA-0047) ML23255A2862023-09-12012 September 2023 NRR E-mail Capture - South Texas Project Draft Request for Additional Information License Amendment Request to Revise the Alternate Source Term Dose Calculation (L-2023-LLA-0047) ML23145A1872023-05-24024 May 2023 July 2023 Emergency Preparedness Program Inspection - Request for Information ML22255A1542022-09-13013 September 2022 Operating Company Information Request for the Cyber Security Baseline Inspection 05000498/2022401 and 05000499/2022401 ML22206A0142022-07-20020 July 2022 NRR E-mail Capture - South Texas Project - Request for Additional Information - 10 CFR 20.2002 Alternate Disposal Request ML22194A0502022-07-0707 July 2022 NRR E-mail Capture - South Texas Project - Updated Draft Request for Additional Information - 10 CFR 20.2002 Alternate Disposal Request ML22194A0492022-06-0808 June 2022 NRR E-mail Capture - South Texas Project - Draft Request for Additional Information - 10 CFR 20.2002 Alternate Disposal Request ML22123A3272022-05-0303 May 2022 STP EP Exercise Inspection July 2022 RFI ML22084A0762022-04-0404 April 2022 Notification of NRC Design Bases Assurance Inspection (Team) (05000498/2022012 and 05000499/2022012) and Request for Information ML21286A5732021-10-18018 October 2021 Notification of NRC Design Bases Assurance Inspection (Programs) (05000498/2022011 and 05000499/2022011) and Request for Information ML21166A2392021-06-16016 June 2021 Notification of Inspection (NRC Inspection Report 05000498/2021003 and 05000499/2021003) and Request for Information ML21160A1522021-06-0909 June 2021 Request for Information NRC Inspection 2021-003 Public Radiation Safety ML21133A2372021-05-0505 May 2021 Request for Additional Information: STP EP Exercise Inspection - July 2021 ML21039A8902021-02-0808 February 2021 NRR E-mail Capture - South Texas Project - Request for Additional Information - 1RE22 Inspection Summary Report for Steam Generator Tubing ML21029A3312021-01-29029 January 2021 NRR E-mail Capture - South Texas Project - Draft Request for Additional Information - 1RE22 Inspection Summary Report for Steam Generator Tubing ML20280A5452020-08-17017 August 2020 STP 2020 PIR Request for Information ML20111A0052020-04-17017 April 2020 NRR E-mail Capture - South Texas Project - Request for Additional Information - Proposed Alternative to ASME OM Code 2012 Edition - Relief Request PRR-01 ML20070N0222020-03-10010 March 2020 NRC Selection for Onsite Review ML20057G4612020-02-26026 February 2020 05000498/499 Request for Information - Occupational Radiation Safety Inspection ML20045E2172020-02-13013 February 2020 Licensed Operator Positive Fitness-For-Duty Test ML20036F5862020-02-0404 February 2020 Request for Additional Information - Proposed Alternative to ASME Code Requirements for the Repair of Essential Cooling Water System Class 3 Buried Piping (EPID L-2019-LLR-0096)Redacted ML19165A1032019-06-14014 June 2019 NRR E-mail Capture - Draft RAI for STP TS 3.8.1.1 Sbdg SR Change ML19081A1512019-03-21021 March 2019 NRR E-mail Capture - Draft Round 2 RAI - Sbdg Voltage and Frequency LAR (L-2018-LLA-0078) ML18283B9522018-10-10010 October 2018 NRR E-mail Capture - Final RAI - South Texas Standby DG TS Change (L-2018-LLA-0078) ML18263A1432018-09-12012 September 2018 NRR E-mail Capture - Final RAI for South Texas Project RR-ENG-E-16 (L-2018-LLR-0097) ML18197A4172018-07-17017 July 2018 Notification of NRC Triennial Heat Sink Performance Inspection (05000498/2018003 and 05000499/2018003) and Request for Information ML18003B4222018-01-0303 January 2018 NRR E-mail Capture - Final Request for Additional Information Amendment Request to Modify the Emergency Response Organization for South Texas Project ML17229B4672017-08-16016 August 2017 Notification of NRC Inspection 05000499/2017008 and Request for Information ML17132A0712017-05-15015 May 2017 Information Request the Cyber Security Baseline Inspection, Notification to Perform Inspection 05000498/2017407; 05000499/2017407 ML17103A6272017-04-13013 April 2017 Notification of Evaluations of Changes, Tests, and Experiments Inspection (05000498/2017007 and 05000499/2017007) and Request for Information ML16351A1502016-12-16016 December 2016 Correction Letter Closeout of Request for Information Questions That Are No Longer Applicable Associated with the Resolution of Generic Safety Issue 191 (CAC Nos. MF2400 - MF2409) ML16302A4532016-12-12012 December 2016 Closeout of Request for Additional Information Questions That Are No Longer Applicable, Resolution of Generic Safety Issue (GSI) 191 (CAC Nos. MF2400-MF2409) ML16343A0422016-12-0808 December 2016 Request for Additional Information for the Review of the South Texas Project, Units 1 and 2 License Renewal Application (CAC NOS. ME4936, ME4937) ML16340A1022016-12-0505 December 2016 Requests for Additional Information for the Review of the South Texas Project License Renewal Application (CAC Nos. ME4936 and ME4937) ML16246A0952016-09-15015 September 2016 Correction to 8/26/16 Request for Additional Information Enclosure, License Amendment Request to Revise Technical Specification 5.3.2 to Allow Operation with 56 Full-Length Control Rod Assemblies ML16214A2912016-08-26026 August 2016 Summary of June 28-30, 2016, Regulatory Audit at Westinghouse in Rockville, MD, License Amendment Request to Revise Technical Specification 5.3.2 to Allow Operation with 56 Full-Length Control Rod Assemblies ML16187A0522016-07-0707 July 2016 Request for Additional Information Regarding License Renewal Application ML16141B0812016-05-31031 May 2016 Audit Summary, Risk Audit on April 12-13, 2016, at Alumni Center at the University of Texas, Austin, Tx; Pilot Generic Safety Issue 191 Submittal and Exemption Request, and Draft Request for Additional Information ML16125A2902016-05-26026 May 2016 Request for Additional Information, Risk Review, Exemption and License Amendment Request for a Risk-Informed Approach to Resolve Generic Safety Issue (GSI)-191 (CAC Nos. MF2400-MF2409) ML16127A4522016-05-12012 May 2016 Supplemental Information Needed for Acceptance of Requested Licensing Action, Amendment Request to Revise Technical Specification 5.3.2 to Allow Operation with 56 Full-Length Control Rod Assemblies ML16104A3522016-04-22022 April 2016 Requests for Additional Information Set 35 for the Review of the South Texas Project License Renewal Application (Tac Nos. ME4936, ME4937) ML16082A5072016-04-11011 April 2016 Request for Additional Information, Phased Response Requested, Exemption and License Amendment Request for a Risk-Informed Approach to Resolve Generic Safety Issue (GSI)-191 (CAC Nos. MF2400-MF2409) ML16082A4842016-03-22022 March 2016 NRR E-mail Capture - South Texas Project Units 1 & 2, Draft Request for Additional Information for Risk Review for GSI-191 ML16081A0042016-03-18018 March 2016 NRR E-mail Capture - South Texas Project Units 1 & 2, Draft Request for Additional Information for Thermal-hydraulic Review for GSI-191 ML16053A1872016-03-0101 March 2016 Request for Additional Information, Request to Revise Technical Specification 6.8.3.j, Containment Leakage Rate Testing Program, to Extend Integrated Leak Rate Test Interval from 10 to 15 Years (CAC MF6176-MF6177) ML16060A2872016-02-29029 February 2016 NRR E-mail Capture - Request for Additional Information - STP LRA Safety Review 2024-01-24
[Table view] |
Text
July 23, 2004 Mr. James J. Sheppard President and Chief Executive Officer South Texas Project Nuclear Operating Company P. O. Box 289 Wadsworth, TX 77483
SUBJECT:
SOUTH TEXAS PROJECT ELECTRIC GENERATING COMPANY, UNITS 1 AND 2 - REQUEST FOR ADDITIONAL INFORMATION RE: SAFEGUARDS CONTINGENCY PLAN AND SECTION 9.4.1 OF THE PHYSICAL SECURITY PLAN (TAC NOS. MC2974 AND MC2975)
Dear Mr. Sheppard:
In response to the April 29, 2003, Orders revising the design basis threat, you submitted a revised physical security plan, safeguards contingency plan, and training and qualification plan, including an implementation schedule, for South Texas Project Electric Generating Company, Units 1 and 2.
The Nuclear Regulatory Commission staff is reviewing your submission and has determined that a request for additional information (RAI) is necessary in order to complete its evaluation based on its review of your Safeguards Contingency Plan and Section 9.4.1 of the Physical Security Plan. Please respond to the enclosed RAI within 10 days from the receipt of this letter.
If circumstances result in the need to revise the target response date, please contact me at (301) 415-1460.
Sincerely,
/RA/
Brian Benney, Project Manager Security Plan Review Team Division of Licensing Project Management Office of Nuclear Reactor Regulation Docket Nos. 50-498 and 50-499
Enclosure:
As stated cc w/o encl: See next page NOTICE: The Enclosure contains Safeguards WARNING: Violation of Section 147 of Information. Upon separation from the the Atomic Energy Act, Safeguards Enclosure, this letter is DECONTROLLED.
Information is subject to Civil and Criminal Penalties SAFEGUARDS INFORMATION
July23, 2004 Mr. James J. Sheppard President and Chief Executive Officer South Texas Project Nuclear Operating Company P. O. Box 289 Wadsworth, TX 77483
SUBJECT:
SOUTH TEXAS PROJECT ELECTRIC GENERATING COMPANY, UNITS 1 AND 2 - REQUEST FOR ADDITIONAL INFORMATION RE: SAFEGUARDS CONTINGENCY PLAN AND SECTION 9.4.1 OF THE PHYSICAL SECURITY PLAN (TAC NOS. MC2974 AND MC2975)
Dear Mr. Sheppard:
In response to the April 29, 2003, Orders revising the design basis threat, you submitted a revised physical security plan, safeguards contingency plan, and training and qualification plan, including an implementation schedule, for South Texas Project Electric Generating Company, Units 1 and 2.
The Nuclear Regulatory Commission staff is reviewing your submission and has determined that a request for additional information (RAI) is necessary in order to complete its evaluation based on its review of your Safeguards Contingency Plan and Section 9.4.1 of the Physical Security Plan. Please respond to the enclosed RAI within 10 days from the receipt of this letter.
If circumstances result in the need to revise the target response date, please contact me at (301) 415-1460.
Sincerely,
/RA/
Brian Benney, Project Manager Security Plan Review Team Division of Licensing Project Management Office of Nuclear Reactor Regulation Docket Nos. 50-498 and 50-499
Enclosure:
As stated cc w/o encl: See next page DISTRIBUTION:
SPRT R/F M. Webb RidsNsirDns R. Gramm RidsNrrDlpm H. Berkow OGC A. Howell, RIV ACRS ADAMS Accession Number: ML042110107 OFFICE SPRT/NRR/PM SPRT/NRR/LA SPRT/NSIR SPRT/NRR/SC NAME BBenney CHawes JPeralta JNakoski DATE 07/23/04 07/22/04 07/23/04 07/23/04 OFFICIAL RECORD COPY
South Texas Project, Units 1 & 2 cc: S. M. Head, Manager, Licensing Nuclear Quality & Licensing Department Senior Resident Inspector STP Nuclear Operating Company U.S. Nuclear Regulatory Commission P. O. Box 289, Mail Code: N5014 P. O. Box 910 Wadsworth, TX 77483 Bay City, TX 77414 Environmental and Natural Resources A. Ramirez/C. M. Canady Policy Director City of Austin P. O. Box 12428 Electric Utility Department Austin, TX 78711-3189 721 Barton Springs Road Austin, TX 78704 Jon C. Wood Matthews & Branscomb Mr. L. K. Blaylock 112 East Pecan, Suite 1100 Mr. W. C. Gunst San Antonio, TX 78205 City Public Service Board P. O. Box 1771 Arthur C. Tate, Director San Antonio, TX 78296 Division of Compliance & Inspection Bureau of Radiation Control Mr. C. A. Johnson/A. C. Bakken Texas Department of Health AEP Texas Central Company 1100 West 49th Street P. O. Box 289 Austin, TX 78756 Mail Code: N5022 Wadsworth, TX 77483 Brian Almon Public Utility Commission INPO William B. Travis Building Records Center P. O. Box 13326 700 Galleria Parkway 1701 North Congress Avenue Atlanta, GA 30339-3064 Austin, TX 78701-3326 Regional Administrator, Region IV Susan M. Jablonski U.S. Nuclear Regulatory Commission Office of Permitting, Remediation 611 Ryan Plaza Drive, Suite 400 and Registration Arlington, TX 76011 Texas Commission on Environmental Quality D. G. Tees/R. L. Balcom MC-122 Texas Genco, LP P.O. Box 13087 P. O. Box 1700 Austin, TX 78711-3087 Houston, TX 77251 Mr. Terry Parks, Chief Inspector Judge, Matagorda County Texas Department of Licensing Matagorda County Courthouse and Regulation 1700 Seventh Street Boiler Division Bay City, TX 77414 P. O. Box 12157 Austin, TX 78711 A. H. Gutterman, Esq. Mr. Ted Enos Morgan, Lewis & Bockius 4200 South Hulen 1111 Pennsylvania Avenue, NW Suite 630 Washington, DC 20004 Ft. Worth, Texas 76109 Mr. T. J. Jordan, Vice President Engineering & Technical Services STP Nuclear Operating Company P. O. Box 289 Wadsworth, TX 77483