ML041940199

From kanterella
Jump to navigation Jump to search

Technical Specifications, Issuance of Amendment Regarding Primary Containment and Drywell Isolation Instrumentation to Increase the Analytical Limit for Detected Temperature
ML041940199
Person / Time
Site: Perry 
Issue date: 07/09/2004
From:
NRC/NRR/DLPM
To:
Sands S, 415-3154, NRR/DLPM
Shared Package
ML041960518 List:
References
TAC MC0342
Download: ML041940199 (1)


Text

Primary Containment and Drywell Isolation Instrumentation 3.3.6.1 Table 3.3.6.1-1 (page 1 of 6)

Primary Containment and Drywell Isolation Instrumentation APPLICABLE CONDITIONS MOOES OR REQUIRED REFERENCED OTHER CHANNELS FROM SPECIFIED PER TRIP REQUIRED SURVEILLANCE ALLOWABLE FUNCTION CONDITIONS SYSTEM ACTION C.1 REQUIREMENTS VALUE

1. Hain Steam Line Isolation
a. Rcactor Vessel Water Level-Low Low Low, Level 1
b. Main Steam Line Pressure-Low 1,2,3 1

2 2

D SR 3.3.6.1.1 SR 3.3.6.1.2 SR 3.3.6.1.3 SR 3.3.6.1.4 SR 3.3.6.1.5 SR 3.3.6.1.6 E

SR 3.3.6.1.1 SR 3.3.6.1.2 SR 3.3.6.1.3 SR 3.3.6.1.L SR 3.3.6.1.5 SR 3.3.6.1.6

> 14.3 inches a 795.2 psig

c. Main Steam Line Flow-High 1,2,3 2 per MSL D

SR 3.3.6.1.1 SR 3.3.6.1.2 SR 3.3.6.1.3 SR 3.3.6.1.4 SR 3.3.6.1.5 SR 3.3.6.1.6 S 256.5 psid

d. Condenser Vacuum -Low 1,2(a),

3 (a) 2 D

SR 3.3.6.1.1 SR 3.3.6.1.2 SR 3.3.6.1.3 SR 3.3.6.1.4 SR 3.3.6.1.5 2 7.6 inches Hg vacuum

e.

Main Steam Line Pipe Tunnel Teffperature-High

f. Main Steam Line Turbine Building Temperature-High
9. Manual Initiation 1,2,3 1,2,3 2

2 D

SR 3.3.6.1.1 SR 3.3.6.1.2 SR 3.3.6.1.4 SR 3.3.6.1.5 SR 3.3.6.1.7 D

SR 3.3.6.1.1 SR 3.3.6.1.2 SR 3.3.6.1.4 SR 3.3.6.1.5 G

SR 3.3.6.1.5 C 158.9F S 149.6 0F I

1,2,3 NA

2. Primary Containment and Drywell Isolation
a. Reactor vessel Water Level-Low Lou, Level 2 1,2,3 2(b)

H SR 3.3.6.1.1 SR 3.3.6.1.2 SR -3.3.6.1.3 SR 3.3.6.1.4 SR 3.3.6.1.5

> 127.6 inches (continued)

(a) with any turbine stop valve not closed.

(b) Required to initiate the associated dryweal isolation function.

PERRY - UNIT I 3.3-54 AEmendment No. 130