Text

Primary Containment and Drywell Isolation Instrumentation 3.3.6.1 Table 3.3.6.1-1 (page 1 of 6)

Primary Containment and Drywell Isolation Instrumentation APPLICABLE CONDITIONS MOOES OR REQUIRED REFERENCED OTHER CHANNELS FROM SPECIFIED PER TRIP REQUIRED SURVEILLANCE ALLOWABLE FUNCTION CONDITIONS SYSTEM ACTION C.1 REQUIREMENTS VALUE

1. Hain Steam Line Isolation
a. Rcactor Vessel Water 1,2,3 2 D SR 3.3.6.1.1 > 14.3 inches Level- Low Low Low, SR 3.3.6.1.2 Level 1 SR 3.3.6.1.3 SR 3.3.6.1.4 SR 3.3.6.1.5 SR 3.3.6.1.6
b. Main Steam Line 1 2 E SR 3.3.6.1.1 a 795.2 psig Pressure- Low SR 3.3.6.1.2 SR 3.3.6.1.3 SR 3.3.6.1.L SR 3.3.6.1.5 SR 3.3.6.1.6
c. Main Steam Line 1,2,3 2 per MSL D SR 3.3.6.1.1 S 256.5 psid Flow- High SR 3.3.6.1.2 SR 3.3.6.1.3 SR 3.3.6.1.4 SR 3.3.6.1.5 SR 3.3.6.1.6
d. Condenser Vacuum -Low 1,2(a), 2 D SR 3.3.6.1.1 2 7.6 inches SR 3.3.6.1.2 Hg vacuum 3 (a) SR 3.3.6.1.3 SR 3.3.6.1.4 SR 3.3.6.1.5
e. Main Steam Line Pipe 1,2,3 2 D SR 3.3.6.1.1 C 158.9F Tunnel Teffperature- SR 3.3.6.1.2 High SR 3.3.6.1.4 SR 3.3.6.1.5 SR 3.3.6.1.7
f. Main Steam Line S 149.6 0F Turbine Building Temperature-High 1,2,3 2 D SR SR SR 3.3.6.1.1 3.3.6.1.2 3.3.6.1.4 I

SR 3.3.6.1.5

9. Manual Initiation 1,2,3 G SR 3.3.6.1.5 NA
2. Primary Containment and Drywell Isolation
a. Reactor vessel Water 1,2,3 H SR 3.3.6.1.1 > 127.6 inches Level- Low Lou, Level 2 2 (b) SR 3.3.6.1.2 SR -3.3.6.1.3 SR 3.3.6.1.4 SR 3.3.6.1.5 (continued)

(a) with any turbine stop valve not closed.

(b) Required to initiate the associated dryweal isolation function.

PERRY - UNIT I 3.3-54 AEmendment No. 130