Letter Sequence RAI |
---|
|
|
MONTHYEARML0307700442003-03-18018 March 2003 Request for Additional Information (Rai), Request for Change to Technical Specifications Relating to Containment Closure and Fuel Handling Area Ventilation Requirements Project stage: RAI ML0417004152004-06-24024 June 2004 Facsimile Transmission, Draft Request for Additional Information (RAI) to Be Discussed in an Upcoming Conference Call Project stage: Draft RAI ML0418901682004-07-16016 July 2004 RAI, Request for Change to Technical Specifications - Relaxation of Requirements Applicable During Movement of Irradiated Fuel Project stage: RAI ML0424504762004-09-16016 September 2004 Units, 1 and 2, License Amendments 263 and 245, Relax Technical Specification Requirements Applicable During Movement of Irradiated Fuel Project stage: Acceptance Review ML0426103122004-09-16016 September 2004 Units, 1 and 2, Technical Specifications, Relax Technical Specification Requirements Applicable During Movement of Irradiated Fuel Project stage: Other 2004-06-24
[Table View] |
Similar Documents at Salem |
---|
Category:Letter
MONTHYEARIR 05000272/20230042024-02-0505 February 2024 Integrated Inspection Report 05000272/2023004 and 05000311/2023004 ML24009A1022024-01-26026 January 2024 Exemption from Select Requirements of 10 CF Part 73 (EPID L-2023-LLE-0045 (Security Notifications, Reports, and Recordkeeping and Suspicious Activity Reporting)) IR 05000272/20234012024-01-22022 January 2024 Material Control and Accounting Program Inspection Report 05000272/2023401 and 05000311/2023401 ML24004A1542024-01-0808 January 2024 Notification of Conduct of a Fire Protection Team Inspection LR-N23-0079, Special Report 23-02-00 Pursuant to the Requirements of Salem Unit 1 Technical Specification 3.3.3.7, Action 10, for the Unit 1 Main Steam Line Rad Monitor Inoperable for Greater than Seven Days2023-12-0707 December 2023 Special Report 23-02-00 Pursuant to the Requirements of Salem Unit 1 Technical Specification 3.3.3.7, Action 10, for the Unit 1 Main Steam Line Rad Monitor Inoperable for Greater than Seven Days ML23270C0072023-11-29029 November 2023 Notice of Proposed Amendment to Decommissioning Trust Agreement LR-N23-0077, Loss of Coolant Accident Peak Cladding Temperature Margin Tracking - Annual Report 2023 & 30 Day Report for Salem Unit 1 Upflow Conversion2023-11-29029 November 2023 Loss of Coolant Accident Peak Cladding Temperature Margin Tracking - Annual Report 2023 & 30 Day Report for Salem Unit 1 Upflow Conversion ML23324A3072023-11-17017 November 2023 Request for Exemption from Enhanced Weapons, Firearms Background Checks, and Security Event Notifications Implementation IR 05000272/20230032023-11-13013 November 2023 Integrated Inspection Report 05000272/2023003 and 05000311/2023003 LR-N23-0072, Core Operating Limits Report Cycle 302023-11-0101 November 2023 Core Operating Limits Report Cycle 30 IR 05000272/20230102023-10-12012 October 2023 Biennial Problem Identification and Resolution Inspection Report O5000272/2023010 and 05000311/2023010 IR 05000272/20234022023-10-12012 October 2023 and Salem Nuclear Generating Station, Units 1 and 2 - Security Baseline Inspection Report 05000354/2023402, 05000272/2023402 and 05000311/2023402 (Cover Letter Only) LR-N23-0045, and Peach Bottom Atomic Power Station, Units 2 and 3 - Notice of Proposed Amendment to Decommissioning Trust Agreement2023-09-0808 September 2023 and Peach Bottom Atomic Power Station, Units 2 and 3 - Notice of Proposed Amendment to Decommissioning Trust Agreement ML23249A2612023-09-0606 September 2023 License Amendment Request to Modify the Salem and Hope Creek Exclusion Area Boundary IR 05000272/20230052023-08-31031 August 2023 Updated Inspection Plan for Salem Nuclear Generating Station, Units 1 and 2 (Reports 05000272/2023005 and 05000311/2023005) ML23233A0762023-08-21021 August 2023 Requalification Program Inspection ML23192A8212023-08-14014 August 2023 and Salem Nuclear Generating Station, Unit Nos. 1 and 2 - Issuance of Amendment Nos. 234, 347, and 329 Revise Technical Specifications to Delete Meteorological Tower Location IR 05000272/20230022023-08-0909 August 2023 Integrated Inspection Report 05000272/2023002 and 05000311/2023002 LR-N23-0055, Special Report 272/23-01-00, Pursuant to the Requirements of Technical Specification 3.3.3.1, Action 23, for the Vent Noble Gas Rad Monitor Inoperable for Greater than Seven Days2023-08-0303 August 2023 Special Report 272/23-01-00, Pursuant to the Requirements of Technical Specification 3.3.3.1, Action 23, for the Vent Noble Gas Rad Monitor Inoperable for Greater than Seven Days IR 05000354/20230022023-08-0303 August 2023 Integrated Inspection Report 05000354/2023002 and Independent Spent Fuel Storage Installation Inspection Report 07200048/2023001 LR-N23-0054, In-Service Inspection Activities2023-07-26026 July 2023 In-Service Inspection Activities LR-N23-0046, Emergency Plan Document Revisions Implemented June 28, 20232023-07-10010 July 2023 Emergency Plan Document Revisions Implemented June 28, 2023 LR-N23-0005, License Amendment Request to Amend Technical Specifications (TS) 6.8.4.f for Permanent Extension of Type a and Type C Leak Rate Test Frequencies2023-06-23023 June 2023 License Amendment Request to Amend Technical Specifications (TS) 6.8.4.f for Permanent Extension of Type a and Type C Leak Rate Test Frequencies ML23139A1472023-06-0505 June 2023 Relief Request Associated with Fourth Interval In-service Inspection Limited Examinations of Weld Coverage ML23096A1842023-05-0909 May 2023 Issuance of Amendment No. 328 Revise and Relocate Reactor Coolant System Pressure and Temperature Limits and Pressurizer Overpressure Protection System Limits to Pressure and Temperature Limits Report IR 05000272/20230012023-05-0303 May 2023 Integrated Inspection Report 05000272/2023001 and 05000311/2023001 ML23081A4662023-05-0202 May 2023 Issuance of Amendment Nos. 346 and 327 Revise Technical Specifications to Extend Allowable Outage Time for Inoperable Emergency Diesel Generator IR 05000272/20233012023-05-0101 May 2023 Initial Operator Licensing Examination Report 05000272/2023301 and 05000311/2023301 LR-N23-0034, 2022 Annual Radiological Environmental Operating Report (AREOR) - Salem Nuclear Generating Station, Unit Nos. 1 and 2 and Hope Creek Generating Station2023-04-27027 April 2023 2022 Annual Radiological Environmental Operating Report (AREOR) - Salem Nuclear Generating Station, Unit Nos. 1 and 2 and Hope Creek Generating Station LR-N23-0035, 2022 Annual Radioactive Effluent Release Report (ARERR)2023-04-27027 April 2023 2022 Annual Radioactive Effluent Release Report (ARERR) LR-N23-0033, Core Operating Limits Report Cycle 272023-04-26026 April 2023 Core Operating Limits Report Cycle 27 LR-N23-0010, License Amendment Request Revision of Technical Specification (TS) to Delete TS Section 5.5 - Meteorological Tower Location2023-04-21021 April 2023 License Amendment Request Revision of Technical Specification (TS) to Delete TS Section 5.5 - Meteorological Tower Location ML23089A0942023-04-17017 April 2023 NRC to PSEG Hope Creek, Transmittal of the National Marine Fisheries Service'S March 24, 2023, Biological Opinion GAR-2020-02842 Concerning Salem and Hope Creek ML23087A1492023-04-17017 April 2023 NRC to PSEG Salem, Transmittal of the National Marine Fisheries Service'S March 24, 2023, Biological Opinion GAR-2020-02842 Concerning Salem and Hope Creek ML23103A3232023-04-13013 April 2023 Submittal of Updated Final Safety Analysis Report, Rev. 26, Summary of Revised Regulatory Commitments for Hope Creek, Summary of Changes to PSEG Nuclear LLC, Quality Assurance Topical Report, NO-AA-10, Rev. 89 ML23095A3682023-04-12012 April 2023 and Salem Nuclear Generating Station, Unit Nos. 1 and 2 - Threshold Determination for Proposed Transfer of Land Ownership LR-N23-0006, Report on Status of Decommissioning Funding for Reactors and Independent Spent Fuel Storage Installations2023-03-24024 March 2023 Report on Status of Decommissioning Funding for Reactors and Independent Spent Fuel Storage Installations ML23086A0912023-03-24024 March 2023 NMFS to NRC, Transmittal of Biological Opinion for Continued Operations of Salem and Hope Creek Nuclear Generating Stations RS-23-049, Constellation Energy Generation, LLC, Report on Status of Decommissioning Funding for Reactors and Independent Spent Fuel Storage Installations2023-03-23023 March 2023 Constellation Energy Generation, LLC, Report on Status of Decommissioning Funding for Reactors and Independent Spent Fuel Storage Installations LR-N23-0019, and Salem Generating Station, Units 1 and 2 - Guarantees of Payment of Deferred Premiums2023-03-21021 March 2023 and Salem Generating Station, Units 1 and 2 - Guarantees of Payment of Deferred Premiums ML23044A1052023-03-13013 March 2023 Issuance of Amendment Nos. 345 and 326 Relocate Technical Specifications Requirements for Reactor Head Vents to Technical Requirements Manual ML23037A9712023-03-0909 March 2023 and Salem Nuclear, Unit Nos. 1 and 2 Issuance of Amendment Nos. 233, 344, and 325 Relocate Technical Specification Staff Qualification Requirements to the PSEG Quality Assurance Topical Report IR 05000272/20230112023-03-0707 March 2023 Comprehensive Engineering Team Inspection Report 05000272/2023011 and 05000311/2023011 IR 05000272/20220062023-03-0101 March 2023 Annual Assessment Letter for Salem Nuclear Generating Station, Units 1 and 2 (Reports 05000272/2022006 and 05000311/2022006) LR-N23-0016, and Salem Generating Station, Units 1 and 2 - Report of Changes, Tests, and Experiments2023-02-28028 February 2023 and Salem Generating Station, Units 1 and 2 - Report of Changes, Tests, and Experiments LR-N23-0012, Annual Property Insurance Status Report2023-02-24024 February 2023 Annual Property Insurance Status Report LR-N23-0014, Stations Submittal of 2022 Annual Report of Fitness for Duty Performance Data Per 10 CFR 26.203(e) and 10 CFR 26.7172023-02-23023 February 2023 Stations Submittal of 2022 Annual Report of Fitness for Duty Performance Data Per 10 CFR 26.203(e) and 10 CFR 26.717 ML23034A1532023-02-0909 February 2023 Operator Licensing Examination Approval ML23019A3482023-02-0202 February 2023 Issuance of Relief Request No. SC-I5R-221 for the Alternative Repair for Service Water System Piping LR-N23-0003, Response to Requests for Additional Information Salem Unit 2 Relief Request S2-I4R-2112023-02-0101 February 2023 Response to Requests for Additional Information Salem Unit 2 Relief Request S2-I4R-211 2024-02-05
[Table view] Category:Request for Additional Information (RAI)
MONTHYEARML22333A9022022-11-29029 November 2022 NRR E-mail Capture - Final Iolb RAI - Salem 1 and 2 LAR to Revise TS to Extend Allowed Outage Time for Inoperable EDG ML22318A1062022-11-14014 November 2022 Information Request for Quadrennial Baseline Comprehensive Engineering Team Inspection; Notification to Perform Inspection 05000272/2023011 and 05000311/2023011 ML22290A2202022-10-17017 October 2022 NRR E-mail Capture - Final RAI - Salem 1 and 2 LAR to Revise TS to Extend Allowed Outage Time for Inoperable EDG ML22055A0702022-02-22022 February 2022 NRR E-mail Capture - Final RAI - Salem 1-Relief Request Associated with Fourth Inservice Inspection (ISI) Interval Limited Examinations (L-2021-LLR-0085) ML21256A1902021-09-10010 September 2021 NRR E-mail Capture - Exelon Generation Company, LLC - Request for Additional Information Regarding License Transfer Application ML21144A2132021-05-24024 May 2021 NRR E-mail Capture - Exelon Generation Company, LLC - Request for Additional Information Regarding License Transfer Application ML21068A4142021-03-0909 March 2021 NRR E-mail Capture - Final RAI for Salem Unit 1 LAR to Revise and Relocate Pressurizer Overpressure Protection System Limits to Pressure and Temperature Limits Report ML21043A1442021-02-11011 February 2021 NRR E-mail Capture - Salem - Final RAI Alternative for Examination of ASME Section XI, Category B-B, Item Number B2.11and B2.12 (L-2020-LRR-0103) ML21021A2592021-01-21021 January 2021 NRR E-mail Capture - Final RAI - Salem 1 - Steam Generator Tube Inspection Report ML20281A5172020-10-13013 October 2020 Notification of Conduct of a Fire Protection Team Inspection ML18267A1712018-09-21021 September 2018 NRR E-mail Capture - Final RAI from PRA Branch: Revise Technical Specifications to Increase Inverter AOT Extension (L-2018-LLA-0140) ML18264A0122018-09-20020 September 2018 NRR E-mail Capture - Final RAI from I&C Branch: Revise Technical Specifications to Increase Inverter AOT Extension (L-2018-LLA-0140) ML18250A3132018-09-0606 September 2018 NRR E-mail Capture - Final RAI: Revise Technical Specifications to Increase Inverter AOT Extension (L-2018-LLA-0140) ML18171A3212018-06-20020 June 2018 NRR E-mail Capture - Final RAI: Revise Technical Specifications to Adopt TSTF-411 and 418 (L-2017-LLA-0442) ML18094B0832018-04-0505 April 2018 Enclosurequest for Additional Information (Letter to P. Duke RAI Regarding Entergy Operations, Inc.'S Decommissioning Funding Plan Update for Salem and Hope Creek, and Peach Bottom ISFSIs Docket Nos. 72-48 and 72-29) ML18067A1482018-03-0808 March 2018 Enclosurequest for Additional Information (Letter to P. R. Simpson Request for Additional Information Regarding Exelon Generating Company, Llc'S Decommissioning Funding Plan Update for Independent Spent Fuel Storage Installation) ML17212B1152017-07-31031 July 2017 Request for Additional Information - Salem Units 1 and 2 - Containment Fan Coil Unit Allowed Outage Time Amendment Request (CACs MF9364 and MF9365) ML17199A1122017-07-18018 July 2017 Request for Additional Information - Salem Units 1 and 2 - Accident Monitoring Instrumentation License Amendment Request (CAC Nos. MF8859 & MF8860) ML17192A1672017-07-11011 July 2017 Request for Additional Information - Salem Unit 1 - Steam Generator Tube Inspection Report ML17115A4032017-05-0909 May 2017 Request for Additional Information Regarding Relief Request SC-14R-171 - Use of Code Cases N-695-1 and N-696-1 ML16321A4642016-11-21021 November 2016 and Salem Nuclear Generating Station, Unit Nos. 1 and 2 - Request for Additional Information Regarding License Amendment Request to Remove Certain Training Requirements ML16218A0052016-08-11011 August 2016 Request for Additional Information Concerning Request for an Extension to Enforcement Guidance Memorandum 12-001 ML16195A4492016-07-14014 July 2016 Request for Additional Information Regarding Chilled Water System Modifications ML16188A4152016-07-0707 July 2016 Request for Additional Information Aging Management Program Plan for Reactor Vessel Internals ML16124A5802016-05-0303 May 2016 and Salem Nuclear Generating Station, Unit Nos. 1 and 2 - Redacted - Request for Additional Information Review of Security Plan Revision 17 Changes ML16013A1592016-02-17017 February 2016 Request for Additional Information Regarding Chilled Water System Modifications ML15287A1412015-11-0202 November 2015 Request for Additional Information License Amendment Request Regarding Replacement of Source Range and Intermediate Range Neutron Monitoring Systems ML15287A1052015-11-0202 November 2015 Request for Additional Information License Amendment Request to Isolate Unborated Water Sources and Use Gamma-Metrics Post-Accident Neutron Monitors During Mode 6 (Refueling) (CAC Nos. MF5831 & MF5832) ML15299A3832015-10-29029 October 2015 Supplemental Information Needed for Acceptance of Requested Licensing Action Amendment Request Regarding Chilled Water System Modification ML15069A1812015-03-31031 March 2015 Request for Additional Information Aging Management Program Plan for Reactor Vessel Internals (TAC Nos. MF5149 and MF5150) ML15075A2602015-03-24024 March 2015 Request for Additional Information Spring 2014 Steam Generator Tube Inspections ML15055A3772015-03-10010 March 2015 and Salem Nuclear Generating Station, Unit Nos. 1 and 2, Request for Additional Information Request to Update Appendix B to Renewed Facility Operating License DPR-70, DPR-75 and NPF-57 ML14197A6192014-07-24024 July 2014 and Salem Nuclear Generating Station, Units 1 and 2 - Request for Additional Information Regarding Cyber Security Plan Milestone 8 Implementation Schedule (Tac Nos. MF3384, MF3385 and MF3386) ML14168A2422014-06-28028 June 2014 Request for Additional Information Regarding Flooding Hazard Reevaluation ML14135A2912014-06-0202 June 2014 RAI Regarding Request for Relief SC-I4R-140 from American Society of Mechanical Engineers Boiler & Pressure Vessel Code, Section XI Requirements Regarding the Reactor Vessel Head Flange Seal Leak Detection ML14086A6362014-04-30030 April 2014 Request for Additional Information Regarding Core Operating Limits Report ML14066A2952014-03-0606 March 2014 Licensed Operator Positive Fitness-For-Duty-Test (FY14) ML13330A5672013-11-22022 November 2013 Request for Additional Information: Salem Units 1 and 2 - Relief Request SC-14R-133 Repair of Service Water Piping (TAC MF1375 & 1376) ML13304B4182013-11-0101 November 2013 Request for Additional Information Associated with Near-Term Task Force Recommendation 2.3, Seismic Walkdowns ML13304B9362013-10-29029 October 2013 Request for Additional Information: Salem Units 1 and 2 - Relief Request SC-14R-133 Repair of Service Water Piping (TAC MF1375 & 1376) ML13270A4142013-10-17017 October 2013 Interim Staff Evaluation and Request for Additional Information Regarding the Overall Integrated Plan for Implementation of Order EA-12-051, Reliable Spent Fuel Pool Instrumentation (TAC Nos. MF0913 and Mf ML13249A0112013-09-0505 September 2013 Weko Seal Relief Request RAI ML13196A3382013-07-15015 July 2013 2013 Decommissioning Fund Report RAI ML13192A2322013-07-11011 July 2013 Draft Request for Additional Information Overall Integrated Plan in Response to Order EA-12-051, Reliable Spent Fuel Pool Instrumentation. ML13186A1672013-07-11011 July 2013 Request for Additional Information Overall Integrated Plan for Reliable Spent Fuel Pool Instrumentation (Order Number EA-12-051) ML13179A3032013-06-28028 June 2013 RAIs for Salem Regarding Response to Order EA-12-051 (SFP Instrumentation) ML13137A4882013-06-0505 June 2013 Request for Additional Information Relief Request SC-l4R-133 ML13149A0862013-06-0505 June 2013 Request for Additional Information Decommissioning Funding Status Report ML13102A2752013-04-25025 April 2013 Request for Additional Information Change to PSEG Emergency Plan to Remove the Backup R45 Plant Vent Radiation Monitor Indications ML13063A7172013-03-11011 March 2013 Second Request for Additional Information Deletion of Condition for Inoperable Control Area Air Condition System/Control Room Emergency Air Conditioning System Isolation Dampers 2022-02-22
[Table view] |
Text
July 16, 2004 Mr. A. Christopher Bakken, III President & Chief Nuclear Officer PSEG Nuclear, LLC - X04 Post Office Box 236 Hancocks Bridge, NJ 08038
SUBJECT:
SALEM NUCLEAR GENERATING STATION, UNIT NOS. 1 AND 2, REQUEST FOR ADDITIONAL INFORMATION RE: REQUEST FOR CHANGE TO TECHNICAL SPECIFICATIONS - RELAXATION OF REQUIREMENTS APPLICABLE DURING MOVEMENT OF IRRADIATED FUEL (TAC NOS.
MB5710 AND MB5711)
Dear Mr. Bakken:
By letter dated July 29, 2002, PSEG Nuclear, LLC (PSEG) submitted a request for changes to the Salem Nuclear Generating Station, Unit Nos. 1 and 2, Technical Specifications (TSs). The proposed changes would allow relaxation of Containment Integrity and Containment and Control Room Ventilation requirements during the movement of irradiated fuel. By letter dated March 18, 2003, the U.S. Nuclear Regulatory Commission (NRC) forwarded a request for additional information (RAI) to PSEG in order to complete its review. By letter dated March 28, 2003 PSEG submitted a Correction of Information changing the X/Q factor for exclusion area boundary and to change the fuel decay time. By letter dated May 1, 2003, PSEG submitted its response to the questions in the NRCs March 18, 2003, letter.
The NRC staff is reviewing your request and RAI response, and has determined that additional information is necessary in order to complete its evaluation. On June 14, 2004, the NRC faxed the enclosed RAIs to PSEG in preparation for a conference call. Review of the RAI would allow PSEG to identify areas where clarification is needed as well as determine a schedule within which a response can be provided. In a subsequent phone call, PSEG stated that no further clarifications of the RAI questions are necessary and, hence, a conference call was not held.
Please provide your response to the enclosed questions within 30 days of receipt of this letter.
Meeting this target date is essential to timely completion of the NRCs review of this application.
Sincerely,
/RA/
Daniel Collins, Project Manager, Section 2 Project Directorate I Division of Licensing Project Management Office of Nuclear Reactor Regulation Docket Nos. 50-272 and 50-311
Enclosure:
As stated cc w/encl: See next page
July 16, 2004 Mr. A. Christopher Bakken, III President & Chief Nuclear Officer PSEG Nuclear, LLC - X04 Post Office Box 236 Hancocks Bridge, NJ 08038
SUBJECT:
SALEM NUCLEAR GENERATING STATION, UNIT NOS. 1 AND 2, REQUEST FOR ADDITIONAL INFORMATION RE: REQUEST FOR CHANGE TO TECHNICAL SPECIFICATIONS - RELAXATION OF REQUIREMENTS APPLICABLE DURING MOVEMENT OF IRRADIATED FUEL (TAC NOS.
MB5710 AND MB5711)
Dear Mr. Bakken:
By letter dated July 29, 2002, PSEG Nuclear, LLC (PSEG) submitted a request for changes to the Salem Nuclear Generating Station, Unit Nos. 1 and 2, Technical Specifications (TSs). The proposed changes would allow relaxation of Containment Integrity and Containment and Control Room Ventilation requirements during the movement of irradiated fuel. By letter dated March 18, 2003, the U.S. Nuclear Regulatory Commission (NRC) forwarded a request for additional information (RAI) to PSEG in order to complete its review. By letter dated March 28, 2003 PSEG submitted a Correction of Information changing the X/Q factor for exclusion area boundary and to change the fuel decay time. By letter dated May 1, 2003, PSEG submitted its response to the questions in the NRCs March 18, 2003, letter.
The NRC staff is reviewing your request and RAI response, and has determined that additional information is necessary in order to complete its evaluation. On June 14, 2004, the NRC faxed the enclosed RAIs to PSEG in preparation for a conference call. Review of the RAI would allow PSEG to identify areas where clarification is needed as well as determine a schedule within which a response can be provided. In a subsequent phone call, PSEG stated that no further clarifications of the RAI questions are necessary and, hence, a conference call was not held.
Please provide your response to the enclosed questions within 30 days of receipt of this letter.
Meeting this target date is essential to timely completion of the NRCs review of this application.
Sincerely,
/RA/
Daniel Collins, Project Manager, Section 2 Project Directorate I Division of Licensing Project Management Office of Nuclear Reactor Regulation Docket Nos. 50-272 and 50-311
Enclosure:
As stated cc w/encl: See next page DISTRIBUTION PUBLIC PDI-2 Reading JClifford RDenning GMeyer, RGN-I ACRS OGC DCollins RTaylor CRaynor ADAMS Accession Number: ML041890168 OFFICE PDI-1 PDI-2/PM PDI-2/SC NAME Dcollins for JHardy DCollins JClifford DATE 7/15/04 7/15/04 7/15/04 OFFICIAL RECORD COPY
Salem Nuclear Generating Station, Unit Nos. 1 and 2 cc:
Mr. Michael H. Brothers Dr. Jill Lipoti, Asst. Director Vice President - Site Operations Radiation Protection Programs PSEG Nuclear - X15 NJ Department of Environmental P.O. Box 236 Protection and Energy Hancocks Bridge, NJ 08038 CN 415 Trenton, NJ 08625-0415 Mr. John T. Carlin Vice President - Nuclear Assessments Brian Beam PSEG Nuclear - N10 Board of Public Utilities P.O. Box 236 2 Gateway Center, Tenth Floor Hancocks Bridge, NJ 08038 Newark, NJ 07102 Mr. David F. Garchow Regional Administrator, Region I Vice President - Eng/Tech Support U.S. Nuclear Regulatory Commission PSEG Nuclear - N28 475 Allendale Road P.O. Box 236 King of Prussia, PA 19406 Hancocks Bridge, NJ 08038 Senior Resident Inspector Mr. Steven Mannon Salem Nuclear Generating Station Acting Manager - Licensing U.S. Nuclear Regulatory Commission PSEG Nuclear - N21 Drawer 0509 P.O. Box 236 Hancocks Bridge, NJ 08038 Hancocks Bridge, NJ 08038 Mr. Carl J. Fricker Jeffrie J. Keenan, Esquire Plant Manager PSEG Nuclear - N21 PSEG Nuclear - N21 P.O. Box 236 P.O. Box 236 Hancocks Bridge, NJ 08038 Hancocks Bridge, NJ 08038 Ms. R. A. Kankus Joint Owner Affairs PECO Energy Company Nuclear Group Headquarters KSA1-E 200 Exelon Way Kennett Square, PA 19348 Lower Alloways Creek Township c/o Mary O. Henderson, Clerk Municipal Building, P.O. Box 157 Hancocks Bridge, NJ 08038
REQUEST FOR ADDITIONAL INFORMATION REQUEST FOR CHANGES TO TECHNICAL SPECIFICATIONS - RELAXATION OF REQUIREMENTS APPLICABLE DURING MOVEMENT OF IRRADIATED FUEL SALEM NUCLEAR GENERATING STATION, UNIT NOS. 1 AND 2 By letter dated July 29, 2002, PSEG Nuclear (the licensee) submitted a proposed amendment to the Technical Specifications for Salem Nuclear Generating Station, Units 1 and 2. The proposed amendment would revise the Technical Specifications based on a re-analysis of the design basis Fuel Handling Accident (FHA).
The Nuclear Regulatory Commission (NRC) staff has reviewed the information the licensee provided that supports the proposed Technical Specification changes. In order for the staff to complete its evaluation, the following additional information is requested:
- 1. The proposed Technical Specification change proposes changing the definition of CORE ALTERATIONS. As a result of the proposed change the applicability section of several technical specifications are proposed to be changed. The applicability is changed from: "During CORE ALTERATIONS or movement of irradiated fuel within the containment" to "During movement of irradiated fuel within the containment."
IN 90-77, "Inadvertent Removal of Fuel Assemblies from the Reactor Core," discusses events during removal of upper guide structures and upper internals. During these events fuel assemblies were inadvertently removed from the reactor creating the high potential for a fuel handling accident.
A review of the Salem licensing bases in UFSAR Section 15.4.6.11 does not specify how the spent fuel assembly is dropped inside of containment.
CORE ALTERATIONS, as presently defined in the Technical Specifications, is the movement or manipulation of any component within the reactor pressure vessel with the vessel head removed and fuel in the vessel. This definition would bound inadvertent movement of a single fuel assembly.
The combination of the proposed change in the definition of CORE ALTERATIONS and applicability statements appear to not bound the known potential for inadvertent movement of fuel assemblies. In light of these considerations please justify why the proposed technical specification change should not include applicability for a fuel handling accident occurring during the movement of other core components 1
The Salem UFSAR Section 15.4.6.1 states:
"The accident is defined as dropping of a spent fuel assembly onto the spent fuel pit floor in the fuel handling building or inside containment resulting in the rupture of the cladding of all the fuel rods in the assembly despite many administrative controls and physical limitations imposed on fuel handling operations. All refueling operations are conducted in accordance with prescribed procedures under direct surveillance of a supervisor."
Enclosure
.2. Proposed Technical Specification 3.9.4 proposes the following: "The equipment hatch inside door is capable of being closed and held in place by a minimum of four bolts, or an equivalent closure device installed and capable of being closed." Please define what criteria are used to determine whether a device is an equivalent closure device to the equipment hatch. Please define the devices to be used.
- 3. The staff has reviewed Salems May 1, 2003 response (LR-N03-0136) to the staffs request for additional information related to the proposed license amendment. The response to question 5 does not appear to be responsive to the staff s question.
Please describe the outage activities that could prevent the establishment of fuel handling building closure and the compensatory actions that would need to be taken.
It would also be helpful for the staff to understand that in the event of a fuel handling accident that the fuel building would be closed promptly (or within a reasonable time frame) to limit the release of radioactivity.
- 4. Per page 6 of the July 29, 2002 amendment request, the ability to close the Salem equipment hatch is dependent on AC power. In the case of a loss of AC power coincident with a fuel handling accident, electrical power may not be available for closing the hatch. Please explain what measures are in place to promptly close the equipment hatch without AC power. NUREG-14492 also states that with four bolts installed that the Salem equipment hatch had gaps between the equipment hatch seals. How many bolts will be needed to close the equipment hatch to prevent the release of radioactivity?
- 5. The proposed amendment requires the Containment Purge or the Auxiliary Building Ventilation System with suction from the containment atmosphere to be available during fuel movement. Closure controls are in place for the personnel airlock and the containment equipment hatch along with a definition for closure time (defined as 1 hour1.157407e-5 days <br />2.777778e-4 hours <br />1.653439e-6 weeks <br />3.805e-7 months <br />). The flows out the Containment Purge or the Auxiliary Building Ventilation Systems are forced flow pathways and will likely release a much greater amount of radioactivity than either the containment equipment hatch or personnel airlock after a fuel handling accident. No provisions are made to close these dominant flow paths whereas time limiting provisions are made for closing the personnel airlock and the containment equipment hatch. Please explain why there are no defense-in-depth measures taken promptly to secure the Containment Purge or the Auxiliary Building Ventilation Systems after a fuel handling accident.
- 6. Provide the criterion used to decide if the containment personnel airlock and the containment equipment hatch are capable of being closed within 1 hour1.157407e-5 days <br />2.777778e-4 hours <br />1.653439e-6 weeks <br />3.805e-7 months <br />.
- 7. What criteria will be used to determine if closure of the containment is necessary in the event of adverse weather? Has the impact of wind on fuel handling been evaluated (for example, reduced pool visibility due to pool surface disruption)? What steps would be taken in the event of severe weather to minimize the impact of flying debris or missile hazards?
2 NUREG-1449, "Shutdown and Low-Power Operation at Commercial Nuclear Power Plants in the United States," page B-5.
- 8. Will your Emergency Plan be updated to include an accident release through the equipment hatch? Will your Emergency Operating Procedures be updated to address the specific details needed to respond to this accident scenario?
- 9. Will you inform the State Emergency Response personnel about this accident scenario?
- 10. The proposed technical specification specifies that a "designated" crew is available to close the Containment Structure Equipment Hatch Shield Doors rather than a "dedicated" crew who would have no other duties. Specify what other duties the designated crew will have and where they will be stationed relative to the air lock doors.