Text

SAFEGUARDS INFORMATION June 25, 2004 Mr. Daniel J. Malone Site Vice President Nuclear Management Company, LLC 27780 Blue Star Memorial Highway Covert, MI 49043-9530 c/o Mr. Bruce Rowland

SUBJECT:

PALISADES NUCLEAR PLANT - REQUEST FOR ADDITIONAL INFORMATION RE: SECURITY PLAN SECTIONS 1-9 (TAC NO. MC2949)

Dear Mr. Malone:

In response to the April 29, 2003, Orders revising the design basis threat, you submitted revised physical security plans, safeguards contingency plans, and guard training and qualification plans, including an implementation schedule, for Palisades Nuclear Plant.

The Nuclear Regulatory Commission staff is reviewing your submission and has determined that a request for additional information (RAI) is necessary in order to complete its evaluation based on its review of Sections 1 through 9 of your physical security plan. Please respond to the enclosed RAI within 10 days from the date of this letter. If circumstances result in the need to revise the target response date, please contact me at (301) 415-3308.

Sincerely,

/RA/

Bhalchandra Vaidya, Project Manager Security Plan Review Team Project Directorate II Division of Licensing Project Management Office of Nuclear Reactor Regulation Docket No. 50-255

Enclosure:

As stated cc w/o encl: See next page WARNING: Violation of Section 147 NOTICE: The enclosed information contains Safeguards of the Atomic Energy Act, Information. Upon separation from the enclosure, this Safeguards Information is subject to letter is DECONTROLLED.

Civil and Criminal Penalties SAFEGUARDS INFORMATION

June 25, 2004 Mr. Daniel J. Malone Site Vice President Nuclear Management Company, LLC 27780 Blue Star Memorial Highway Covert, MI 49043-9530 c/o Mr. Bruce Rowland

SUBJECT:

PALISADES NUCLEAR PLANT - REQUEST FOR ADDITIONAL INFORMATION RE: SECURITY PLAN SECTIONS 1-9 (TAC NO. MC2949)

Dear Mr. Malone:

In response to the April 29, 2003, Orders revising the design basis threat, you submitted revised physical security plans, safeguards contingency plans, and guard training and qualification plans, including an implementation schedule, for Palisades Nuclear Plant.

The Nuclear Regulatory Commission staff is reviewing your submission and has determined that a request for additional information (RAI) is necessary in order to complete its evaluation based on its review of Sections 1 through 9 of your physical security plan. Please respond to the enclosed RAI within 10 days from the date of this letter. If circumstances result in the need to revise the target response date, please contact me at (301) 415-3308.

Sincerely,

/RA/

Bhalchandra Vaidya, Project Manager Security Plan Review Team Project Directorate II Division of Licensing Project Management Office of Nuclear Reactor Regulation Docket No. 50-255

Enclosure:

As stated cc w/o encl: See next page DISTRIBUTION: PUBLIC SPRT R/F OGC ACRS ADAMS Accession Number: ML041800425 C:\ORPCheckout\FileNET\ML041800425.wpd OFFICE SPRT/NRR/PM SPRT/NSIR SPRT/NRR/SC NAME BVaidya JPeralta JNakoski DATE 6/25/04 6/25/04 6/25/04 OFFICIAL RECORD COPY

Palisades Plant cc:

Robert A. Fenech, Senior Vice President Michigan Department of Attorney General Nuclear, Fossil, and Hydro Operations Special Litigation Division Consumers Energy Company 525 West Ottawa St.

1945 Parnall Rd. Sixth Floor, G. Mennen Williams Building Jackson, MI 49201 Lansing, MI 48913 Arunas T. Udrys, Esquire Manager, Regulatory Affairs Consumers Energy Company Nuclear Management Company, LLC 1 Energy Plaza 27780 Blue Star Memorial Highway Jackson, MI 49201 Covert, MI 49043 Regional Administrator, Region III Director of Nuclear Assets U.S. Nuclear Regulatory Commission Consumers Energy Company 801 Warrenville Road Palisades Nuclear Plant Lisle, IL 60532-4351 27780 Blue Star Memorial Highway Covert, MI 49043 Supervisor Covert Township John Paul Cowan P. O. Box 35 Executive Vice President & Chief Nuclear Covert, MI 49043 Officer Nuclear Management Company, LLC Office of the Governor 700 First Street P. O. Box 30013 Hudson, WI 54016 Lansing, MI 48909 Jonathan Rogoff, Esquire U.S. Nuclear Regulatory Commission Vice President, Counsel & Secretary Resident Inspectors Office Nuclear Management Company, LLC Palisades Plant 700 First Street 27782 Blue Star Memorial Highway Hudson, WI 54016 Covert, MI 49043 Douglas E. Cooper Michigan Department of Environmental Quality Senior Vice President - Group Operations Waste and Hazardous Materials Division Palisades Nuclear Plant Hazardous Waste and Radiological Nuclear Management Company, LLC Protection Section 27780 Blue Star Memorial Highway Nuclear Facilities Unit Covert, MI 49043 Constitution Hall, Lower-Level North 525 West Allegan Street Daniel J. Malone P.O. Box 30241 Site Vice President Lansing, MI 48909-7741 Palisades Nuclear Plant Nuclear Management Company, LLC 27780 Blue Star Memorial Highway Covert, MI 49043