RAI, Generic Letter 88-20
ML041740429
Person / Time
Site: Browns Ferry Tennessee Valley Authority icon.png
Issue date: 06/21/2004
From: Jabbour K
NRC/NRR/DLPM/LPD2
To: Singer K
Tennessee Valley Authority
Jabbour K, NRR/DLPM, 415-1496
References
GL-88-020, TAC MC1895
Download: ML041740429 (4)


Text

June 21, 2004 Mr. Karl W. Singer Chief Nuclear Officer and Executive Vice President Tennessee Valley Authority 6A Lookout Place 1101 Market Street Chattanooga, TN 37402-2801

SUBJECT:

BROWNS FERRY NUCLEAR PLANT, UNIT 1 REQUEST FOR ADDITIONAL INFORMATION RELATED TO GENERIC LETTER 88-20, INDIVIDUAL PLANT EXAMINATION FOR SEVERE ACCIDENT VULNERABILITY (TAC NO. MC1895)

Dear Mr. Singer:

As a follow-up to the February 27, 2004, meeting between the U.S. Nuclear Regulatory Commission (NRC) staff and the Tennessee Valley Authority representatives, the NRC staff committed to providing you a letter identifying the specific information needed for the closeout of Generic Letter 88-20 for Browns Ferry Unit 1. This information is included in the enclosure to this letter.

The NRC staff finds that a response to the enclosed request for additional information is needed before we can complete the review. This request was discussed with Mr. T. Abney of your staff on June 2, 2004, and it was agreed that a response, under oath and affirmation, would be provided within 60 days of receipt of this letter. If you have any questions, please contact me at (301) 415-1496.

Sincerely,

/RA/

Kahtan N. Jabbour, Senior Project Manager, Section 2 Project Directorate II Division of Licensing Project Management Office of Nuclear Reactor Regulation Docket No. 50-259

Enclosure:

Request for Additional Information cc w/encl: See next page

ML041740429 OFFICE PDII-2 / PM PDII-2 / LA RES/PRAB/SC SPSB /SC PDII-2 / SC(A)

NAME KJabbour BClayton MDrouin MRubin WBurton DATE 6/8/04 6/8/04 6/18/04 6/18/04 6/21/04

REQUEST FOR ADDITIONAL INFORMATION RELATED TO GENERIC LETTER 88-20 TENNESSEE VALLEY AUTHORITY BROWN FERRY NUCLEAR PLANT, UNIT 1 DOCKET NO. 50-259 1.

Please discuss in detail how the individual plant examination (IPE)/probabilistic risk assessment (PRA) performed for Brown Ferry Plant (BFN), Unit 1, will properly reflect the units anticipated configuration at commercial operation. Please provide the version designation or date of the current Unit 1 IPE/PRA, the total estimated core damage frequency, and the large early release frequency.

2.

Based on the results of the Unit 1 IPE/PRA, please discuss the specific vulnerabilities to severe accidents which are identified, if any, for BFN Unit 1. Also, please identify and discuss the proposed plant improvements, such as design changes and changes to operating procedures, maintenance, surveillance, training or staffing, resulting from the IPE/PRA.

3.

Please discuss any methods and processes used in BFN Unit 1 IPE/PRA but not used in the BFN Units 2 and 3 IPE/PRA, that would potentially affect the results (e.g., mask a vulnerability).

4.

Please list and discuss the weaknesses and deficiencies identified by the staff in the staff evaluation reports and the Nuclear Regulatory Commission contractors Technical Evaluation Report for the BFN Units 2 and 3 IPE/PRA dated September 28, 1994, and May 4, 1999, respectively. In addition please identify all Units 2 and 3 peer review facts and observations that were judged by the peer review team to be necessary to address (Significance level A and B in NEI 00-02, Industry PRA Review Guidance).

Please describe how the weakness, deficiencies, and significant peer review observations have been resolved in the current Unit 1 IPE/PRA.

Mr. Karl W. Singer BROWNS FERRY NUCLEAR PLANT Tennessee Valley Authority cc:

Mr. Ashok S. Bhatnagar, Senior Vice President Nuclear Operations Tennessee Valley Authority 6A Lookout Place 1101 Market Street Chattanooga, TN 37402-2801 Mr. James E. Maddox, Vice President Engineering & Technical Services Tennessee Valley Authority 6A Lookout Place 1101 Market Street Chattanooga, TN 37402-2801 Site Vice President Browns Ferry Nuclear Plant Tennessee Valley Authority P.O. Box 2000 Decatur, AL 35609 General Counsel Tennessee Valley Authority ET 11A 400 West Summit Hill Drive Knoxville, TN 37902 Mr. T. J. Niessen, Acting General Manager Nuclear Assurance Tennessee Valley Authority 6A Lookout Place 1101 Market Street Chattanooga, TN 37402-2801 Mr. Michael D. Skaggs, Plant Manager Browns Ferry Nuclear Plant Tennessee Valley Authority P.O. Box 2000 Decatur, AL 35609 Mr. Jon R. Rupert, Vice President Browns Ferry Unit 1 Restart Browns Ferry Nuclear Plant Tennessee Valley Authority P.O. Box 2000 Decatur, AL 35609 Mr. Robert G. Jones Browns Ferry Unit 1 Plant Restart Manager Browns Ferry Nuclear Plant Tennessee Valley Authority P.O. Box 2000 Decatur, AL 35609 Mr. Mark J. Burzynski, Manager Nuclear Licensing Tennessee Valley Authority 4X Blue Ridge 1101 Market Street Chattanooga, TN 37402-2801 Mr. Timothy E. Abney, Manager Licensing and Industry Affairs Browns Ferry Nuclear Plant Tennessee Valley Authority P.O. Box 2000 Decatur, AL 35609 Senior Resident Inspector U.S. Nuclear Regulatory Commission Browns Ferry Nuclear Plant 10833 Shaw Road Athens, AL 35611 State Health Officer Alabama Dept. of Public Health RSA Tower - Administration Suite 1552 P.O. Box 303017 Montgomery, AL 36130-3017 Chairman Limestone County Commission 310 West Washington Street Athens, AL 35611