Letter Sequence Approval |
---|
|
|
MONTHYEARML0401501832004-01-21021 January 2004 Request for Additional Information for Proposed Amendment Re Turbine Building Service Water Header Isolation Logic Project stage: RAI ML0408505472004-03-17017 March 2004 Response to RAI Related to License Amendment Request 197 to Kewaunee Technical Specifications Project stage: Response to RAI ML0414801582004-05-18018 May 2004 Response to Request for Additional Information Related to License Amendment Request 197 to the Kewaunee Nuclear Power Plant Technical Specifications Project stage: Response to RAI ML0423904602004-08-18018 August 2004 Response to Request for Additional Information Related to License Amendment Request 197 to the Kewaunee Nuclear Power Plant Technical Specifications Project stage: Response to RAI ML0427300902004-09-24024 September 2004 Technical Specification Pages for Amendment No. 177 Turbine Building Service Water Header Isolation (TS) S110810 Project stage: Other ML0416100952004-09-24024 September 2004 Issuance of Amendment No. 177 Re. Revision of TS 3.3.e, Service Water System Project stage: Approval 2004-05-18
[Table View] |
|
---|
Category:Letter
MONTHYEARML23339A1332024-01-26026 January 2024 Exemption from the Req of 10 CFR Part 50.82(a)(8)(i)(A) to Use the Kewaunee Decommissioning Trust Fund for the Management of Site Restoration Activities IR 05000305/20230022023-12-27027 December 2023 NRC Inspection Report 05000305/2023002 (Drss); 07200064/2023001 (Drss) ML23332A1922023-11-28028 November 2023 Solutions, Inc., Request for Exemptions from Enhanced Weapons, Firearms Background Checks, and Security Event Notifications Implementation ML23278A1002023-10-0505 October 2023 Response to Request for Additional Information (RAI) Application for Kewaunee Solutions (Ks) Site Restoration Activities ML23222A1522023-08-29029 August 2023 Letter RAI KPS Exemption Site Restoration Final Repaired IR 05000305/20230012023-08-17017 August 2023 NRC Inspection Report No. 05000305/2023001-Kewaunee Power Station ML23171B0822023-07-0505 July 2023 Letter - Kewaunee Power Station - Issuance of Exemption from Certain Requirements from 10 CFR Part 20, Appendix G, Section Iii.E ML23132A0012023-05-11011 May 2023 2022 Annual Radiological Environmental Operating Report ML23116A2182023-04-26026 April 2023 2022 Annual Radioactive Effluent Release Report ML23089A3042023-03-30030 March 2023 Decommissioning Fund Status Report ML23088A2752023-03-29029 March 2023 Solutions, Inc., Request for Exemption from 10 CFR 20, Appendix G, Section Iii.E ML23093A0312023-03-29029 March 2023 Solutions, Inc., Request for Exemptions from 10 CFR 50.82(a)(8)(i)(A) and 50.75(h)(1)(iv) for Site Restoration Activities ML23087A0402023-03-27027 March 2023 Annual Property Insurance Status Report ML23087A0292023-03-27027 March 2023 2022 Annual Report of Occupational Radiation Exposure ML22361A1022023-02-24024 February 2023 Reactor Decommissioning Branch Project Management Changes for Some Decommissioning Facilities and Establishment of Backup Project Manager for All Decommissioning Facilities ML23024A0122023-01-26026 January 2023 Letter to Energysolutions Transmitting Threshold Determination for Merger/Restructuring IR 05000305/20220022023-01-0303 January 2023 NRC Inspection Report Nos. 05000305/2022002(DRSS) Kewaunee Power Station ML22292A2302022-11-25025 November 2022 U.S. Nuclear Regulatory Commissions Analysis of Dominion Energy Kewaunees Decommissioning Funding Status Report for Kewaunee Power Station, Docket No. 50-305 ML22290A0052022-10-13013 October 2022 Resubmittal of Kewaunee Power Station Independent Spent Fuel Storage Installation (ISFSI) Only Emergency Plan (Ioep) and IOEP- Emergency Action Level (EAL) Basis Document, Revision 0KS ML22241A0302022-08-25025 August 2022 (Ksp) ISFSI Submittal of Security Plan, Training and Qualification Plan and Safeguards Contingency Plan, Revision 5 IR 05000305/20220012022-08-0101 August 2022 NRC Inspection Report Nos. 05000305/2022001(DNMS) - Kewaunee Power Station ML22215A1512022-07-27027 July 2022 Executed Financial Assurance Instruments for the Kewaunee License Transfer License No. DPR-43 (Docket Nos. 50-305, 72-64) ML22209A1252022-07-26026 July 2022 Amendment No. 11 to Indemnity Agreement No. B-53 for Kewaunee Power Station (KPS) - Signed by Kewaunee Solutions, Inc ML22175A1132022-06-30030 June 2022 Solutions, Inc. - Letter for Review and Acceptance of the Energysolutions, LLC Decommissioning Quality Assurance Program with Enclosure ML22160A5272022-06-28028 June 2022 Enclosure 1 - Amendment No. 221 to Renewed Facility Operating License No. DPR-43 ML22160A5282022-06-28028 June 2022 Enclosure 2 - Amendment No. 11 to Indemnity Agreement B-53 ML22160A5262022-06-28028 June 2022 Letter - KPS - Issuance of Conforming License Amendment Regarding Indirect Transfer of License from DEK, Inc. to Kewaunee Solutions, Inc ML22188A0812022-06-23023 June 2022 ISFSI, Virgil C. Summer Nuclear Station, Unit 1 & ISFSI, North Anna Power Station, Units 1 & 2 & ISFSI, Surry Power Station, Units 1 & 2 & ISFSI - Submission of Revision 32 of the Quality Assurance Topical Report ML22172A2452022-06-22022 June 2022 Notification of Planned Closing Date and Required Regulatory Approvals for the Kewaunee License Transfer Transaction ML22175A0662022-06-17017 June 2022 Designation of Additional Reviewing Official for ISFSI and 10 CFR Part 37 Program Security Background Investigations ML22166A3392022-06-13013 June 2022 Notification of Nuclear Insurance ML22138A2552022-05-10010 May 2022 Submittal of 2021 Annual Radiological Environmental Operating Report ML22158A2112022-05-10010 May 2022 Summary of Facility Changes, Tests and Experiments and Summary of Commitment Changes ML22108A0352022-04-0101 April 2022 License Transfer to Kewaunee Solutions, Inc ML22091A1892022-04-0101 April 2022 Independent Spent Fuel Storage Installation - Annual Radioactive Effluent Release Report ML22089A2432022-03-30030 March 2022 Decommissioning Funding Status Report, Financial Test and Independent Public Accountants' Letter of Attestation ML22076A0652022-03-15015 March 2022 Energy Solutions and Dominion Energy Kewaunee - Supplement to License Transfer Application Related to Use of Existing Dominion Energy Quality Assurance Program ML22060A1912022-02-25025 February 2022 Response to Request for Additional Information Related to Submittal for Approval of the Kewaunee Solutions Decommissioning Quality Assurance Program (Dqap), Revision O for Kewaunee Power Station (KPS) ML22066A4982022-02-24024 February 2022 Nuclear Property Insurance Coverage ML22047A0572022-02-16016 February 2022 Supplement to License Transfer Application Related to Decommissioning Quality Assurance Program ML22032A3242022-02-0202 February 2022 Letter to C. Sly, Dominion, from B. Watson, NRC - Dominion Energy Kewaunee, Inc. - RAI Regarding Energysolutions Submittal for Approving Decommissioning Quality Assurance Program IR 05000305/20210012021-12-27027 December 2021 NRC Inspection Report Nos. 05000305/2021001 (Dnms); 07200064/2021001 (DNMS) ML21351A4352021-12-19019 December 2021 U.S. Nuclear Regulatory Commission'S Analysis of Dominion Energy Kewaunee, Inc.'S Decommissioning Funding Status Report for Kewaunee Power Station, Docket No. 50-305 ML21355A2972021-12-14014 December 2021 ISFSI, 10 CFR 72.30 Decommissioning Funding Plan ML21309A0152021-11-0909 November 2021 Acceptance Review of Dominion Energy Kewaunee, Inc. - Energysolutions Submittal for Approving Decommissioning Quality Assurance Program (EPID L-2021-DP3-0000) ML21301A1782021-10-28028 October 2021 Response to Request for Additional Information Regarding Application for Order Approving Transfer of Control of Kewaunee Power Station License and Conforming License ML21294A3652021-10-21021 October 2021 Changes to Decommissioning Trust Agreement ML21288A5572021-10-18018 October 2021 Energysolutions Submittal for Approving Decommissioning Quality Assurance Program (EPID L-2021-DP3-0000) ML21257A0682021-09-30030 September 2021 Request for Additional Information Regarding Application for Order Approving Transfer of Control of Kewaunee Power Station License and Conforming License Amendments ML21277A2462021-09-29029 September 2021 Resubmittal of Solutions Decommissioning Quality Assurance Program (Dqap), Revision 0 2024-01-26
[Table view] Category:License-Operating (New/Renewal/Amendments) DKT 50
MONTHYEARML17123A0282017-06-0707 June 2017 Enclosure 1 - KPS Amendment 220 Regarding Permanent Removal of Spent Fuel for the Spent Fuel Pool - LAR260 ML17052A5912017-05-0909 May 2017 KPS Amendment 219 - Removal of Cyber Security Requirements for Operating License ML16341C7912017-03-0202 March 2017 Enclosure 1 - Amendment to Facility Operating License ML16320A0442016-11-30030 November 2016 Amendment No. 217 ML15245A4822015-10-0707 October 2015 Millstone Power Station, Surry Power Station, and North Anna Power Station - Issuance of Amendments to Revise the Cyber Security Milestone 8 Completion Date in the Renewed Facility Operating Licenses ML14237A0452015-02-13013 February 2015 Issuance of Amendment No. 215, Revise Operating License and Technical Specifications to the Permanently Defueled Technical Specifications Consistent with Permanent Cessation of Reactor Operation ML14008A2972014-06-23023 June 2014 Issuance of Amendment No. 213 - Deletion of License Conditions Associated with Extended Operations ML14111A2342014-06-0909 June 2014 Issuance of Amendment No. 212 Revise Operating License and Technical Specifications to the Permanently Defueled Technical Specifications Consistent with Permanent Cessation of Reactor Operation ML11192A2492011-08-31031 August 2011 Issuance of Amendment Regarding Cyber Security to Dominion Plants ML11102A0272011-07-29029 July 2011 Issuance of Amendment License Amendment Request to Change the Current Licensing Basis for Automatic Operation of Transformer Load Tap Changers ML1110105232011-04-29029 April 2011 Issuance of Amendment 208 Regarding Technical Specification Change Regarding Reactor Vessel Heatup and Cooldown Curves and Low Temperature Overpressure Protection for 52.1 Effective Full Power Years ML0530403522011-02-24024 February 2011 Current Facility Operating License DPR-43, Tech Specs, Revised 10/07/2015 ML1101006002011-02-24024 February 2011 Renewed License ML1101005752011-02-24024 February 2011 Issuance of Renewed Facility Operating License No. DPR-043 for Kewaunee Power Station ML1033706912011-02-0202 February 2011 Part 080 ME2139 List of Acronyms and Abbreviations ML1020206622011-02-0202 February 2011 Issuance of Amendment for Conversion to Improved Technical Specifications with Beyond Scope Issues ML1002110292009-08-0303 August 2009 2009 Kewaunee Power Station Retake Examination Proposed Exam Files ML0912710592009-06-0101 June 2009 License Amendment No. 206, Containment Purge and Vent Isolation Valves Surveillance Requirement ML0905707102009-04-30030 April 2009 Issuance of Amendment No. 205 Seismic Analysis Methodology for the Auxiliary Building Crane ML0905708922009-04-27027 April 2009 Issuance of Amendment No. 204 Re. One-time Extension of the 15-Year Containment Integrated Leak Rate Test Interval ML0902805812009-02-0606 February 2009 Issuance of Amendment No. 203 Regarding Diesel Generator Fuel Storage Tank Capacity Requirement ML0833607832009-01-0909 January 2009 Issuance of Amendment Steam Line Isolation Function Applicability (Tac No. MD8544) ML0832906532008-12-30030 December 2008 License Amendment, Issuance of Amendment No. 201 Shield Building and Auxiliary Building Special Ventilation Train Filter Heater Requirements ML0829710792008-11-20020 November 2008 Issuance of Amendment to Relocate Spent Fuel Pool Crane Requirements from the Technical Specifications to the Technical Requirements Manual ML0829405472008-11-0606 November 2008 License Amendment, Increased the Minimum Required Safety Injection Accumulator Boron Concentration from 1900 parts-per-million (Ppm) to 2400 Ppm ML0816201402008-07-0202 July 2008 Issuance of Amendment Deletion of License Condition on Fuel Burnup ML0804603632008-03-28028 March 2008 Issuance of Amendment Regarding Nuclear Instrumentation System Permissive Setpoints ML0807701792008-03-28028 March 2008 Issuance of Amendments Licensing Basis Design Criteria Associated with Internal Flooding ML0728802892007-10-31031 October 2007 License Amendment Regarding Relocation of Technical Specifications Requirements ML0721300932007-08-0202 August 2007 Revised Pages of Facility Operating License No. DPR-43 ML0711100062007-05-18018 May 2007 Issuance of Amendment Refueling Water Storage Tank Boron Concentration ML0712001862007-05-0101 May 2007 Issuance of License Amendment 191 Regarding Emergency Diesel Generator Rated Load Testing ML0704300202007-03-0808 March 2007 Radiological Accident Analysis ML0631800362006-12-14014 December 2006 License Amendment 189 Regarding Referencing the American Society of Mechanical Engineers Boiler and Pressure Vessel Code for Operation and Maintenance of Nuclear Power Plants ML0617002082006-07-17017 July 2006 Issuance of Amendment Steam Generator Tube Integrity ML0616402862006-07-12012 July 2006 Issuance of Amendment Surveillance Interval Extension ML0532100822005-11-18018 November 2005 Correction to Amendment 186 ML0521504282005-10-0404 October 2005 Issuance of License Amendment 186 Regarding Technical Specification Changes for Radioactive Effluents Control Program and Off-Site Dose Calculation Manual ML0518801062005-07-0505 July 2005 Issuance of Conforming Amendment Re Transfer of Facility Operating License from Nuclear Management Company, Wisconsin Public Service Corp and Wisconsin Power and Light Company to Dominion Energy Kewaunee, Inc ML0517100302005-06-21021 June 2005 Emergency License Amendment, Revises the TSs to Remove the Requirement to Have a Containment Spray Pump Suction Flow Path from the Containment Sump ML0516000912005-06-20020 June 2005 Issuance of Amendment Auxiliary Feedwater System ML0503902742005-04-0606 April 2005 Issuance of License Amendment 182 Relocation of Surveillance Requirements ML0505407072005-03-24024 March 2005 License Amendment, Revised Technical Specification Rod Position Indication ML0435001062005-02-15015 February 2005 Issuance of License Amendment 180 Administrative Changes to Technical Specifications ML0433800022004-12-22022 December 2004 Issuance of Amendment Deletion of Requirements for Submittal of Occupational Radiation Exposure Reports, Reports of Challenges to and Failures of the Pressurizer Power Operated Relief Valves and Safety Valves ML0431200302004-10-29029 October 2004 Administrative Change to Facility Operating License in Conjunction with the Commission Order EA-03-086 Regarding Revised Design Basis Threat... ML0514402972004-10-26026 October 2004 Revision to Emergency Action Levels, Facility Operating License as Amended Through October 21, 2004 Document ML0426400982004-10-0505 October 2004 License Amendment, Revises TS 3.3.a.2.B, by Extending Completion Time from 1 Hour to 24 Hours for an Accumulator That Is Inoperable for Any Reason Other than Failure to Meet Minimum Boron Concentration Requirements ML0416100952004-09-24024 September 2004 Issuance of Amendment No. 177 Re. Revision of TS 3.3.e, Service Water System ML0422300682004-09-22022 September 2004 License Amendment No. 176, Revise TS 3.10.f.2 to Add an Allowed Outage Time for the Individual Rod Position Indication (Irpi) System of 24 Hours with More than One Irpi Group Inoperable & Adds the Definition of Immediately to TS Section 1.0 2017-06-07
[Table view] Category:Safety Evaluation
MONTHYEARML23339A1362024-01-26026 January 2024 Safety Evaluation Re NRC Issuance of Exemption for Site Restoration ML23024A0122023-01-26026 January 2023 Letter to Energysolutions Transmitting Threshold Determination for Merger/Restructuring ML22175A1132022-06-30030 June 2022 Solutions, Inc. - Letter for Review and Acceptance of the Energysolutions, LLC Decommissioning Quality Assurance Program with Enclosure ML18225A0202018-08-29029 August 2018 ISFSI; North Anna 1 & 2 Isfsls, and Unit 3; Surry Power 1 & 2, and Isfsls); Dominion Energy Kewaunee, Inc. (Kewaunee Power Station and Isfsi): Request for Threshold Determination Under 10 CFR 50.80 ML17332A0782017-12-12012 December 2017 ISFSI; Millstone and ISFSI; North Anna and ISFSI; Surry and ISFSI - Request for Approval of Revision 24 of the Nuclear Facility Quality Assurance Program Description Topical Report, DOM-QA-1 (CAC Nos. MF9732-MF9739; EPID L-2017-LLQ-0001) ML17123A0292017-06-0707 June 2017 Enclosure 2 - Safety Evaluation Report Related to the Unloaded Spent Fuel Pool at KPS - LAR260 ML17046A3162017-04-0606 April 2017 Connecticut, Virginia, Millstone, North Anna, Surry, Submission of Revision 21 of the Quality Assurance Topical Report for NRC Approval and Submission Revision 22 for Information Only (CAC Nos. MF8128 - MF8234) ML15245A4822015-10-0707 October 2015 Millstone Power Station, Surry Power Station, and North Anna Power Station - Issuance of Amendments to Revise the Cyber Security Milestone 8 Completion Date in the Renewed Facility Operating Licenses ML14237A0452015-02-13013 February 2015 Issuance of Amendment No. 215, Revise Operating License and Technical Specifications to the Permanently Defueled Technical Specifications Consistent with Permanent Cessation of Reactor Operation ML14279A4822014-10-31031 October 2014 Issuance of Amendment, No. 214 Revise Permanently Defueled Emergency Plan and Emergency Action Level Scheme ML14261A2232014-10-27027 October 2014 Letter and Safety Evaluation, Exemptions from Emergency Planning Requirements of 10 CFR 50.47 and 10 CFR 50 Appendix E ML14008A2972014-06-23023 June 2014 Issuance of Amendment No. 213 - Deletion of License Conditions Associated with Extended Operations ML14111A2342014-06-0909 June 2014 Issuance of Amendment No. 212 Revise Operating License and Technical Specifications to the Permanently Defueled Technical Specifications Consistent with Permanent Cessation of Reactor Operation ML14104A0462014-05-12012 May 2014 Approval of Certified Fuel Handler Training Program ML12271A3662012-10-0404 October 2012 Relief Request Number RR-2-4 Regarding Fourth 10-Year Interval Inservice Inspection Program ML12249A4412012-09-20020 September 2012 Evaluation of Relief Request Number RR-G-5 Regarding Fourth 10-Year Interval Inservice Inspection Program ML1200505532012-02-17017 February 2012 Millstone Power Station Units 2 and 3, North Anna Power Station, Units 1 and 2, Surry Power Station Units 1 and 2 - Review of Dominion Fleet Quality Assurance Topical Report, Revision 11 ML11271A1782011-10-0303 October 2011 Review of Topical Report, Revision 11 for Kewaunee Power Station and ISFSI, Millstone Power Station, Units 1, 2, & 3 and ISFSI, North Anna Power Station, Units 1 & 2 and ISFSI, Surry Power Station, Units 1 & 2 and ISFSI (Tac ME6649, ME6650, ML11192A2492011-08-31031 August 2011 Issuance of Amendment Regarding Cyber Security to Dominion Plants ML11102A0272011-07-29029 July 2011 Issuance of Amendment License Amendment Request to Change the Current Licensing Basis for Automatic Operation of Transformer Load Tap Changers ML1110105232011-04-29029 April 2011 Issuance of Amendment 208 Regarding Technical Specification Change Regarding Reactor Vessel Heatup and Cooldown Curves and Low Temperature Overpressure Protection for 52.1 Effective Full Power Years ML1033605042011-02-0202 February 2011 Part 002 ME2139 Safety Evaluation and Safety Evaluation Attachments ML1020206622011-02-0202 February 2011 Issuance of Amendment for Conversion to Improved Technical Specifications with Beyond Scope Issues ML1019701932010-08-22022 August 2010 Approval of Revision to Previously Approved IST Relief Request VRR-5 ML1016200342010-06-21021 June 2010 Approval to Remove Mixing Vane Grid Restriction in Appendix B of Dominion Fleet Topical Report DOM-NAF-2-A ML0934106522009-12-22022 December 2009 Authorization of Proposed Alternative RR-1-11 Regarding Visual Examinations for Reactor Pressure Vessel Bottom-Mounted Instrument Penetrations ML0923210792009-09-28028 September 2009 Irradiated Fuel Management Program and Preliminary Decommissioning Cost Estimate ML0905707102009-04-30030 April 2009 Issuance of Amendment No. 205 Seismic Analysis Methodology for the Auxiliary Building Crane ML0905708922009-04-27027 April 2009 Issuance of Amendment No. 204 Re. One-time Extension of the 15-Year Containment Integrated Leak Rate Test Interval ML0902805812009-02-0606 February 2009 Issuance of Amendment No. 203 Regarding Diesel Generator Fuel Storage Tank Capacity Requirement ML0833607832009-01-0909 January 2009 Issuance of Amendment Steam Line Isolation Function Applicability (Tac No. MD8544) ML0829710792008-11-20020 November 2008 Issuance of Amendment to Relocate Spent Fuel Pool Crane Requirements from the Technical Specifications to the Technical Requirements Manual ML0829405472008-11-0606 November 2008 License Amendment, Increased the Minimum Required Safety Injection Accumulator Boron Concentration from 1900 parts-per-million (Ppm) to 2400 Ppm ML0816201402008-07-0202 July 2008 Issuance of Amendment Deletion of License Condition on Fuel Burnup ML0814902822008-05-20020 May 2008 Submittal of Approved Topical Report DOM-NAF-5, Revision 0.0-A, Application of Dominion Nuclear Core Design and Safety Analysis Methods to the Kewaunee Power Station (KPS) ML0807701792008-03-28028 March 2008 Issuance of Amendments Licensing Basis Design Criteria Associated with Internal Flooding ML0804603632008-03-28028 March 2008 Issuance of Amendment Regarding Nuclear Instrumentation System Permissive Setpoints ML0806305402008-03-28028 March 2008 Issuance of License Amendment 196 Nuclear Core Design and Safety Analysis Methods ML0801604122008-02-0707 February 2008 Issuance of Amendment Regarding Emergency Diesel Generator Testing ML0728802892007-10-31031 October 2007 License Amendment Regarding Relocation of Technical Specifications Requirements ML0722903732007-08-30030 August 2007 Safety Evaluation for Topical Report DOM-NAF-5 ML0721102772007-08-14014 August 2007 Reactor Vessel Surveillance Capsule Test Results for Capsule T ML0721200032007-08-0202 August 2007 Conforming License Amendment to Incorporate the Mitigation Strategies Required by Section B.5.b. of Commission Order EA-02-026 Tac No. MD4543) ML0711100062007-05-18018 May 2007 Issuance of Amendment Refueling Water Storage Tank Boron Concentration ML0712001862007-05-0101 May 2007 Issuance of License Amendment 191 Regarding Emergency Diesel Generator Rated Load Testing ML0704300202007-03-0808 March 2007 Radiological Accident Analysis ML0631800362006-12-14014 December 2006 License Amendment 189 Regarding Referencing the American Society of Mechanical Engineers Boiler and Pressure Vessel Code for Operation and Maintenance of Nuclear Power Plants ML0624205112006-08-30030 August 2006 Approval of Topical Report DOM-NAF-3 ML0617002082006-07-17017 July 2006 Issuance of Amendment Steam Generator Tube Integrity ML0616402862006-07-12012 July 2006 Issuance of Amendment Surveillance Interval Extension 2024-01-26
[Table view] |
Text
September 24, 2004 Mr. Thomas Coutu Site Vice President Kewaunee Nuclear Power Plant Nuclear Management Company, LLC N490 Highway 42 Kewaunee, WI 54216-9511
SUBJECT:
KEWAUNEE NUCLEAR POWER PLANT - ISSUANCE OF AMENDMENT RE: TURBINE BUILDING SERVICE WATER HEADER ISOLATION (TAC NO. MB9944)
Dear Mr. Coutu:
The U.S. Nuclear Regulatory Commission has issued the enclosed Amendment No. 177 to Facility Operating License No. DPR-43 for the Kewaunee Nuclear Power Plant. This amendment revises the Technical Specifications (TSs) in response to your application dated July 7, 2003, as supplemented March 17, May 18, and August 18, 2004.
The amendment revises TS Section 3.3.e, Service Water System, to add requirements for the turbine building service water header isolation logic.
A copy of the Safety Evaluation is also enclosed. The Notice of Issuance will be included in the Commission's next regular biweekly Federal Register notice.
Sincerely,
/RA/
Carl F. Lyon, Project Manager, Section 1 Project Directorate III Division of Licensing Project Management Office of Nuclear Reactor Regulation Docket No. 50-305
Enclosures:
- 1. Amendment No. 177 to License No. DPR-43
- 2. Safety Evaluation cc w/encls: See next page
ML041610095 *No significant changes to SE NRR-058 OFFICE PDIII-1/PM PDIII-1/LA SPLB/SC EEIB/SC IROB/SC OGC PDIII-1/SC NAME FLyon THarris DSolorio* EMarinos* TBoyce RWeisman LRaghavan DATE 08/25/04 08/25/04 5/5/04 6/4/04 09/03/04 09/23/04 09/23/04 Kewaunee Nuclear Power Plant cc:
John Paul Cowan David Zellner Executive Vice President & Chairman - Town of Carlton Chief Nuclear Officer N2164 County B Nuclear Management Company, LLC Kewaunee, WI 54216 700 First Street Hudson, MI 54016 Mr. Jeffery Kitsembel Electric Division Plant Manager Public Service Commission of Wisconsin Kewaunee Nuclear Power Plant PO Box 7854 N490 Highway 42 Madison, WI 53707-7854 Kewaunee, WI 54216-9511 Manager, Regulatory Affairs Kewaunee Nuclear Power Plant N490 Highway 42 Kewaunee, WI 54216-9511 David Molzahn Nuclear Asset Manager Wisconsin Public Service Corporation 600 N. Adams Street Green Bay, WI 54307-9002 Resident Inspectors Office U. S. Nuclear Regulatory Commission N490 Highway 42 Kewaunee, WI 54216-9510 Regional Administrator, Region III U. S. Nuclear Regulatory Commission 2443 Warrenville Road, Suite 210 Lisle, IL 60532-4351 Jonathan Rogoff Vice President, Counsel & Secretary Nuclear Management Company, LLC 700 First Street Hudson, WI 54016 Larry L. Weyers Chairman, President and CEO Wisconsin Public Service Corporation 600 North Adams Street Green Bay, WI 54307-9002
NUCLEAR MANAGEMENT COMPANY, LLC DOCKET NO. 50-305 KEWAUNEE NUCLEAR POWER PLANT AMENDMENT TO FACILITY OPERATING LICENSE Amendment No. 177 License No. DPR-43
- 1. The U.S. Nuclear Regulatory Commission (the Commission) has found that:
A. The application for amendment by Nuclear Management Company, LLC (NMC),
dated July 7, 2003, as supplemented March 17, May 18, and August 18, 2004, complies with the standards and requirements of the Atomic Energy Act of 1954, as amended (the Act), and the Commissions rules and regulations set forth in 10 CFR Chapter I; B. The facility will operate in conformity with the application, the provisions of the Act, and the rules and regulations of the Commission; C. There is reasonable assurance (i) that the activities authorized by this amendment can be conducted without endangering the health and safety of the public, and (ii) that such activities will be conducted in compliance with the Commissions regulations; D. The issuance of this amendment will not be inimical to the common defense and security or to the health and safety of the public; and E. The issuance of this amendment is in accordance with 10 CFR Part 51 of the Commissions regulations and all applicable requirements have been satisfied.
- 2. Accordingly, the license is amended by changes to the Technical Specifications as indicated in the attachment to this license amendment, and paragraph 2.C.(2) of Facility Operating License No. DPR-43 is hereby amended to read as follows:
(2) Technical Specifications The Technical Specifications contained in Appendix A, as revised through Amendment No. 177, are hereby incorporated in the license. The licensees shall operate the facility in accordance with the Technical Specifications.
- 3. This license amendment is effective as of its date of issuance and shall be implemented within 60 days of the date of issuance.
FOR THE NUCLEAR REGULATORY COMMISSION
/RA/
L. Raghavan, Chief, Section 1 Project Directorate III Division of Licensing Project Management Office of Nuclear Reactor Regulation
Attachment:
Changes to the Technical Specifications Date of Issuance: September 24, 2004
ATTACHMENT TO LICENSE AMENDMENT NO. 177 FACILITY OPERATING LICENSE NO. DPR-43 DOCKET NO. 50-305 Replace the following pages of the Appendix A Technical Specifications with the attached revised pages. The revised pages are identified by amendment number and contain marginal lines indicating the areas of change.
REMOVE INSERT TS 3.3-7 TS 3.3-7 TS Table 4.1-1 (Page 7 of 7) TS Table 4.1-1 (Page 7 of 7)
The following marked-up TS Bases page is provided for information only.
TS B3.3-4
SAFETY EVALUATION BY THE OFFICE OF NUCLEAR REACTOR REGULATION RELATING TO AMENDMENT NO. 177 TO FACILITY OPERATING LICENSE NO. DPR-43 NUCLEAR MANAGEMENT COMPANY, LLC KEWAUNEE NUCLEAR POWER PLANT DOCKET NO. 50-305
1.0 INTRODUCTION
By application to the U.S. Nuclear Regulatory Commission (NRC) July 7, 2003 (ADAMS Accession No. ML031980490), as supplemented by letters dated March 17 (ML040850547),
May 18, 2004 (ML041480158), and August 18, 2004 (ML042390460), Nuclear Management Company, LLC (NMC, or the licensee) requested changes to Technical Specification (TS) 3.3.e, Service Water System, for the Kewaunee Nuclear Power Plant (Kewaunee). The proposed changes include operability requirements for the non-essential service water (SW) header isolation valves, the associated valve isolation logic, and surveillance requirements.
The licensee stated that its analysis demonstrated that SW flow to the non-safety related turbine building SW header might be exceeded under some postulated accident conditions, and the subsequent decrease of SW flow to the safety-related components could impact the ability to remove design-basis heat loads from safety-related components. As provided in the original SW system design, however, operators had the ability to isolate the turbine building SW supply through remote manually controlled isolation valves SW-4A or 4B. The proposed changes to the TSs establish operability requirements for the turbine building service water header isolation valves and the associated isolation logic which will automatically close the isolation valves upon receipt of a safety injection signal concurrent with a low-pressure signal in the respective SW header. The licensee also proposes to add a surveillance requirement to ensure that design capabilities are maintained and tested.
The supplements, dated March 17, May 18, and August 18, 2004, provided additional information that clarified the application, did not expand the scope of the application as originally noticed, and did not change the NRC staffs original proposed no significant hazards consideration determination as published in the Federal Register on August 5, 2003 (68 FR 46244).
Specifically, the proposed changes would add TS Section 3.3.e.1.A.3, as follows.
A. TWO service water trains are OPERABLE with each train consisting of:
- 3. An OPERABLE turbine building service water header isolation valve and associated isolation logic capable of closing the header isolation valve, or a closed and deactivated turbine building service water header isolation valve.
The proposed changes also add a surveillance requirement to Table TS 4.1-1 to calibrate and test the SW turbine header isolation logic trip each refueling cycle.
2.0 REGULATORY EVALUATION
The regulatory requirements on which the NRC staff based its review of the licensees proposed changes to the TSs are in Title 10 of the Code of Federal Regulations (10 CFR),
Section 50.55a(h), Protection and safety systems. Specifically, 10 CFR 50.55a(h)(2) provides requirements for protection systems for nuclear power plants and references Institute of Electrical and Electronics Engineers (IEEE) Standard 279, Criteria for Protection Systems for Nuclear Power Generating Stations, as an optional standard. IEEE 279-1968 is the licensing basis for Kewaunee protection systems.
The staff also considered (1) NRC standard practice with respect to Allowed Outage Times (AOTs) for TS LCOs, as reflected in NUREG-1431, Standard Technical Specifications Westinghouse Plants, and (2) the current plant licensing basis as reflected in Section 9.6.2 of the Kewaunee Updated Safety Analysis Report (USAR), Service Water System. USAR Section 9.6.2 states that automatic isolation actuates on a train basis to maintain cooling as long as possible to the non-safety features equipment.
3.0 TECHNICAL EVALUATION
3.1 Background
The SW System at Kewaunee was designed to provide redundant cooling water supplies to the following safety-related components: the containment fan coil units, diesel generators, air compressors, component cooling heat enchanters, safety injection pump stuffing boxes and/or coolers, and control room air conditioners. Cooling water for some non-essential and non-redundant coolers and equipment is also supplied from the SW headers. The original design includes the provision for remote manual isolation of non-essential loads following an accident. Two electric motor-driven SW pumps are connected to a SW Header A and two are connected to SW Header B. The headers are connected by normally-open valves SW-3A and 3B. A safety injection signal or a SW low-pressure signal will close redundant valves SW-3A and 3B. Once this occurs, the SW headers will become independent and redundant.
Two of the SW pumps serving one header receive power from one 4160V safety-feature bus, and the other two SW pumps serving the other header receive power from a separate safety-feature bus. Each header has an isolation valve (SW-4A or 4B) to isolate SW to non-essential turbine building loads. Only one header is connected to the turbine building non-essential components at a time. Both headers need to have protection against excess turbine building SW header pressure demand, because it cannot be predicted which header would be aligned to the non-essential loads at the start of an accident.
While conducting SW system testing during the 2001 refueling outage, the licensee discovered the potential for higher-than-expected non-safety related turbine building SW demand during
some postulated accident conditions. The increased turbine building SW flow, and subsequent decreased safety-related SW flow, could impact the ability of the safety-related SW flow to remove the design basis heat loads from safety-related components. The original design of the SW system provided for remote manual operation of isolation valves from the control room, which could be used to isolate the SW flow to the non-safety related turbine building components. However, the licensee determined that automatic isolation was necessary to assure adequate SW flow to safety-related components under postulated accident conditions.
The licensee initiated Design Change Request (DCR)-3338 under 10 CFR 50.59 to install actuation circuitry to automatically close the turbine building non-essential SW supply by actuating the respective isolation valve SW-4A or SW-4B upon initiation of a safety injection signal concurrent with a low SW header pressure.
3.2 Evaluation The licensee proposes to add TS 3.3.e.1.A.3 to establish operability requirements for the non-essential turbine building service water header isolation valves and associated valve isolation logic, as well as surveillance requirements to ensure that design basis capabilities are maintained.
The automatic isolation of SW to non-essential load design provides independent and redundant closure signals to the SW-4 valves: A-train to SW-4A and B-train to SW-4B. The closure signals are developed from the safety injection sequence signal coincident with low SW header pressure on the corresponding A-train and B-train SW headers. The signal for SW isolation logic is at step 9 of the safety injection sequence. Step 9 is a later point in the safety injection sequence than the automatic start of both SW pumps. This is an appropriate step in the safety injection sequence because of the time necessary to establish header pressures with both pumps running on the respective header. Using low header pressure as the coincident signal is appropriate because it indicates that SW supply to the safety-related loads will not be adequate unless the SW supply to the non-essential load is isolated.
The licensee stated that it performed single-failure analysis for the control circuit to assess the impact of a failure on the safety-related portion of the service water system. The turbine building header can only be selected to one engineered safeguards header of service water at a time. Each safeguards service water header is capable of handling 100 percent of the post accident SW cooling needs. Since there can only be one safeguards header selected at any one time to provide turbine building header flow, there is no single failure that can cause both trains of engineered safeguards service water to be inoperable. Therefore, the design meets the single-failure criterion at the system level.
The staff evaluated the licensees proposed changes using IEEE 279-1968, which is part of the licensing basis for Kewaunee. DCR-3338 does not provide for a new plant protection system.
Instead, it uses the output from an existing protection system (safety injection actuation) in conjunction with low SW header pressure, to automatically isolate the non-safeguards SW header to assure that the safeguards SW flow and pressure assumed in the licensees accident analysis is provided for engineered safeguards SW loads. Since the isolation function is necessary to mitigate a design basis accident, the design of the isolation logic is required to meet the protection system design criteria required by 10 CFR 50.55a(h), which for Kewaunee is IEEE 279. In Enclosures 3, 4, and 5 to its letter dated March 17, 2004 (ML040850547), the
licensee addressed how DCR-3338 conformed to the 21 requirements of Section 4, Requirements, of IEEE 279-1968. The NRC staff reviewed DCR-3338 and the licensees assessment and, based on the licensees assessment, has determined that DCR-3338 conforms to IEEE 279-1968.
The addition of TS 3.3.e.1.A.3 will ensure the SW system is capable of supplying cooling water flow to the required safety-related components, under all conditions, by automatically isolating SW flow to the turbine building when necessary during a design-basis accident. The operators currently have the ability to isolate the turbine building service water supply through manual remote actuation of the non-essential service water header isolation valves, SW-4A and 4B.
This change to the TS will establish requirements for automatically closing the turbine building non-essential SW supply valves upon receipt of a safety injection signal coincident with a low-pressure signal in the respective non-essential SW header. Operability requirements that are specified in TS 3.3.e.1.A.3 maintain the functional capability of the SW system commensurate with the AOTs already established in the Kewaunee TSs for the SW system, consistent with NRC policy as reflected in the Westinghouse Standard Technical Specifications.
The operability of valves SW-4A and 4B is assured by existing TS 4.2, "ASME Code Class In-Service Inspection and Testing."
The licensee proposes to require calibration and testing of the SW turbine header isolation logic trip (SW 4A/B) each refueling cycle. The surveillance requirements are included as item no. 45 to Table TS 4.1-1, Minimum Frequencies for Checks, Calibrations and Test of Instrument Channels. The calibration and testing is consistent with that of other safety significant systems, such as the auxiliary feedwater pump low discharge pressure trip system and other safety injection system actuation circuit tests. Therefore, the NRC staff finds that the proposed TS change is acceptable.
The proposed addition of TS 3.3.e.1.A.3 is consistent with the Kewaunee licensing basis as discussed in USAR Section 9.6.2, maintains AOTs that are commensurate with NRC policy, and satisfies 10 CFR 50.55a(h) requirements. Therefore, the NRC staff finds that the proposed TS changes are acceptable.
The licensee proposed changes to the TS Bases consistent with the proposed changes to the TSs. The NRC staff has no objections to the proposed changes to the TS Bases.
3.3 Conclusion The NRC staff concludes, based on the evaluation discussed above, that the addition of TS 3.3.e.1.A.3 will ensure that the SW system is capable of supplying required safety-related components under all conditions, by automatically isolating SW flow to the turbine building when necessary in accordance with the plant licensing basis. Therefore, the staff finds the proposed TS changes to be acceptable.
4.0 STATE CONSULTATION
In accordance with the Commission's regulations, the Wisconsin State official was notified of the proposed issuance of the amendment. The State official had no comments.
5.0 ENVIRONMENTAL CONSIDERATION
This amendment changes a requirement with respect to installation or use of a facility component located within the restricted area as defined in 10 CFR Part 20 or changes a surveillance requirement. The NRC staff has determined that the amendment involves no significant increase in the amounts, and no significant change in the types, of any effluent that may be released offsite and that there is no significant increase in individual or cumulative occupational radiation exposure. The Commission has previously issued a proposed finding that this amendment involves no significant hazards consideration and there has been no public comment on such finding (68 FR 46244). Accordingly, this amendment meets the eligibility criteria for categorical exclusion set forth in 10 CFR 51.22(c)(9). Pursuant to 10 CFR 51.22(b) no environmental impact statement or environmental assessment need be prepared in connection with the issuance of this amendment.
6.0 CONCLUSION
The NRC staff has concluded, based on the considerations discussed above, that: (1) there is reasonable assurance that the health and safety of the public will not be endangered by operation in the proposed manner, (2) such activities will be conducted in compliance with the Commissions regulations, and (3) the issuance of this amendment will not be inimical to the common defense and security or to the health and safety of the public.
Principal Contributors: R. Reyes-Maldonado H. Li F. Lyon Date: September 24, 2004