Minutes of Internal Meeting of the Davis-Besse Oversight Panel
ML041400452
Person / Time
Site: Davis Besse Cleveland Electric icon.png
Issue date: 05/18/2004
From: Grobe J
NRC/RGN-III
To:
NRC/RGN-III
References
Download: ML041400452 (8)


Text

May 18, 2004 MEMORANDUM TO: Davis-Besse Oversight Panel FROM: John A. Grobe, Chairman, Davis-Besse Oversight Panel /RA/

SUBJECT:

MINUTES OF INTERNAL MEETING OF THE DAVIS-BESSE OVERSIGHT PANEL The implementation of the IMC 0350 process for the Davis-Besse Nuclear Power Station was announced on April 29, 2002. An internal panel meeting was held on January 15, 2004. Attached for your information are the minutes from the internal meeting of the Davis-Besse Oversight Panel, and the Open Action Items List.

Attachments: As stated cc w/att: D. Weaver, OEDO J. Caldwell, RIII G. Grant, RIII S. Reynolds, DRP B. Clayton, EICS DB0350

DOCUMENT NAME: C:\ORPCheckout\FileNET\ML041400452.wpd To receive a copy of this document, indicate in the box: "C" = Copy without attachment/enclosure "E" = Copy with attachment/enclosure "N" = No copy OFFICE RIII RIII RIII RIII NAME CLipa for CLipa for CLipa JGrobe RBaker/trn DPassehl DATE 05/18/04 05/18/04 05/18/04 05/18/04 OFFICIAL RECORD COPY

MEETING MINUTES: Internal IMC 0350 Oversight Panel Meeting Davis-Besse Nuclear Power Station DATE: January 15, 2004 TIME: 8:30 a.m. Central ATTENDEES:

J. Grobe W. Ruland S. Thomas C. Lipa A. Mendiola D. Hills D. Passehl R. Baker Agenda Items:

1. Discuss/Approve Todays Agenda The Panel approved the agenda, but modified the order of presentations. THE APPROVED AGENDA REFLECTS THE ORDER LISTED IN THESE MINUTES.
2. Discuss Plant Status and Inspector Insights and Emergent Issues List S. Thomas led a discussion of plant status and inspector insights and emergent issues.

The plant is in Mode 4 (temperature less than 280 degrees F). The licensee has completed repair of the pump casing steam leak on #1 Auxiliary Feedwater pump.

Overspeed testing is scheduled for today, January 15. The licensee will also perform work on #2 Auxiliary Feedwater pump to preclude a similar leakage problem developing on that pump. Work on both pumps is scheduled to be completed on January 17, 2004.

Following completion of the auxiliary feedwater pump work, the licensee intends to return to Mode 3 and heatup to normal operating temperature and pressure. Plant management will resume its observation and assessment of plant operations before requesting that the NRC schedule the followup restart readiness inspection.

Repair and testing continues on a small steam leak on a body-to-bonnet seal weld on valve RC1AB, the reactor coolant system loop 2 hot leg flow transmitter source valve.

3. Discuss New/Potential Licensing Issues J. Hopkins briefed the Panel on the status of licensing issues. The technical NRR staff reviewing the Steam Generator (SG) inspection license amendment request is drafting an RAI to send to the licensee. If the request is not approved, the licensee will be required to shutdown, if restarted, by March 9, 2004, and conduct the SG inspection.
4. Discuss Communication Status A. Mendiola briefed the Panel on the Communications status. The Restart Communication Plan has been reviewed by the Panel Chairman and is being reviewed by the Region III Public Affairs staff.

The Communications Team will hold a meeting next Wednesday, January 21, 2004, to review correspondence items, assign a tracking number to each, and recommend dispositioning for each item. The Communication Team Tracking Matrix will be updated with the results and presented to the Panel for review.

5. Panel Discussion on Providing DRAFT Restart Communication Plan to the Commission J. Grobe led a discussion on the action to present a DRAFT version of the Restart Communication Plan to the Commission. The plan will be attached to a memorandum from J. Grobe which clarifies sensitivity of the information contained in the DRAFT plan and that the plan will be revised as required based on the licensees completion of corrective actions and assessed readiness for restart. The DRAFT plan is due to the Commission by next Friday, January 23, 2004.

NEW ACTION ITEM (238) - A. MENDIOLA TO DRAFT A MEMO FROM JOHN GROBE TO CALDWELL, DYER, AND COLLINS TO ACCOMPANY AND DISCUSS SENSITIVITY OF INFORMATION IN DRAFT RESTART COMM PLAN. (Due Date:

01/21/04)

6. Brief Panel on CATI Report Review for Comments C. Lipa informed the Panel that the final draft CATI report is out for review and that comments are due back to P. Lougheed by tomorrow, 1/16/04.

J. Lara, C. Lipa, P. Lougheed, and Z. Falevits will meet next week to discuss issues involving the proposed Non-Cited Violations. One action will be to verify that the Significance Determination Process evaluation is complete for all issues characterized as minor and greater than minor. Another action is to resolve an action plan for moving forward with two issues that are still awaiting risk assessments from the licensee. Final significance determination is not possible without the information from the licensee. The specific issues are: 1) High Pressure Injection minimum recirculation flow, and

2) Containment Air Cooler fouling and performance.

Additionally, J. Grobe, J. Lara, C. Lipa, P. Lougheed, and Z. Falevits will meet next Tuesday, January 20, to conduct a final review of the licensee commitments listed in Revision 1 to the licensees Operational Improvement Plan and discuss the impact these have on the Confirmatory Order.

7. Update and Discussion on Licensees Plan to Revise/Update the Nov. 23 Integrated Readiness for Restart Report and Operational Improvement Plan C. Lipa led a discussion on whether or not the licensees Integrated Readiness to Support Restart report requires a revision. Some activities the licensee took credit for are now not being done, or have been changed. The Panel discussed having the

licensee issue an update or supplement to the report in place of a revision. Either way, the licensee needs to docket the changes. J. Grobe took an action to contact the licensee and request clarification on how they intend to address the issue.

8. Discuss Requirements/Action Items for Development of Presentation for Jim Caldwell/

Jim Dyer/Sam Collins A. Mendiola led a discussion of what actions are required to develop a Panel presentation for J. Caldwell, J. Dyer, and S. Collins. The major topics for the presentation will include a summary of completion of the Restart Checklist Items, Key messages from the Restart Communication Plan, fut ure inspection planning, and review of the Restart Recommendation Memorandum and Confirmatory Order. The presentation should also include a slide which captures the NRC efforts to date for interaction with the public. A. Mendiola and C. Lipa will finalize an action plan for other key required activities to support the presentation to discuss at a future Panel meeting.

9. Discuss Action Items C. Lipa led a review of the Open Action Items list. One new Action Item was added to the open action items list and one item was closed.

THE UPDATED OPEN ACTION ITEMS LIST IS ATTACHED TO THESE MINUTES.

10. Discuss Punch List C. Lipa led a review of the Punchlist. R. Baker took the action to update the Punchlist with the Panels comments.
11. Discuss/Update Milestones and Commitments The Panel reviewed and discussed upcoming milestones and commitments.

January 15, 2004 DAVIS-BESSE OVERSIGHT PANEL OPEN ACTION ITEM LIST Item Action Item Assigned to Comments Due Number (Date generated) Date 197 Develop a communication J. Stang 6/24-Lead changed; 08/21-Lead 02/02/04 plan with restart Qs and As. changed; 09/30-Discussed, list of Q &

(06/17) As is being gathered for review and forwarding to RA; 10/14-Discussed, J.

Shea is compiling the list of Q & As for review by the Panel and results will be forwarded to the RA; 10/21-Brainstorming session to occur 10/23 to final presentation to Panel; 11/20-The list of Q&As will be inserted to the Comm Matrix today; 12/15-Discussed, Plan with Panel Chairman; 12/30-Discussed, major rework in progress and plan will need to go back into concurrence.

208 Evaluate the need to call M. Phillips 10/14-Investigation is still ongoing; TBD back CI regarding Allegation 12/23-Discussed, awaiting DOJ RIII-2002-A-0177 (D-B) after Investigation.

the OI Investigation is complete (08/21) 212 Determine whether the J. Stang 10/14-Discussed, Set of bullets still 01/20/04 Communication Team has under development; item will be received all electronic and discussed at next Panel meeting on written correspondence from 10/16; 11/04 -Discussed, J. Stang is external sources. If there is adding to Comm. Matrix; 11/20-Only reasonable confidence that remaining is the documented criteria the Communication Team for proof of reasonable confidence; has all the correspondence 12/15-Discussed, all inputs received then develop a set of bullets from panel members-closure memo to explaining why there is document completeness confidence in reasonable confidence. draft and will go to Panel next week; (09/23) 12/30-Discussed, Bullets in review and NRR will forward to Region; 1/06-Discussed, List of Bullets in final review and will be disseminated 1/09/04.

219 Brief Jim Caldwell on how S. Thomas 10/28-Brief will include research 01/15/04 Immediate Action information on Exelon approach; Maintenance issue was 11/20-NRC is reviewing a copy of the resolved. He would like to licensees revised procedure; 12/15-see the revised procedure. Discussed, FENOC rep met with SRI (10/21) 12/14 to review new procedure; 12/18-Discussed, need to setup briefing for RA; 1/06-Discussed, brief will be given to Branch Chief with follow on briefing then setup for Jim Caldwell.

January 15, 2004 DAVIS-BESSE OVERSIGHT PANEL OPEN ACTION ITEM LIST Item Action Item Assigned to Comments Due Number (Date generated) Date 220 Develop inspection plan D. Passehl 11/20-The plan is being developed and 02/02/04 requirements which include supplemented from baseline review of post restart requirements; 12/15-Discussed, draft security program plan in final; 01/13-Discussed, decided effectiveness. (10/28) this action item refers to only security inspections 224 Rewrite the proposed IN on D. Hills 12/15-Discussed, D. Hills is working; 02/15/04 TSP to be generic and 12/23-Discussed, this issue will be reflect attainable plant discussed internally in RIII and brought conditions and what to Panel on 1/06/03 for a final decision information should be on how to proceed.

disseminated to the industry concerning Boric Acid Corrosion Control Programs. (12/09) 228 Place all Email requests M. Mitchell 1/06-Discussed, will verify ADAMS 01/23/04 sent throughout Agency, package is in place to support responses received, and collection of emails and responses-issue resolutions in ADAMS email requests will be resent due to package for documentation. small response to date.

(12/16) 231 As soon as the final RRATI D. Passehl 02/09/04 report is issued, Email a copy to Rick Jacobs at INPO.(12/19) 232 Track the status of the J. Stang 12/30-Discussed, J. Dyer briefed on 01/23/04 response to Gunter on Fire 12/29/03; J. Caldwell brief scheduled Protection Issues due for 12/31/03; 01/13-Discussed, due 01/16/04. (12/30) date extended until 01/16/04; 01/15-Discussed, the due date extended for final draft, by agreement with Region to 01/23/04.

234 Develop protocol paper for W. Ruland 01/15-Discussed, protocol paper being 01/16/04 NRC representative on DOJ drafted as a letter from Jim Caldwell to committee interface with Bruce Boger and includes criteria for 0350 Panel for updates. Immediate Action.

(01/06) 235 Advise panel on need for J. Jacobson 01/13-Discussed, will contact Jacobson 01/27/04 post-restart inspection, for when a brief will be provided to the based on review of our Panel.

Greenpeace 2.206 petition and the immediate action response letter we issued on Nov 26, 2003. (01/08)

January 15, 2004 DAVIS-BESSE OVERSIGHT PANEL OPEN ACTION ITEM LIST Item Action Item Assigned to Comments Due Number (Date generated) Date 236 Review the Dec 31, 2003 D. Passehl 01/22/04 revision of NRC Inspection Manual Chapter 0350 against current Panel Process Plan and brief Panel on results. (01/13) 237 Discuss with NRC Dept of J. Hopkins 01/15-Discussed, J. Hopkins discussed 01/16/04 Research personnel the with Research. The Panel decided this preliminary accident item is Closed.

sequence precursor program and/or NRC Dept of Research results. (01/13) 238 Draft a Memo from John A. Mendiola 01/21/04 (NEW Grobe to Caldwell, Dyer, ITEM) and Collins to accompany and discuss sensitivity of information in DRAFT Restart Comm Plan. (01/15)