Summary of Public Meeting to Discuss the Manual Chapter 0350 Process at the Davis-Besse Nuclear Power Station
ML041180174
Person / Time
Site: Davis Besse Cleveland Electric icon.png
Issue date: 04/23/2004
From: Christine Lipa
NRC/RGN-III/DRP/RPB4
To:
References
Download: ML041180174 (5)


Text

April 23, 2004 LICENSEE: FirstEnergy Nuclear Operating Company FACILITY: Davis-Besse Nuclear Power Station, Unit 1

SUBJECT:

SUMMARY

OF THE APRIL 8, 2004, PUBLIC MEETINGS TO DISCUSS LICENSEE PERFORMANCE AND PLANNED ACTIVITIES AS PART OF THE MANUAL CHAPTER 0350 PROCESS AT THE DAVIS-BESSE NUCLEAR POWER STATION On April 8, 2004, the Nuclear Regulatory Commission (NRC) held two public meetings at the Oak Harbor High School in Oak Harbor, Ohio. The first meeting was between the NRC Davis-Besse Oversight Panel and FirstEnergy Nuclear Operating Company (FENOC) to discuss licensee performance and planned activities as part of the Manual Chapter 0350 process at the Davis-Besse Nuclear Power Station. The letter of notification, meeting notice, NRC presentation, and licensee presentation can be found in ADAMS as ML040840626, ML040840628, ML041040069, and ML041050604, respectively. The transcript of the meeting will be made publicly available in ADAMS and on the NRCs Davis-Besse web page when it is available. A list of NRC and licensee meeting participants can be found in the attached Enclosure. This was the first public meeting held between the Oversight Panel and the licensee since restart of the facility was approved on March 8, 2004. Agenda topics included, milestones between restart approval and 100% reactor power, assessment of plant performance, highlights of the licensees Cycle 14 Operational Improvement Plan, and licensees plans to implement the Confirmatory Order.

The second meeting was between the NRC and members of the public. During the meeting, the NRC summarized the discussion from the earlier meeting between the NRC and FENOC and then provided time for public questions and comments. The meeting notice and NRC agenda can be found in ADAMS as ML040840629 and ML041040069, respectively.

These documents and many others related to the reactor vessel head degradation can also be found on the NRCs website at http://www.nrc.gov/reactors/operating/ops-experience/vessel-head-degradation.html.

/RA/

Christine A. Lipa, Chief Branch 4 Division of Reactor Projects Docket No. 50-346 License No. NPF-3

Enclosure:

As Stated See Attached Distribution

DOCUMENT NAME: C:\ORPCheckout\FileNET\ML041180174.wpd To receive a copy of this document, indicate in the box: "C" = Copy without attachment/enclosure "E" = Copy with attachment/enclosure "N" = No copy OFFICE RIII RIII NAME DPassehl/trn CLipa DATE 04/23/04 04/23/04 OFFICIAL RECORD COPY

FirstEnergy Nuclear Operating Company cc w/encl: The Honorable Dennis Kucinich G. Leidich, President - FENOC J. Hagan, Senior Vice President Engineering and Services, FENOC Plant Manager Manager - Regulatory Affairs M. OReilly, Attorney, FirstEnergy Ohio State Liaison Officer R. Owen, Administrator, Ohio Department of Health Public Utilities Commission of Ohio President, Board of County Commissioners of Lucas County C. Koebel, President, Ottawa County Board of Commissioners D. Lochbaum, Union Of Concerned Scientists J. Riccio, Greenpeace P. Gunter, N.I.R.S.

C. Emahiser, Ottawa County Sheriff J. P. Greer, Director, Ottawa County Emergency Management Agency H. Barlos, President, Lucas County Board of Commissioners J. Telb, Lucas County Sheriff B. Halsey, Director, Lucas County Emergency Management Agency G. Adams, Village Administrator, Genoa The Honorable John Weber The Honorable Lowell C. Krumnow The Honorable Joseph Verkin The Honorable Thomas Leaser The Honorable Jack Ford The Honorable Thomas Brown The Honorable Jacqueline Bird INPO

FirstEnergy Nuclear Operating Company ADAMS Distribution:

AJM DFT DWW Project Director, NRR Project Mgr., NRR RidsNrrDipmlipb JLC1 GEG HBC RML2 SRI Davis-Besse DRPIII DRSIII PLB1 JRK1 DB0350

Enclosure Meeting Participants NRC J. Grobe, Chairman, Davis-Besse Oversight Panel W. Ruland, Director, Project Directorate III C. Lipa, Projects Branch Chief, RIII J. Jacobson, Reactor Inspector, DRS, RIII C. Thomas, Senior Resident Inspector, Davis-Besse V. Mitlyng, Public Affairs, RIII FirstEnergy Nuclear Operating Company L. Myers, Chief Operating Officer M. Bezilla, Site Vice President C. Price, Manager, Business Services